Peter Salvucci & Sons, Inc. v. State, 5900
Court | Supreme Court of New Hampshire |
Writing for the Court | LAMPRON |
Citation | 110 N.H. 136,268 A.2d 899 |
Parties | PETER SALVUCCI & SONS, INC. v. STATE. |
Docket Number | No. 5900,5900 |
Decision Date | 27 February 1970 |
Devine, Millimet, McDonough, Stahl & Branch and Robert A. Backus, Manchester (Joseph A. Millimet, Manchester, orally), for plaintiff.
Alexander J. Kalinski, Manchester, special counsel, for the State.
Action by plaintiff under RSA 491:8 to recover damages from the State for a breach of contract involving the construction of a part of Interstate Route 93 in Franconia. Trial before a master (Charles J. Flynn). A view of the different sites involved was taken on July 5, 1966. Evidence was presented before the master on various days between July 11 and September 23, 1966. The master's report included 60 specific findings and rulings made after a consideration of plaintiff's 113 requests for findings and rulings and of 31 such requests submitted by the defendant. The parties also filed memoranda of law and written arguments. The master's recommendation that the plaintiff be awarded the sum of $111,114.41 was accepted by the Superior Court (Bownes, J.) and judgment for plaintiff entered in that amount plus interest and costs in accordance with a motion by plaintiff.
Defendant excepted to the denial of its motion to dismiss made at the end of plaintiff's case and at the close of all the evidence. Defendant also excepted to the denial of its motions to set aside the master's report and for a continuance of plaintiff's motion for judgment on the report until the transcript of the evidence was available to the defendant. These exceptions were reserved and transferred by the Superior Court.
On January 13, 1958, Peter Salvucci and Sons, Inc., a Massachusetts corporation, entered into a contract with the State of New Hampshire, for the bid price of $837,267.63, to construct 7200 feet of highway in the town of Franconia running from Station 1 to Station 72. This project (P-3293-A) will be referred to as 'Job A' or 'Job I.' On April 29, 1958, the same parties entered into an agreement for the construction of 10,600 feet of highway adjoining the former and running from Stations 72 to 178. This project (P-3293-B) will be called 'Job B' or 'Job 2.' The completion date for both of these projects was October 15, 1959.
The essentials of plaintiff's claims are that in soliciting the bids for Job A the State represented to it that the work could be performed with materials obtained by widening the slopes of the highways; that free gravel and borrow could be obtained from the National Forest lands through which the highways were to be built; that the only cost to the contractor would be the cost of replanting the areas from which such materials were taken at a cost of approximately $50 per acre.
Plaintiff alleged 'that when it undertook to do the work in the manner represented to it by the State, it was denied the right to widen the slopes and the right to obtain free gravel and borrow from the National Forest land so that it had to obtain large quantities of gravel and borrow from other locations.
'The State's failure to make free gravel and borrow available, as represented, not only required that the Plaintiff purchase large quantities of material, which it was entitled to receive without charge, but also put the Plaintiff to great additional expense for the cost of digging and hauling the same, instead of being able to construct the projects as anticipated by the use of much more economical machinery and equipment.'
The plaintiff further alleged that the State, subsequent to the awarding of these two contracts, reaffirmed its promise to make free borrow and gravel available to the plaintiff in quantities and qualities sufficient to satisfy the 340,000 cubic yards required perform Job A at places and times necessary for its performance.
The plaintiff alleged that as a result of the breach of its contract by the State, both in its original misrepresentations and in its subsequent promises, it was put to great additional expense and suffered severe damages in its performance, not only of Job A, but also of Job B. These breaches it is alleged caused the plaintiff direct extra expenses in the amount of $225,726.23 and also overall intangible inefficiencies on both jobs which together resulted in a net overall loss to the plaintiff of $454,614.93.
The master made the following findings:
'Materials necessary for the completion of the project will be obtained, if available, by widening the slopes.
'No borrow pit shall be opened up within or outside the right of way to secure materials needed for the construction of the highway, nor shall any excavation be done beyond the work limits as definitely located by the plans, except as additional permission is granted by the Forest Supervisor.'
...
To continue reading
Request your trial-
S & M Constructors, Inc. v. City of Columbus, 81-837
...114 Conn. 250, 158 A. 551; Haggart Const. Co. v. State (1967), 149 Mont. 422, 427 F.2d 686; Peter Salvucci & Sons, Inc. v. State (1970), 110 N.H. 136, 268 A.2d 899, ordered reopened as to the issue of interest and costs only in 110 N.H. 502, 272 A.2d 854, affirmed on that issue in 111 N.H. ......
-
Mo. Consol. Health v. Community Health Plan, WD 59012.
...(S.D.1999) (quoting Mooney's, Inc. v. S.D. Dept. of Transp., 482 N.W.2d 43, 46 (S.D.1992)). See also Peter Salvucci & Sons, Inc. v. State, 110 N.H. 136, 268 A.2d 899 Missouri law implies a covenant of good faith and fair dealing in every contract. Martin v. Prier Brass Mfg. Co., 710 S.W.2d ......
-
Cook v. Oklahoma Bd. of Public Affairs, s. 59824
...day bid period precluded the contractor from making adequate soil analysis and test borings.); Peter Salvucci & Sons, Inc. v. State, 110 N.H. 136, 268 A.2d 899 [N.H.1970], reaffirmed, 111 N.H. 259, 281 A.2d 164 (the bidder was allowed insufficient time to make a personal 27 Compare Valentin......
-
Paras v. City of Portsmouth, 6894
...87 N.H. 492, 179 A. 357 (1935); Manchester v. Boston & Maine R. R., 98 N.H. 52, 94 A.2d 552 (1953); Peter Salvucci & Sons, Inc. v. State, 110 N.H. 136, 155-56, 268 A.2d 899, 911-12 (1970); aff'd 111 N.H. 259, 281 A.2d 164 (1971). In this case the board of taxation freely admitted in its opi......
-
S & M Constructors, Inc. v. City of Columbus, 81-837
...114 Conn. 250, 158 A. 551; Haggart Const. Co. v. State (1967), 149 Mont. 422, 427 F.2d 686; Peter Salvucci & Sons, Inc. v. State (1970), 110 N.H. 136, 268 A.2d 899, ordered reopened as to the issue of interest and costs only in 110 N.H. 502, 272 A.2d 854, affirmed on that issue in 111 N.H. ......
-
Mo. Consol. Health v. Community Health Plan, WD 59012.
...(S.D.1999) (quoting Mooney's, Inc. v. S.D. Dept. of Transp., 482 N.W.2d 43, 46 (S.D.1992)). See also Peter Salvucci & Sons, Inc. v. State, 110 N.H. 136, 268 A.2d 899 Missouri law implies a covenant of good faith and fair dealing in every contract. Martin v. Prier Brass Mfg. Co., 710 S.W.2d ......
-
Cook v. Oklahoma Bd. of Public Affairs, s. 59824
...day bid period precluded the contractor from making adequate soil analysis and test borings.); Peter Salvucci & Sons, Inc. v. State, 110 N.H. 136, 268 A.2d 899 [N.H.1970], reaffirmed, 111 N.H. 259, 281 A.2d 164 (the bidder was allowed insufficient time to make a personal 27 Compare Valentin......
-
Paras v. City of Portsmouth, 6894
...87 N.H. 492, 179 A. 357 (1935); Manchester v. Boston & Maine R. R., 98 N.H. 52, 94 A.2d 552 (1953); Peter Salvucci & Sons, Inc. v. State, 110 N.H. 136, 155-56, 268 A.2d 899, 911-12 (1970); aff'd 111 N.H. 259, 281 A.2d 164 (1971). In this case the board of taxation freely admitted in its opi......