Pioneer Constr., Inc. v. May (In re May)
Decision Date | 29 August 2014 |
Docket Number | Adversary No. 12–06020.,Bankruptcy No. 12–60371. |
Citation | 518 B.R. 99 |
Parties | In re Jeffery A. MAY, Debtor. Pioneer Construction, Inc., Creditor/Plaintiff v. Jeffery A. May, Debtor/Defendant. |
Court | U.S. Bankruptcy Court — Southern District of Georgia |
David H. Johnson, Colby E. Longley, McCorkle & Johnson, LLP, Savannah, GA, for Plaintiff.
H. Lehman Franklin, Jr., Kimberly S. Ward, H. Lehman Franklin, PC, Statesboro, GA, for Defendant.
This matter came on for trial on the Complaint to Determine Dischargeability of Debt filed by Pioneer Construction, Inc.(“Plaintiff”) against Jeffery A.May (“Debtor”).(ECF No. 16;A.P. ECF No. 1.)1The Complaint contends that a February 7, 2012, Consent Judgment (“Consent Judgment”) entered against the Debtor by the Superior Court of Bulloch County, Georgia, held the Debtor liable for willful conversion of payments for real property improvements under O.C.G.A. §§ 16–8–15and51–10–6. (A.P. ECF No. 1 ¶¶ 9, 10.)According to the Plaintiff, the Consent Judgment conclusively determines that the Debtor's actions constitute a willful and malicious injury to the property of another and therefore establishes the Plaintiff's claim as nondischargeable under 11 U.S.C. § 523(a)(6).(Id.¶ 11.)
A trial was held on April 21, 2014, after which I took the matter under advisement.I have considered the stipulated facts, testimony, documentary evidence, and oral arguments presented by the parties.For the reasons that follow, I find that Plaintiff's claim does not fall within the exception of 11 U.S.C. § 523(a)(6) and that debt is therefore dischargeable.
The Debtor is the former CEO and CFO of May Specialty Fabricators, Inc.(“May Specialty”), a structural and miscellaneous steel fabrications subcontractor.(Stip., Att. A of A.P. ECF No. 49at 9, ¶ 4.)The Plaintiff is a general contractor that regularly engages in public works construction.The Plaintiff's claim against the Debtor arises from May Specialty's failure to pay one of its suppliers for materials used in a public construction project.
On May 15, 2008, the Plaintiff entered into a contract with the Georgia Ports Authority to provide construction materials and labor to real property known as Container Berth Eight Reefer Racks, Garden City, Georgia (“Reefer Racks Project”).(Stip., Att. A of A.P. ECF No. 49at 9, ¶ 1.)On July 21, 2008, the Plaintiff entered into two contracts with May Specialty for work on the Reefer Racks Project: a construction subcontract (“Subcontract”) and a separate purchase order (“Purchase Order”).(SeeStip., Att. A of A.P. ECF No. 49at 9, ¶ 3.)The Debtor did not personally guarantee May Specialty's performance under either agreement.
Under the Subcontract, May Specialty would be paid $160,000.00 for “Labor, Materials and Supervision for the erection of structural steel, steel stairs & railings and miscellaneous steel fabrication as per contract plans and specifications dated April 3, 2008.”(July 21, 2008, Subcontract Agreement between Pioneer Construction, Inc. and May Specialty Fabricators, Inc., Pl.'s Ex. 7at 24.)The Subcontract also obligated May Specialty to broadly indemnify the Plaintiff:
(Subcontract, Pl.'s Ex. 7at 18–19)(emphasis added.)
The Purchase Order provided that May Specialty would be paid $953,500.00 to “Furnish, F.O.B. Project Site, all structural steel, miscellaneous steel fabrications, anchor belts, metal decking, epoxy kits, steel pipe bollards, metal fasteners and all other materials required for a 100% complete operational system.”(July 21, 2008, Purchase Order Agreement between Pioneer Construction, Inc. and May Specialty Fabricators, Inc., Pl.'s Ex. 6at 5.)
May Specialty subcontracted with The Haskell Company(“Haskell”) to supply a portion of the construction materials due under the Purchase Order (“Supplier Contract”).(Stip., Att. A of A.P. ECF No. 49at 9, ¶ 3.)The injury at issue in this case arose when May Specialty failed to pay Haskell with the proceeds from the Plaintiff's final payment on the Purchase Order.Since the Reefer Racks Project was a public construction contract, Georgia law required the Plaintiff to post a payment bond to ensure the payment of all parties contributing to the construction.(SeeStip., Att. A of A.P. ECF No. 49at 9, ¶ 2.)May Specialty's failure to pay the full amount due on the Supplier Contract allowed Haskell to make a claim against the payment bond.
On May 20, 2008, the Plaintiff obtained a bond from The Ohio Casualty Insurance Company(“Surety”) for the full amount due on the Reefer Racks Project, $1,963,900.00.(SeeStip., Att. A of A.P. ECF No. 49at 9, ¶ 2.)In compliance with O.C.G.A. § 13–10–63, the payment bond provided that any supplier or subcontractor who had not been paid in full for materials furnished or labor provided “shall have the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of commencement of such action and to prosecute such action to final execution and judgment for the sum or sums due to him.”SeeO.C.G.A. §§ 13–10–60, et seq.;(The Ohio Casualty Insurance Company Payment Bond 3–913–375, Pl.'s Ex. 5at 7.)
The payment bond did not require potential bond claimants to have a contractual relationship with the Plaintiff in order to collect on the bond.(Seeid. )In order to maintain an action on the payment bond, Georgia law only requires a bond claimant to provide:
[W]ritten notice to the contractor within 90 days from the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was performed or done.
However, a general contractor may significantly limit this otherwise broad exposure to remote bond claimants by complying with O.C.G.A. § 13–10–62(a), which requires the general contractor to, within 15 days after physical construction begins, 1) post a Notice of Commencement at the public works construction site and 2) file the same Notice of Commencement with the Superior Court in the county in which the site is located.O.C.G.A. § 13–10–62.Compliance with O.C.G.A § 13–10–62(a) bars all parties without a direct contractual relationship to the general contractor from proceeding against the bond, unless the potential bond claimant provides written notice detailing its contribution to the project “within 30 days from the filing of the notice of commencement or 30 days following the first delivery of labor, material, machinery, or equipment, whichever is later.”SeeO.C.G.A. § 13–10–63(a)(2).
On June 5, 2008, the Plaintiff recorded a Notice of Commencement for the Reefer Racks Project in the Superior Court of Chatham County, Georgia.(SeeJan. 11, 2010, Order on Motions for Summary Judgment, The Haskell Company v. Pioneer Construction, Inc., et al., Civil ActionNo. CV09–171BA, Def.'s Ex. 12at 2.)However, the Plaintiff failed to post a Notice of Commencement at the job site.(Id. )This oversight allowed parties without a contractual relationship to the Plaintiff, such as Haskell, to proceed against the payment bond under the more relaxed notice requirements of O.C.G.A. § 13–10–63(a)(1) –90 days from the claimant's last work on the project—instead of the more stringent requirements of O.C.G.A. § 13–10–63(a)(2) –30 days from the claimant's first work on the project.(Seeid. )Haskell made its first delivery to the job site on July 28, 2008.(SeePl.'sEx. 8.)It made its last delivery on September 29, 2008.(Seeid. )Haskell provided written notice of its intent to state a claim against the payment bond to the Plaintiff on November 24, 2008.SeeJan. 11, 2010, Order on Motions for Summary Judgment, The Haskell Company v. Pioneer Construction, Inc., et al, Civil ActionNo. CV09–171BA, Def.'s Ex. 12at 3.)Thus, had the Plaintiff posted a Notice of...
To continue reading
Request your trialUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology
