Pointe Dev. LLC v. Enter. Bank
| Decision Date | 10 August 2010 |
| Docket Number | No. WD 71591.,WD 71591. |
| Citation | Pointe Dev. LLC v. Enter. Bank & Trust, 316 S.W.3d 543 (Mo. App. 2010) |
| Parties | POINTE DEVELOPMENT, LLC, Respondent,v.ENTERPRISE BANK AND TRUST, Appellant. |
| Court | Missouri Court of Appeals |
Michael S. Cessna and Leonard B. Rose, Kansas City, MO, for appellant.
Steven W. White, Independence, MO, for respondent.
Before Division One: JAMES M. SMART, JR., Presiding Judge, MARK PFEIFFER, Judge and CYNTHIA L. MARTIN, Judge.
Enterprise Bank and Trust (“Enterprise”) appeals from the trial court's judgment in favor of Pointe Development, LLC (“Pointe”) in the amount of $51,469.92. Enterprise claims that the trial court erred in granting judgment to Pointe on its claim for breach of contract because Enterprise's loan commitment included a condition subsequent that the cost of construction could not exceed the loan amount which was not satisfied by Pointe, relieving Enterprise of the obligation to provide the loan. We affirm.
Pointe was formed to develop unimproved property in Raymore, Missouri. The site was to be improved by the construction of seventy-four townhome units (“Project”). In August 2005, Pointe, through its managing member Steve Walker, approached Northstar Bank (“Northstar”) to obtain a site development loan and a construction loan for the Project. The site development loan was to be used to construct roads, sewers, curbs, and other similar improvements to the land. The construction loan was to be used to construct fourteen townhome units.
On August 4, 2005, Northstar's loan committee approved Pointe's request for funding. On August 12, 2005, Northstar issued a written loan commitment agreeing to extend Pointe a site development loan in the amount $875,000 and a construction loan in the amount of $1,105,400. The single page commitment, titled “Credit Approval Request,” was delivered by facsimile to Pointe on August 15, 2005. The commitment reflected that both loans were to be secured by a deed of trust on the Project and by Walker's personal guaranty. The commitment noted with respect to the construction loan that the “LTV would be the lesser of 100% of cost or 85% of APV.” “LTV” means loan to value. “APV” means appraised value.
In April 2006, Pointe requested that Northstar approve a $125,000 increase in the site development loan. Northstar approved this request, thus increasing the site development loan to a total of $1,000,000. The written loan commitment (i.e. the August 12, 2005 “Credit Approval Request”) was not revised to reflect this modification, though other records received in evidence indicate the revised site development loan in the amount of $1,000,000 was fully funded by Northstar.
Sometime prior to July 2006, Walker told Charles VanZante, the Northstar employee who signed the loan commitment, that the cost of construction of the townhomes would exceed $1,105,400, the amount of the construction loan. Walker did not ask Northstar to increase the amount of the construction loan, however. 2
In July 2006, Enterprise acquired Northstar and assumed Northstar's obligations to Pointe pursuant to the commitment. Sometime during and after July 2006, Walker similarly advised loan officers at Enterprise that the cost of construction of the townhomes was expected to exceed the construction loan amount. In July, August, or September of 2006, Walker provided Enterprise with documentation that indicated that the cost of construction of the townhomes was expected to increase from $1,105,400 to $1,340,308. Walker did not ask Enterprise to increase the construction loan.
Walker testified that he had the funds available to cover the cost to construct the townhomes over and above the amount of the construction loan. Walker testified that he told Enterprise he would be able to cover any shortfall between the construction loan amount and the cost of construction of the townhomes.
Walker sought to close on the construction loan with Enterprise in or around August 2006. Enterprise attempted to impose additional requirements on Pointe as a condition of closing, which Walker refused to perform. Enterprise refused to close on the construction loan.
Pointe sought and secured construction loan financing from an alternative source and used the proceeds of the new financing to pay off the development loan owed to Enterprise. Because Enterprise would not close on the construction loan when Pointe requested, and because Pointe was required to secure a construction loan from an alternative source, Pointe claimed it was damaged in the amount of $51,469.92.
Pointe filed suit against Enterprise for breach of contract. The case was tried to the court on September 3, 2008. On August 26, 2009, the Honorable W. Stephen Nixon entered Judgment in favor of Pointe in the amount of $51,469.02. The trial court noted that it had heard testimony and made credibility determinations consistent with its Judgment. The trial court found that Enterprise breached its agreement to fund the construction loan component of the loan commitment by failing to close the loan as requested by Pointe in August of 2006. Specifically, the trial court found that while there may have been discussions between Walker and Enterprise's loan officers regarding an increase in the cost of construction of the townhomes, there was no meeting of the minds between the parties to seek approval for an increase in the construction loan amount. The trial court found that Pointe never asked Enterprise to increase or modify, in any respect, the construction loan promised by the loan commitment. The trial court found that the original construction loan component of the loan commitment remained in full force and effect and was never withdrawn or revoked by Enterprise.
Enterprise appeals.
“In a court tried case, the ‘judgment of the trial court will be sustained by the appellate court unless there is no substantial evidence to support it, unless it is against the weight of the evidence, unless it erroneously declares the law, or unless it erroneously applies the law.’ ” Mo. Pub. Serv. Comm'n v. Hurricane Deck Holding Co., 302 S.W.3d 786, 789 (Mo.App. W.D.2010) ().
In its sole point on appeal, Enterprise claims that the trial court erred in granting judgment to Pointe on its claim for breach of contract. Enterprise concedes its commitment formed a contract with Pointe. The essence of Enterprise's argument on appeal is that it was relieved of its obligation to perform the contract because the loan commitment included a condition subsequent that the cost of construction would not exceed the $1,105,400 construction loan-a condition Pointe did not satisfy, thus relieving Enterprise of its obligation to fund the construction loan. We disagree.
“A condition subsequent is a condition ‘which by its express terms provides for an ipso facto cancellation on the happening or non-occurrence of a stipulated event or condition.” Reed Stenhouse, Inc. of Mo. v. Portnoy, 642 S.W.2d 947, 952-53 (Mo.App. E.D.1982) ( quoting Berger v. McBride & Son Builders, 447 S.W.2d 18, 19 (Mo.App.1969)). See also Boatmen's Bank of Mid-Mo. v. Crossroads W. Shopping Ctr., Ltd., 907 S.W.2d 800 (Mo.App. W.D.1995).3 “ ” Duncan v. Acad. of Sisters of the Sacred Heart of St. Joseph, Mo., 350 S.W.2d 814, 818-19 (Mo. banc 1961) ( quoting Holekamp Lumber Co. v. State Highway Comm'n, 173 S.W.2d 938, 942 (Mo.1943)). “Words of limitation normally associated with the creation of a condition subsequent include the following: ‘upon condition that’; ‘upon express condition that’; ‘provided that’; ‘but if’; ‘if it happens that’ or a phrase of like import.” DeHart v. Ritenour Consol. Sch. Dist., 663 S.W.2d 332, 333 (Mo.App. E.D.1983) ().4
Enterprise failed to identify in its initial brief any provision of the loan commitment which Enterprise believed warranted the “implication” of a condition subsequent. This notable omission was highlighted by Pointe in its brief, prompting Enterprise, in its reply brief, to point to the following language in the loan commitment as the alleged condition subsequent: “LTV would be the lesser of 100% of cost or 85% of APV.”
We conclude that this provision of the loan commitment is not a condition subsequent, whether express or...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Dallas v. Am. Gen. Life & Accident Ins. Co.
...for an ipso facto cancellation on the happening or non-occurrence of a stipulated event or condition.’ ” Pointe Dev., LLC v. Enter. Bank & Trust, 316 S.W.3d 543, 546 (Mo.Ct.App.2010) (quoting Reed Stenhouse, Inc. of Mo. v. Portnoy, 642 S.W.2d 947, 952–53 (Mo.Ct.App.1982)). The term “conditi......
-
Coffey v. Coffey
...construed strictly. Weitzel v. Sioux Valley Heart Partners, 2006 S.D. 45, ¶ 38, 714 N.W.2d 884, 895-96; Point Dev., LLC v. Enter. Bank & Tr., 316 S.W.3d 543, 546-47 (Mo. Ct. App. 2010); 17A Am. Jur. 2d Contracts § 453, Westlaw (database updated Nov. 2016). "[A]n act or event designated in a......