Prime Investors & Developers, LLC v. Meridien Cos., 4D19-1005
Court | Court of Appeal of Florida (US) |
Writing for the Court | Gerber, J. |
Citation | 289 So.3d 1 |
Parties | PRIME INVESTORS & DEVELOPERS, LLC and Homestead Holdings II, LLC, Appellants, v. The MERIDIEN COMPANIES, INC., Appellee. |
Docket Number | No. 4D19-1005,4D19-1005 |
Decision Date | 22 January 2020 |
Vincent F. Vaccarella and Craig Lewis of Vincent F. Vaccarella, P.A., Fort Lauderdale, for appellants.
William M. Lindeman of William M. Lindeman, P.A., Orlando, for appellee.
A developer and a contractor jointly appeal from the circuit court's order granting a subcontractor's motion for final summary judgment on the subcontractor's claims for breach of contract and to foreclose a construction lien, arising from the subcontractor not receiving full payment for its installation of cabinets and countertops on a hotel project.
The developer and the contractor argue the circuit court erred in entering summary judgment for many reasons, three of which we address here: (1) the contractor's affidavit reflected genuine issues of material fact regarding the subcontractor's material quality and installation; (2) the subcontractor's motion did not address the developer's third affirmative defense alleging lack of compliance with the construction lien statutes' notice and timing requirements; and (3) the circuit court lacked subject matter jurisdiction over the construction lien foreclosure claim because the property is located in Miami-Dade County, not Broward County.
We conclude the first two arguments have merit, for reasons explained below. Therefore, we reverse the circuit court's order granting the subcontractor's motion for final summary judgment. Although the third argument is moot by our decision, we will briefly address that argument because that issue may recur on remand.
We present this opinion in three parts:
The developer hired the contractor to construct a hotel in Miami-Dade County. The contractor then hired the subcontractor to install cabinets and countertops for all guest rooms. The subcontract provided, in pertinent part:
The subcontractor eventually installed the cabinets and countertops in the hotel, and the contractor's construction manager signed off on the installation. The contractor paid the subcontractor in part, but withheld full payment because the contractor found that the cabinets and countertops were deficient in both material quality and installation.
The contractor later filed, in Broward County circuit court, a breach of contract complaint against the subcontractor, alleging that the subcontractor failed to provide the correct materials, timely install the materials, properly install the materials, and correct the defective work.
In response, the subcontractor filed an answer, a counterclaim for breach of contract against the contractor for non-payment, and a third party complaint to enforce its construction lien against the developer. The subcontractor's answer and third party complaint pled that venue was proper in Broward County.
In response to the subcontractor's third party complaint, the developer filed an answer and affirmative defenses. The developer's answer admitted venue was proper in Broward County, but denied the remaining allegations. The developer's third affirmative defense alleged that the subcontractor had failed to comply with the notice and timing requirements of the construction lien statutes provided in chapter 713, Florida Statutes (2016).
After discovery, the subcontractor filed a motion for final summary judgment. The motion alleged, in pertinent part: the contractor and subcontractor modified the subcontract so that the timing of the subcontractor's performance was not linked to the overall project schedule; the contractor agreed to swap out certain materials to save costs; the subcontractor installed the materials in conformance with the contractor-approved shop drawings; all of the materials were installed; and any defective installations were simply punch list items, but the contractor never provided a punch list.
The subcontractor's motion for summary judgment did not address the developer's third affirmative defense alleging the subcontractor had failed to comply with chapter 713's notice and timing requirements.
The developer and the contractor jointly filed a response to the subcontractor's motion for summary judgment. The response argued, in pertinent part: the subcontract provided that the subcontractor's performance was linked to the overall project schedule and time was of the essence, and no modification was made to those timing provisions; the subcontractor was months late in producing the materials, causing the project's overall progress and the hotel's opening to be delayed; the subcontractor's materials did not meet the developer's and the contractor's specification standards; and the subcontractor failed to correct the deficiencies in materials and installation.
In support of the response, the contractor and the developer filed the contractor's chief operating officer's affidavit. The affidavit alleged, in pertinent part:
To continue reading
Request your trial