Peter W. Kero, Inc. v. Terminal Const. Corp.

Citation6 N.J. 361,78 A.2d 814
Decision Date19 February 1951
Docket NumberNo. A--46,A--46
PartiesPETER W. KERO, Inc. v. TERMINAL CONST. CORP.
CourtUnited States State Supreme Court (New Jersey)

Aaron Heller, Passaic, argued the cause for the appellant. Irving Lloyd Gang, Newark, on the brief (Heller & Laiks, Passaic, attorneys).

Samuel R. Blaine, Newark, argued the cause for the respondent (C. Wallace Vail, Newark, attorney).

The opinion of the court was delivered by

ACKERSON, J.

The defendant, Terminal Construction Corporation, was under contract with the United States Government for certain construction work to be performed in the building of the Veterans' Administration Hospital at East Orange, and plaintiff, Peter W. Kero, Inc., was its sub-contractor for the purpose of removing a certain stock pile of earth and rock from the hospital site. The agreement between plaintiff and defendant for the latter work is evidenced by two written contracts, both dated December 10, 1948, both containing the same job designation ('Job No.--C--112; P.O. No.--133') and both drawn up on defendant's purchase order forms. In each document appears identical language providing that the plaintiff will 'furnish all labor, materials, and equipment necessary to remove' a certain stock pile of surplus earth and rock from the site in question. One of the contracts states that the consideration for these services 'shall be paid at prevailing standard rates, the total of which shall not exceed the sum of $18,000.00 * * *'; the other specified 'the total sum of $9500.00' as the price for the same services. Both contracts are signed by Peter W. Kero, as president of P. W. Kero, Inc., and Charles A. Cusick, purchasing agent for the defendant. In the negotiation and execution of these contracts, as well as many prior agreements between the same parties, plaintiff was represented by one person alone; he was its president, Peter W. Kero, who seems to have had complete control of the corporation and all of its business transactions.

Plaintiff rendered bills to the defendant, one dated December 31, 1948 for $5,000 and one dated January 8, 1949, for $4,500, both of which referred to the job number involved and defendant paid these bills by two checks, one for $5,000 dated February 25, 1949, and the other for $4,500 dated March 26, 1949. The second check, which was delivered by Richard N. Dinallo, president of the defendant company to Mr. Kero personally, contained a notation on its face, 'PO--133--Pd--in--full V.A.'

It also appears that when the second check was delivered, Mr. Kero, as president of the plaintiff corporation, executed two releases in favor of the defendant. Both of these releases are on printed general release forms and provide that P. W. Kero, Inc. for the consideration of $1 and other valuable consideration discharges the Terminal Construction Corporation from all claims and demands whatsoever, in the usual terminology of such instruments. However, in one of these releases, immediately following the printed words of general release, appears the following statement in typewriting:

'whereas two contracts were entered into between the parties hereto for work on the Veterans Administration Hospital at East Orange, New Jersey, and one is in the sum of $9500 and the other for a sum not exceeding $18,000.00, the purpose of this release is to release the releasee from all claims of both contracts and of all claims for extras, it being agreed that payment heretofore made in the sum of $9500.00 is in full and all differences between the parties concerning the contracts, the work, or the claims by one against the other are released.'

Both releases were concluded in the following manner:

'In Witness Whereof, the said party of the first part has caused these presents to be signed by its President and its corporate seal to be hereto affixed and attested by its Secretary the 4th day of June Nineteen Hundred and Forty-nine.

By P. W. Kero

'P. W. Kero President

'Attest

At

'Secretary'

Neither of the releases, however, was attested by the defendant's secretary, nor did a corporate or any other seal appear thereon. While the releases are dated 'the 4th day of June Nineteen Hundred and Forty-nine' (the figure '4th' is written in ink and the words 'June' and 'Forty-nine' are in typewriting), Mr. Kero testified that they were actually signed on March 26, 1949, when the second check ($4,500) was delivered to him, and when he signed them at that time they were both completely blank except for the printed matter usually contained in such forms and no type written material whatsoever appeared thereon.

Plaintiff instituted the present action on August 31, 1949, by a complaint, predicated upon the $18,000 contract, to recover an alleged unpaid balance thereunder of $8,500 (after crediting the two checks above mentioned, totaling $9,500) plus the reasonable value of extra work alleged to have been done at defendant's request, amounting to $5,000, thus making the total claim $13,500 plus interest and costs. Defendant's answer asserted that the other contract which set a flat price of $9,500 for the work in question embodied the true and final agreement between the parties and the price therein stipulated for had been paid. The answer further pleaded that any claim which plaintiff may have had under any agreement with respect to the aforementioned work was extinguished by 'general release'. Plaintiff replied that the releases thus referred to were procured through fraud in the particulars hereinafter specified.

The pretrial order stated the parties had agreed that the trial was to be based on the pleadings as filed. However, at the inception of the trial, this order was amended to amplify the issues by the insertion of the following sentence: 'Whether the plaintiff executed a general release, and whether it is barred from recovery by virtue of any release'.

At the close of the evidence defendant moved for a judgment in its favor on the ground that plaintiff had failed to establish any fraud to impugn the validity of the releases and therefore plaintiff's claim was effectively barred thereby. The plaintiff also moved for judgment in its favor on several grounds, Inter alia, that the releases in question are invalid and not binding on it as a matter of law because they (a) bear no seal, corporate or otherwise; (b) are not attested by its secretary; (c) are not signed with the corporate name and only by 'P. W. Kero, President'; (d) are not shown to have been the authorized act of the plaintiff, and (e) being without seal, no consideration is shown to have been given therefor. Both motions were denied and the cause was submitted to the jury resulting in a verdict for the plaintiff in the amount of $8,334.77 with interest and costs, and from the judgment entered thereon the defendant appealed to the Appellate Division of the Superior Court and we certified the cause here on our own motion.

The appeal challenges the trial court's denial of defendant's motion for the direction of a judgment in its favor and also the legal propriety of specified portions of the charge to the jury.

The sole basis of defendant's motion for judgment was that the releases in question barred plaintiff's claim because there was insufficient evidence of fraud in their procurement to warrant the submission of that question to the jury. We think the motion was rightly denied.

The substance of the alleged fraud may be summarized from the testimony given by the plaintiff's president, Peter W. Kero. He testified that for some time prior to March 26, 1949, he had been trying, unsuccessfully, to obtain from the defendant a further payment on account of work done at the hospital site. Finally, on that date, at about 7 o'clock in the evening, he found Dinallo, defendant's president, alone in his office and Dinallo agreed to pay $4,500 on account but stated that the payment would have to be made from his personal account and therefore he would require two releases, before delivering his check, in order to get the money back from his company. He thereupon produced two forms of general release in blank, except for the printed matter usually appearing on such instruments, and, as the typist had gone home, he requested Kero to sign them in blank upon his, Dinallo's express representation that he would have them filled in according to the mutual understanding that they were to discharge the defendant only to the extent of the payments so far made (including the present one) and not to operate as releases in full. Kero said he took Dinallo's '* * * word for it, and signed the blank releases'. He further testified that although he knew he was signing releases and did not read them and was not prevented from doing so, nevertheless, he did observe that the usual blank spaces appearing on such printed stock forms had not been filled in and he stated that over a course of five years business relations with the defendant he had signed 'dozens of releases'.

It is asserted that the aforesaid representation was made deceitfully with no intention of fulfillment and solely for the purpose of obtaining the releases in such form that they could be used thereafter by the defendant in complete bar of any further claims by the plaintiff.

It is the general rule that where a party affixes his signature to a written instrument, such as a release, a conclusive presumption arises that he read, understood and assented to its terms and he will not be heard to complain that he did not comprehend the effect of his act in signing. A notable exception to this rule, however, is when the signature is obtained by fraud or imposition in the execution of the instrument. Christie v. Lalor, 116 N.J.L. 23, 25, 181 A. 312 (Sup.Ct.1935) ; Kearney v. National Grain Yeast Corp., 126 N.J.L. 307, 19 A.2d 19 (E. & A.1940). It is well settled that where a party is induced to sign a release by reason of a misrepresentation intended to deceive him...

To continue reading

Request your trial
63 cases
  • MZM Constr. Co. v. N.J. Bldg. Laborers Statewide Benefit Funds
    • United States
    • U.S. Court of Appeals — Third Circuit
    • 14 Septiembre 2020
    ... 974 F.3d 386 MZM CONSTRUCTION COMPANY, INC., d/b/a MZM Construction Management & ... Advent Int'l Corp. , 220 F.3d 99, 104 (3d Cir. 2000) ; see also ... the effect of [her] act in signing." Peter W. Kero, Inc. v. Terminal Const. Corp. , 6 N.J ... ...
  • New Gold Equities Corp. v. Jaffe Spindler Co.
    • United States
    • New Jersey Superior Court — Appellate Division
    • 28 Febrero 2018
    ... ... New Gold employed BLDG Management Company, Inc. (BLDG), as the property manager. Senen Bacalan was the ... purchasers are expected to read their policies."); Peter W. Kero, Inc. v. Terminal Const. Corp. , 6 N.J. 361, 368, ... ...
  • Bilotti v. Accurate Forming Corp.
    • United States
    • New Jersey Supreme Court
    • 21 Enero 1963
    ... ... & A.1900) and Lippmann v. Hydro-Space Technology, Inc., 77 N.J.Super. 497, 187 A.2d 31 (App.Div.1962), seeking ... See Peter W. Kero, Inc. v. Terminal Construction Corporation, 6 N.J ... ...
  • Energex Lighting v. NORTH AMER. PHILIPS LIGHTING
    • United States
    • U.S. District Court — Southern District of New York
    • 24 Mayo 1991
    ... ... Supp. 93 ... ENERGEX LIGHTING INDUSTRIES, INC., Plaintiff, ... NORTH AMERICAN PHILIPS LIGHTING ... to that of Finance America Capital Corp., in its assets "to secure payment ... of any and ... Kero v. Terminal Construction Corp., 6 N.J. 361, 78 ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT