Peerless Casualty Company v. United States

Decision Date27 February 1957
Docket NumberNo. 5142.,5142.
Citation241 F.2d 811
PartiesPEERLESS CASUALTY COMPANY et al., Defendants, Appellants, v. UNITED STATES of America, For the Use and Benefit of BANGOR ROOFING AND SHEET METAL CO., Plaintiff, Appellee.
CourtU.S. Court of Appeals — First Circuit

John W. Ballou, Bangor, Me., Mitchell & Ballou, Bangor, Me., on the brief, for appellants.

Seth May, Auburn, Me., for appellee.

Before MAGRUDER, Chief Judge, and WOODBURY and HARTIGAN, Circuit Judges.

HARTIGAN, Circuit Judge.

This is an appeal from a judgment entered by the United States District Court for the District of Maine on April 27, 1956, in an action brought by the United States of America, for the use and benefit of Bangor Roofing and Sheet Metal Company, under the Miller Act, 49 Stat. 793 (1935), 40 U.S.C.A. §§ 270a-270d, ordering that plaintiff-appellee recover of the defendants-appellants the sum of $8,185.89 plus interest and costs.

This case arises out of a subcontract, executed on August 17, 1950, between Bangor Roofing and Sheet Metal Company, the plaintiff-appellee, and T. W. Cunningham, Inc., one of the original defendants,1 which stemmed from the principal contract of August 16, 1950 between T. W. Cunningham, Inc. and the United States of America, providing for the construction of buildings and utilities at Caswell, Maine. The defendants-appellants, Peerless Casualty Company and General Reinsurance Corporation, are sureties for Cunningham on a payment bond "for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract," pursuant to 40 U.S.C.A. § 270a (a) (2).

The sole issue presented is whether the plaintiff's suit commenced by the filing of a complaint on September 25, 1953, was instituted within one year after the date of final settlement of the principal contract between Cunningham and the United States of America, as provided by 40 U.S.C.A. § 270b(b).

It is set forth in 40 U.S.C.A. § 270c that where final settlement of a contract has been made, a certified statement by the Comptroller General of the date of such settlement shall be conclusive as to such date upon the parties.2 In this case the Comptroller General certified August 28, 1952 as the date of final settlement. Since plaintiff instituted its suit approximately thirteen months after the certified settlement date, defendants made a motion for summary judgment which was denied by the district court in its opinion and order of October 28, 1955, stating that there was a genuine issue of material fact as to whether the date of final settlement, as certified by the Comptroller General, was supported by substantial evidence. Thereafter, the district court, with the consent of all the parties, held a hearing on the merits in order to ascertain the proper date of final settlement. The entire matter was submitted to the district court on various affidavits, exhibits and depositions.

The pertinent facts, as found by the district court, are as follows: The contract between Cunningham and the Government, which was to have been completed by April 5, 1951, was not fully performed until February 15, 1952. On December 27, 1951 the General Accounting Office sent a form questionnaire to the Corps of Engineers, United States Army, Office of the Division Engineer, in Boston, Massachusetts, hereafter referred to as the Division Office, for the purpose of ascertaining the facts from which the date of final settlement could be determined.

Before answering this questionnaire C. J. Murray, Chief of the Construction Division of the Division Office, on August 28, 1952 signed an office memorandum, addressed to the Chief of Legal Branch of the same office, which stated the account to date on the Cunningham contract, based on the contract and twelve change orders. The memorandum indicated a balance due the contractor, Cunningham, of $20,984.52 and an offsetting amount due the Government of $37,500 for liquidated damages for failure to complete the work on schedule, leaving a net amount due the Government of $16,515.48. On the basis of this memorandum, the Division Office in a letter dated August 29, 1952 recommended August 28, 1952 as the date of final settlement, explaining that on this date "the amount of the balance administratively found due the Government from the contractor under the contract was approved by C. J. Murray, Chief, Construction Division, New England Division, Corps of Engineers." (Emphasis in original.)

Subsequent to August 28, 1952 the Government reversed its previous position and waived its claim for liquidated damages by a modification to the contract whereby February 15, 1952, and not some other prior date, was accepted as the completion date of the Caswell Project. Accordingly, a new account was prepared and approved, which indicated a balance due the contractor, Cunningham, of $20,984.52.

The first manifestation of a change of attitude on the part of the Government was a letter, dated September 4, 1952, and signed by the contracting officer of the Division Office, informing Cunningham that the Caswell Project "has been accomplished in a satisfactory manner and is accepted as of February 15, 1952." A formal order, referred to as Change Order Thirteen, bearing the date of January 2, 1952 and establishing February 15, 1952 as the date of completion of the contract, was approved by the Chief Administrative Assistant to the contracting officer on September 17, 1952.

This order, expressly providing for acceptance by Cunningham, was received by Cunningham on September 24, 1952 and acceptance thereof was mailed on September 26, 1952 to the Division Office, arriving at the Division Office on September 29, 1952. On September 30, 1952 a final pay voucher, bearing that date, was executed, authorizing payment to Cunningham of $20,984.52, "as per estimate attached." The attached estimate, like the pay voucher, was designated "final" and both corresponded numerically — twentieth pay estimate and twentieth pay voucher, but the pay estimate was undated. The pay estimate recited that the contract completion date of February 15, 1952 was determined as per Change Order Thirteen and indicated that C. J. Murray had approved the account as the "Contracting Officer Representative." The pay voucher and the attached pay estimate were mailed on September 30, 1952 to Cunningham and, upon being properly signed by Cunningham, they were returned on October 3, 1952 to the Division Office. Payment was made to Cunningham on October 9, 1952.

The General Accounting Office was first requested to provide a certificate of the date of final settlement of the Caswell Project by one not a party to this action in the spring of 1953. Before determining the final settlement date, the General Accounting Office made further inquiry beyond its questionnaire of December 27, 1951 by means of a letter, dated July 28, 1953, in which it requested the Division Office to furnish a copy of "the document approved by C. J. Murray on August 28, 1952, together with any additional information which may be required to clarify the circumstances under which payment was made by the Government subsequent to a determination that a balance was due the Government."3

The Division Office, in its reply of August 4, 1953, rather than enclosing the August 28, 1952 memorandum, submitted a copy of the undated final pay estimate, the original of which had been attached to the final pay voucher of September 30, 1952, and mistakenly identified it as the document that was approved by C. J. Murray on August 28, 1952 in establishing "the amount of balance due the contractor from the Government as $20,984.52." (Emphasis in original.) The Division Office's reply of August 4, 1953 also stated that the letter "dated August 29, 1952, incorrectly indicated this amount to be due the Government from the contractor." (Emphasis added.)4

Apparently satisfied by this explanation and without further inquiry or other evidence, the General Accounting Office, on August 13, 1953, certified August 28, 1952 as the date of final settlement of the Caswell Project.

The plaintiff commenced suit by its complaint of September 25, 1953. Upon information received from Colonel Pattee of the Division Office in a telephone conversation, the plaintiff alleged in its complaint that September 30, 1952, was the date of final settlement. However, on October 6, 1953, the General Accounting Office issued a certificate to the plaintiff, specifying August 28, 1952, as the date of final settlement.

The August 28, 1952 memorandum, which the General Accounting Office had originally requested of the Division Office in hopes of clarifying the discrepancy between the pay voucher of September 30, 1952 (payment to the contractor) and the account stated as of August 28, 1952 (balance due the Government), was finally received by it on January 12, 1955.

The defendants by their answer admitted that the sum of $8,185.89 "remains due and unpaid" and set up the statute of limitations as a defense. The district court in granting recovery to the plaintiff held that plaintiff's action was instituted within one year after the date of final settlement of the contract. It did so by concluding that 40 U.S.C.A. § 270c, which provides that the date of final settlement as certified by the Comptroller General is conclusive upon the parties, was amended by a recent statute, 68 Stat. 81 (1954), 41 U.S.C.A. § 321, which reads as follows:

"§ 321. * * *
"No provision of any contract entered into by the United States, relating to the finality or conclusiveness of any decision of the head of any department or agency or his duly authorized representative or board in a dispute involving a question arising under such contract, shall be pleaded in
...

To continue reading

Request your trial
16 cases
  • United States Fidelity & Guar. Co. v. Hendry Corporation
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • June 20, 1968
    ...* * The plaintiff cannot claim as of right a broader review by the courts * * *" Peerless Casualty Co. v. United States for Use and Benefit of Bangor Roofing & Sheet Metal Co., 1 Cir. 1957, 241 F.2d 811, 817. See also United States for Use of Soda v. Montgomery, 3 Cir. 1959, 269 F.2d 752; G......
  • Golden West Construction Company v. United States, 6780.
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • July 2, 1962
    ...of the final settlement date was so erroneous as to imply bad faith. And see Peerless Casualty Company et al. v. United States for Use and Benefit of Bangor Roofing and Sheet Metal Company (1 C.A.), 241 F.2d 811; United States of America for Use of Soda v. Montgomery et al. (U.S.D.C.M.D.Pa.......
  • Frank v. Assessors of Skowhegan
    • United States
    • Maine Supreme Court
    • December 2, 1974
    ...and facts' where a confiscation of property or other violation of constitutional right is alleged. See: Peerless Casualty Company v. United States, 241 F.2d 811, 817 (1st Cir. 1957), holding except where Constitution otherwise requires, no broader right to judicial review of administrative ......
  • Northern California Power Agency v. Morton, Civ. A. No. 74-617.
    • United States
    • U.S. District Court — District of Columbia
    • February 14, 1975
    ...disputes clause in Government contracts," and given these holdings the Act is not here applicable. Peerless Casualty Co. v. United States, 241 F.2d 811, 816 (1st Cir. 1957); United States Fidelity & Guaranty Co. v. Hendry Corp., 391 F. 2d 13 (5th Cir. Due Process Accordingly, the due proces......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT