Pelham v. US, Civ. A. No. 84-1935.

Decision Date04 June 1987
Docket NumberCiv. A. No. 84-1935.
PartiesJerry and Phyllis PELHAM, Plaintiffs, v. UNITED STATES of America, et al., Defendants.
CourtU.S. District Court — District of New Jersey

COPYRIGHT MATERIAL OMITTED

Stephen R. Long, Shanley & Fisher, P.C., Morristown, N.J., for plaintiffs.

Ralph J. Marra, Jr., Asst. U.S. Atty., Newark, N.J., for defendants.

OPINION

HAROLD A. ACKERMAN, District Judge.

This personal injury action is brought by the plaintiffs, Jerry and Phyllis Pelham, against the United States, Allis Chalmers Corporation, Fairfield Tractor Company, Inc., L & H Construction Company ("L & H"), Catanzaro & Son Demolition Contractors, Ronald Davis, Ronald Davis Trucking Company, and four unidentified entities. It arises from conduct undertaken in 1982 on a construction and demolition project at the Picatinney Arsenal in Dover, New Jersey, a United States Army installation.

Defendant United States moves for reconsideration of my ruling of November 25, 1985 denying the government's motion to dismiss pursuant to Fed.R.Civ.P. 12(b)(1) or in the alternative, for summary judgment based on the discretionary function exception to the Federal Tort Claims Act (FTCA). Under rule 12 I of the local rules of this district, the court will reconsider its prior ruling if it determines that it overlooked dispositive factual matters or controlling decisions of law.

The government urges two grounds in support of reconsideration: (1) that the court erred in converting its rule 12(b)(1) motion to a motion for summary judgment, and (2) that recent Third Circuit precedent overrules the analysis employed by the court under the FTCA. Because the government argues that new law controls the motion here, I have reconsidered my prior decision. However, for the reasons discussed infra, the government's motion to dismiss is still denied.

STANDARD FOR VIEWING THE FACTS

Turning to the first ground, the government contends that the court incorrectly gave plaintiff the benefit of all favorable inferences when it is the plaintiff that has the burden of demonstrating jurisdiction. The government argues that without the benefit of factual inferences drawn in the plaintiff's favor, the court could not have found jurisdiction.

Reviewing the applicable law, I find that the government is correct in its contention that a motion for summary judgment is an improper vehicle for considering challenges to the subject matter jurisdiction of the court,1 notwithstanding that the government sought summary judgment as an alternative form of relief. When challenged by a defendant, the burden of demonstrating federal jurisdiction rests with the pleader. Tanzymore v. Bethlehem Steel Corp., 457 F.2d 1320, 1321 (3d Cir.1972). In considering a rule 12(b)(1) motion, the court must read the complaint liberally, taking all uncontroverted factual allegations in it as true. See Schuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974). The court may not be aided by presumptions or argumentative inferences drawn from the pleadings. Norton v. Larney, 266 U.S. 511, 515, 45 S.Ct. 145, 147, 69 L.Ed. 413 (1924). It necessarily follows then that the burden may not be switched and imposed on the movant when the basis for seeking judgment is a challenge to the jurisdiction of the court.

It was unnecessary for the court to convert the motion to one for summary judgment, however, for the court may properly look to affidavits, depositions and other extra-pleading material in determining its own jurisdiction. Tanzymore, 457 F.2d at 1323. Therefore, the only practical difference between challenging jurisdiction under rule 56 and rule 12(b)(1) is the way the court construes the facts. Thus, in determining jurisdiction, the court may not provide the nonmovant the benefit of favorable influences, but must determine whether, based on all of its submissions to the court, the nonmovant has borne its burden of demonstrating its entitlement to a federal forum.

The foregoing being so, however, I reject the government's argument that plaintiffs benefitted from favorable factual inferences in my previous opinion. At this point, a review of the facts utilizing the appropriate rule 12(b)(1) standard is in order.

Plaintiff Jerry Pelham worked as a construction laborer for a subcontractor engaged in a construction and demolition project at Building 65 at the Picatinney Arsenal. The project was being carried out pursuant to an agreement between an Army Corps of Engineers and defendant L & H, the general contractor at the job site.

On May 25, 1982, during the demolition phase, plaintiff was called to attach cables to a roof-support suspension beam. He was instructed to stand in a metal garbage dumpster to be lifted on the forks of a forklift to the suspension beam approximately twenty feet above floor level. As the box was being lifted with plaintiff in it, the forklift lurched, causing plaintiff to lose his balance. His hand was caught between the forklift mast chain and pulley, amputating portions of three fingers and severely lacerating a fourth on his left hand.

The contract between the Army Corps of Engineers and L & H governing the demolition and construction phases of this project, which is part of the record of this case, explicates the respective responsibilities of the contractor and the "contracting officer," the person executing the contract on behalf of the government or his or her authorized representative. General Provision 1(b). General Provision 10 provides that all work is subject to the government's inspection at all reasonable times for the government's benefit but that "any such inspection ... shall not relieve the Contractor of the responsibility of providing quality control measures to assure that the contract strictly complies with the contract requirements." Moreover, the contract requires the contractor to personally supervise the work done, General Provision 11, bring the job in compliance "with any applicable Federal, state and municipal laws, codes and regulations," General Provision 12, and generally "take proper safety and health precautions to protect the work, the worker, the public and the property of others," General Provision 12.

General Provision 52 of the contract specifically addresses accident prevention.2 Provision 52(a) states that the contractor shall comply with the pertinent provisions of the Army Corps "Safety and Health Requirements Manual" and "take or cause to be taken such additional measures as the Contracting Officer may determine to be reasonably necessary for the purpose." The contractor must maintain records on and report to the contracting officer on any accident. General Provision 52(b). General Provision 52(c) provides: "The Contracting Officer will notify the Contractor of any noncompliance with the foregoing provisions and the action to be taken." It also provides that if the contractor refuses to comply with a safety order, the contracting officer can issue a stop-work order. Moreover, General Provision 52(e) requires the contractor to submit, before the commencement of construction, written proposals for effectuating these accident prevention provisions. The safety program proposed by L & H pursuant to General Provision 52(c) provided that project superintendent Lawrence R. Maffie assumed full responsibility to "enforce, monitor, record and report on all safety measures." Safety Program, Exh. 4 to the Affirmative of Ralph Marra. Finally, General Provision 52 states: "The work will be conducted under the general direction of the contracting officer and is subject to inspection by his appointed inspectors to insure strict compliance with the terms of the contract."

The government's project engineer at the site was Frederick A. Labudzinski. According to his own deposition, Mr. Labudzinski's duties included monitoring compliance with the plans and specifications of the contract, which included the general provisions of the contract and their safety provisions. See Labudzinski Dep. at 15-18, Exh. D to Plaintiff's Brief in Opposition to Summary Judgment. Mr. Labudzinski spent ten to twenty percent of his time performing on-site tasks. Id. at 20. Throughout the demolition phase of the project, during which plaintiff was injured, either Mr. Labudzinski or an assistant inspected the project on a daily basis. Id. at 34.

Sometime shortly before plaintiff's injury, Mr. Labudzinski inspected the demolition site and first observed a worker in a metal container in the air hoisted by the forklift. Id. at 37-38. When asked whether he believed this procedure met safety requirements, Mr. Labudzinski testified at deposition as follows:

Q. Did you think the practice of having a worker present in a metal container contained on the forks of a forklift suspended in the air met the safety requirements of the general provisions of the building 65 contract when you saw it on the one or two occasions that you did before Mr. Pelham was injured?
A. I raised the issue with the superintendent for L & H Construction, Larry Maffie, M-A-F-F-I-E, Lawrence Maffie on the practice. He assured me that that was, it I recall, standard procedure for that type of demolition.
Q. Are you finished?
A. Yes.
Q. Did you think the practice of having a worker suspended in a container on the forks of a forklift met the safety provisions of the general provisions of the building 65 contract when you saw it on the one or two occasions that you did before Mr. Pelham's injury?
A. Yes.
Q. You mentioned that you raised an issue with Mr. Maffie. What did you see as the issue?
A. The issue was the fact of combining two pieces, or one piece of equipment with something that was — seemed to me at the time to be foreign to that piece of equipment and use it concurrently. Although my experience has been in construction field that there is not a specific piece of equipment for every specific task that is performed and thereby requiring makeshift, if you
...

To continue reading

Request your trial
98 cases
  • Piechowicz v. US
    • United States
    • U.S. District Court — District of Maryland
    • 29 Marzo 1988
    ...United States, 620 F.2d 948, 956 (3d Cir.), cert. denied, 449 U.S. 870, 101 S.Ct. 208, 66 L.Ed.2d 90 (1980); Pelham v. United States, 661 F.Supp. 1063, 1065-66 & n. 1 (D.N.J.1987). It is also to be noted that plaintiffs have the burden of establishing subject matter jurisdiction. For purpos......
  • Assisted Living Associates v. Moorestown Tp.
    • United States
    • U.S. District Court — District of New Jersey
    • 19 Marzo 1998
    ...of New York, Inc., 971 F.Supp. 915 (D.N.J.1997); Panna v. Firstrust Sav. Bank, 760 F.Supp. 432, 435 (D.N.J.1991); Pelham v. United States, 661 F.Supp. 1063, 1065 (D.N.J.1987). III. In support of its motions for reargument, the Planning Board has raised three factual or legal issues which, i......
  • Butko v. Ciccozzi (In re Butko)
    • United States
    • U.S. Bankruptcy Court — Western District of Pennsylvania
    • 8 Enero 2021
    ...553, 586 (E.D. Pa. 2008) ; Glendon Energy Co. v. Borough of Glendon, 836 F. Supp. 1109, 1122 (E.D. Pa. 1993).236 Pelham v. United States, 661 F.Supp. 1063, 1065 (D.N.J.1987) (emphasis added); see Glendon Energy Co. v. Borough of Glendon, 836 F. Supp. at 1122 (reconsideration "addresses only......
  • Rouse v. Plantier
    • United States
    • U.S. District Court — District of New Jersey
    • 9 Febrero 1998
    ...of New York, Inc., 971 F.Supp. 915 (D.N.J.1997); Panna v. Firstrust Sav. Bank, 760 F.Supp. 432, 435 (D.N.J.1991); Pelham v. United States, 661 F.Supp. 1063, 1065 (D.N.J.1987). A motion for reargument "is an extremely limited procedural vehicle" and may not be used to expand the record befor......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT