Peterson v. State

Decision Date25 May 1926
Docket NumberNo. 24376.,24376.
Citation114 Neb. 612,209 N.W. 221
PartiesPETERSON v. STATE.
CourtNebraska Supreme Court

OPINION TEXT STARTS HERE

Syllabus by the Court.

Plaintiffs submitted to the state of Nebraska through the department of public works a bid for the construction of a highway in Sioux county, pursuant to federal aid project No. 102A. The contract provides: “The contractor, in all cases, will be paid for the actual amount of work performed as shown by the ‘final estimates.’ The final estimates were to be, but were not, made by the state engineer. The “chief of the bureau of roads,” whom the contract designates as “the authorized representative of the engineer in charge of all work in the state prepared, pursuant to the contract, estimates and therein certified that $81,867.29 had been paid to plaintiffs and that $278.30 was the remainder due them. Plaintiffs, as the work progressed, accepted payments, aggregating the former sum and made no claim at any time, that measurements, used as a basis for estimates, were inaccurate. Held, that the estimates prepared by the chief of the bureau of roads were admissible in evidence on the issue as to the amount due the contractors.

Where a grading contract provides the manner in which the amount of different materials, which are removed, shall be determined as a basis for calculating the price of the work, and provides that the final estimate shall be signed by the state engineer, and that officer fails, or refuses, to sign such estimate, the court, in an action to recover a remainder due the contractor will follow the method indicated by the contract in determining the amount due.

The measurements and cross sections made during the progress of road building construction work, by the project engineer, in the absence of fraud, or gross mistake, are the best evidence of the quantity and character of the materials removed and expert evidence, based on measurements taken after the work has been fully performed, which enable the witnesses merely to express an opinion in respect of the quantity and character of the removed materials, as shown by the estimates, is incorrect, secondary and incompetent.

The Legislature has not provided by statute for payment of interest upon claims against the state. It follows that, in the absence of statute, or of an agreement therefor, such claims cannot be allowed. See United States v. North Carolina, 136 U. S. 211, 10 S. Ct. 920, 34 L. Ed. 336.

Appeal from District Court, Lancaster County; Stewart, Judge.

On rehearing. Former opinion overruled, judgment of district court reversed, and cause remanded, with directions.

For former opinion, see 113 Neb. 546, 203 N. W. 1002.

DAY, J., dissenting.O. S. Spillman, Atty. Gen., and Lloyd Dort, Asst. Atty. Gen., for the State.

Jacob Fawcett, of Lincoln, D. W. Merrow, of Omaha, and T. S. Allen, of Lincoln, for appellee.

Heard before ROSE, DEAN, DAY, GOOD, and EBERLY, JJ., and REDICK, District Judge.

DEAN, J.

Peterson, Shirley & Gunther, a firm of Omaha contractors, submitted a bid to the department of public works, of Nebraska, wherein it agreed to construct an earth and sand clay road, in Smiley Canyon in Sioux county, for $68,613.97, pursuant to federal aid project No. 102A.

This action was begun in Lancaster county to recover $47,428.72 which plaintiffs allege is the remainder due them, and unpaid, for the construction of the above-mentioned public highway. A jury was waived. Upon trial to the court plaintiffs recovered a judgment for $30,405.51, with interest thereon. From the judgment so rendered the state appealed, and, after argument, an opinion was written which, in all respects, sustained the trial court's judgment. See former opinion, Peterson v. State, 113 Neb. 546, 203 N. W. 1002.

Afterward, on motion of the state, a rehearing was granted. Thereupon the case was again submitted to this court for re-examination following able arguments by the respective counsel. Subsequently a second rehearing was allowed, on the state's application, and much new matter, material to the issues, was presented at the rehearing arguments to which our attention was not formerly directed.

In passing it may be recalled that the federalgovernment is concerned in the construction of “post roads” and the contract therefore provides that the construction works shall be subject to the inspection and approval of the Secretary of Agriculture. 39 U. S. St. at Large, c. 241, p. 355, § 6 (U. S. Comp. St. § 7477f).

In respect of the officers in charge of state highway construction, the contract indicates the following officers and designates their duties.

The engineer in charge of the project is the secretary of the department of public works. He is also designated the state engineer.”

The inspector:

“An authorized representative of the engineer assigned to make detailed inspection of any or all portions of the work or material therefor.”

The division engineer:

“An authorized representative of the engineer in responsible charge of all work and of all project engineers in the division to which he is assigned.”

The project engineer:

“An authorized representative of the engineer whose duties shall be to see that the work is carried out in accordance with the contract and specifications and perform such duties as are herein described as duties of the project engineer.”

The “chief of bureau of roads” is the “authorized representative of the engineer in charge of all work in the state.”

Subsequent to the submission of and pursuant to plaintiffs' bid, the contract in suit was entered into under date of May 5, 1921, wherein, among other things, it is provided:

“After the grading is completed and before final payment is made therefor, the project engineer will cross section the road and make careful measurement to determine the units of various items of work performed, as the basis for final settlement. The contractor, in all cases, will be paid for the actual amount of work performed as shown by the final estimates.”

Final acceptance by the department of public works is stipulated to mean a written acceptance by the department of public works followed by final payment which is to be in accordance with the engineer's final estimate.

The contract requires prospective bidders “to examine the plans, specifications, and special provisions carefully and make sure that the requirements are fully understood. They must satisfy themselves by personal examination of the road as to the nature of the material to be excavated, the location and accessibility of material and other local conditions affecting the contract.” This is so that bidders shall inform themselves in respect of the work to be performed in the project. And this cautionary warning appears in the contract:

“Note.--Bidder's attention is called to paragraph 62, section 1, standard specifications regarding payment of estimates.”

Paragraph 62, so far as material here, follows:

“Final acceptance by the department of public works is stipulated to mean a written acceptance by the department of public works followed by final payment in accordance with the engineer's final estimate.”

Any minor work, not specifically mentioned in the contract, but obviously necessary for the proper completion of the work, shall be executed in proper manner by the contractor and he “shall not be entitled to any extra or additional compensation for the same.” Grading shall be estimated and paid for by the cubic yard and measurement shall be made “by cross sectioning before and after excavation and the volumes determined by the average end area method.”

The contract also contains this:

“Special provisions covering section A of project No. 102, Sioux county.

It is specifically provided and understood in submitting this bid that all explosives which may be required to blast any solid rock or brule clay in solidified form will be furnished to the contractor by the department of public works at a price of fifteen (15) cents per pound. * * * The above mentioned explosive is composed of T. N. T. made up in cartridges of 1/2 pound size. No caps or fuses will be furnished.”

The chief of bureau of roads testified that about “24,000 pounds of T. N. T. and a few hundred pounds of dynamite were used in the project,” and that ordinarily it was assumed that a pound of explosive would remove a yard of rock, although in some instances it takes more explosives. This evidence seems to support the state's contention that plaintiffs removed approximately 24,000 yards of rock. Plaintiffs contend that much more explosives were used but there is testimony which tends to prove that they were used to remove quantities of earth on the expressed ground that it effected a saving for the contractors. True, the contractors had the right to use explosives in moving plow land, for which they received 38 cents a cubic yard, if they counted that the most economical method of removal. But the mere fact that explosives were so used did not entitle them to $1.80 a cubic yard for earth so removed, that being the contract price for the removal of solid rock. Clearly, plaintiffs had no right to so increase the amount of their compensation.

Notwithstanding the following provision in the contract, there is no record of any claim by the plaintiff company for “extra compensation”:

“In any case, where the contractor deems that extra compensation is due him for work or material not clearly covered in this contract nor ordered in writing by the engineer as an extra, as defined above, the contractor shall notify the engineer of his intention to make claim for such extra compensation before he begins the work upon which he bases the claim. ...

To continue reading

Request your trial
3 cases
  • Peterson v. State
    • United States
    • Supreme Court of Nebraska
    • May 25, 1926
  • Hartford Steam Boiler Inspection and Ins. Co. v. State
    • United States
    • Court of Appeals of Texas
    • April 29, 1987
    ...Carolina, 136 U.S. 211, 10 S.Ct. 920, 34 L.Ed. 336; Jobe v. Urquhart, 102 Ark. 470, 143 S.W. 121, Ann.Cas.1914A, 351; Peterson v. State, 114 Neb. 612, 209 N.W. 221. The act authorizing the bringing of this suit makes no provision for the recovering of interest. We know of no statute that gr......
  • State v. Tennessee Gas Transmission Co., 10393
    • United States
    • Court of Appeals of Texas. Court of Civil Appeals of Texas
    • April 4, 1956
    ...Carolina, 136 U.S. 211, 10 S.Ct. 920, 34 L.Ed. 336; Jobe v Urquhart, 102 Ark. 470, 143 S.W. 121, Ann.Cas.1914A, 351; Peterson v. State, 114 Neb. 612, 209 N.W. 221. The act authorizing the bringing of this suit makes no provision for the recovering of interest. We know of no statute that gra......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT