Pittsburgh Const Co. v. West Side Belt R. Co.
Decision Date | 13 February 1907 |
Docket Number | 30. |
Citation | 151 F. 125 |
Parties | PITTSBURGH CONST. CO. v. WEST SIDE BELT R. CO. et al. |
Court | U.S. District Court — Western District of Pennsylvania |
Reed Smith, Shaw & Beal, for plaintiff.
Willis McCook and Lee & Mackey, for defendant.
This is an action of assumpsit brought by the Pittsburgh Construction Company, a corporation of the state of West Virginia, against the West Side Belt Railroad Company, a corporation of Pennsylvania, designated in this opinion as the 'Belt Road,' and John S. Scully and Theodore N. Barnsdall citizens of said state.
The Belt Road on April 17, 1901, entered into a written contract with A. S. Petrie to construct its proposed line of railway. On April 25, 1901, it authorized Petrie to sublet this contract to the plaintiff company, which company was chartered in West Virginia May 14, 1901. On May 24, 1901 Petrie made a new contract with the plaintiff (which was substantially a duplicate of his contract), a copy of which first contract is embodied in the statement of claim as Exhibit A. Contemporaneously with the execution thereof defendants, by indorsement thereon, stipulated:
Petrie, who made the original contract, was not a contractor. It was never intended he should build the road, or was the contract given to him for that purpose. He was an officer of the Belt Road, who resigned to qualify him to take the contract, and become the conduit through whom the contract could be sublet to the plaintiff company, and through whom a portion of the proposed price of construction was, through the agency of Barnsdall and Scully, to be returned to all the stockholders of the Belt Road. The contract of Petrie with the plaintiff seems, therefore, to have been treated as between plaintiff and the Belt Road.
After the construction of the Belt Road its chief engineer sent the following notice to the plaintiff:
Under this notice a large amount of testimony was taken; the Belt Road and plaintiff being each represented by counsel. Later notice was given to Scully and Barnsdall by the following notice:
'To A. S. Petrie, Pittsburgh Construction Company, West Side Belt Railroad Company, John S. Scully, T. N. Barnsdall, J. C. Bower, McCleave & Wendt and Reed, Smith, Shaw & Beal: You are hereby notified that upon Monday, January 16, 1905, at 10 o'clock a.m., at my office, Room 2107, Farmers' Bank Building, Pittsburgh, Pa., I will hold a final meeting under the provisions of the clause of the article of agreement dated the 24th day of May, 1901, between the Pittsburgh Construction Company of the first part and A. S. Petrie of the second part, which clause reads as follows, viz.: 'And it is mutually agreed and distinctly understood that the decision of the chief engineer shall be final and conclusive in any dispute which may arise between the parties to this agreement relating to or touching the same, and each and every of said parties do hereby waive any right of action, suit or suits, or other remedy in law, or otherwise, by virtue of said covenants, so that the decision of the said chief engineer, James H. McRoberts, shall in the nature of an award be final and conclusive on the rights and claims of said parties.' You are requested to be present at this meeting if you see fit.' There is a dispute as to whether Scully and Barnsdall took any part in the proceedings. There is no question, however, they had notice, and that counsel for them requested an opportunity to examine the testimony, and thereafter made no request for further hearing and made no protest. On October 24, 1905, McRoberts made a report or award in which
This suit is brought against Petrie's guarantors to recover said sum of $332,750.98, and a verdict for such amount, with interest, was taken for the plaintiff. Thereupon defendants move for judgment in their favor non obstante veredicto. The grounds of this motion are, first, that this suit cannot be maintained because the plaintiff, a foreign corporation, did not register, as required by Pennsylvania statute, before making the contract on which this suit is based; and, secondly, that the alleged award is invalid because the arbiter failed to pass and report on the claim of the railroad for $96,970.86 for delay in completing the work; and, lastly, the arbiter having found that 'almost every provision of the agreements between the parties had been disregarded, neglected or violated, by both parties, and, in consequence, waived,' the sureties are released.
Taking up the first question, it is proper to defendants to say that, while they deny liability under the contract by reason of plaintiff's nonregistration, they do not deny that in a proper proceeding the railroad company, which is financially responsible, is answerable for just compensation to the plaintiff. In that regard their brief says: 'Where work is done under such a contract, recovery can be had on the quantum meruit, and not on the contract.'
Turning first to the statutes, we have the act of 1874 which provides:
...
To continue reading
Request your trial-
Butler Bros. Shoe Co. v. United States Rubber Co.
... ... each $1,000 of its capital stock. Const. Colo. art. 15, Sec ... 10; 1 Mills' Ann. St. Secs. 499, ... Virginia and West Virginia connected with other railroads, so ... that it ... v. Priebe (Mo. App.) 100 ... S.W. 558; Pittsburgh Const. Co. v. West Side Belt R. Co ... (C.C.) 151 F ... ...
-
Altoona Sanitary Milk Co. v. Armstrong
... ... Co. v. West Side Belt Railroad Co., 151 F. 125; ... McMullen v ... ...
-
Buffalo Refrigerating Mach Co. v. Penn Heat & Power Co.
... ... recognize.' ... The ... case of East Side Bank v. Columbus Tanning Co., 170 ... Pa. 1, 32 A. 539, ... In ... Pittsburgh Construction Co. v. West Side, etc., Co., ... 154 F. 929, ... Pittsburgh Company v. West Side Belt R.R. Co. (C.C.) ... 151 F. 125, and to the additional ... ...
- Pittsburgh Const Co. v. West Side Belt R. Co.