Prior v. First Bank and Trust Co. of Mt. Vernon

Decision Date21 July 1992
Docket NumberNo. 5-91-0038,5-91-0038
Citation231 Ill.App.3d 331,596 N.E.2d 891,173 Ill.Dec. 267
Parties, 173 Ill.Dec. 267 John PRIOR d/b/a Prior Oil Co., Plaintiff-Appellant, v. FIRST BANK AND TRUST CO. OF MT. VERNON, Illinois, as Trustee under the Provisions of a Trust Agreement known as Trust # 15418, Darrell Davis, Evelyn C. Davis, Charles Eugene Davis, Evelyn L. Davis, and Unknown and Non-record owners and other lien claimants, Defendants-Appellees.
CourtUnited States Appellate Court of Illinois

Ronald A. Niemann, Niemann and Parker, Centralia, for plaintiff-appellant.

David L. Piercy, Howard & Howard, Mt. Vernon, for Darrell, Evelyn L., Charles Eugene, and Evelyn C. Davis.

Justice RARICK delivered the opinion of the court:

Plaintiff, John Prior, d/b/a Prior Oil Company, appeals from the granting of summary judgment by the circuit court of Jefferson County in favor of defendants, Darrell, Evelyn C., Charles Eugene and Evelyn L. Davis, on plaintiff's claim for a mechanics' lien against their property. We reverse and remand.

Defendants are the owners of the beneficial interest of a land trust of which First Bank and Trust Co. of Mt. Vernon is the trustee. On October 23, 1987, Terry Flanagan entered into a contract for deed with trustee for the purchase of the real estate comprising the land trust in order to construct a raceway. Pursuant to constructing the raceway, on March 11, 1988, Flanagan entered into an oral agreement with plaintiff for the furnishing of materials and labor to bring the race track into operation. Plaintiff expended some $10,445 in labor and materials but was never paid for the goods and services he furnished. Accordingly, plaintiff brought an action to impose a mechanics' lien. Defendants moved for summary judgment claiming plaintiff had never provided a sworn contractor's statement as required by section 5 of the Mechanics' Liens Act (Ill.Rev.Stat.1987, ch. 82, par. 5) so as to perfect or create his lien. The trial court determined plaintiff's failure to provide the section 5 statement precluded his action for a mechanics' lien and granted defendants' motion for summary judgment. On appeal, plaintiff asserts the trial court erred in granting summary judgment in favor of defendants on the grounds he failed to comply with section 5 of the Mechanics' Liens Act, especially when defendants were on notice of his claim.

Mechanics' liens, being wholly a creation of statute, are in derogation of the common law. (First Federal Savings & Loan Association v. Connelly (1983), 97 Ill.2d 242, 246, 73 Ill.Dec. 454, 456, 454 N.E.2d 314, 316; Aluma Systems, Inc. v. Frederick Quinn Corp. (1990), 206 Ill.App.3d 828, 838, 151 Ill.Dec. 618, 625, 564 N.E.2d 1280, 1287; Suddarth v. Rosen (1967), 81 Ill.App.2d 136, 139, 224 N.E.2d 602, 603.) As such, mechanics' lien statutes, affording extraordinary remedies to certain classes of contractors and subcontractors (Suddarth, 81 Ill.App.2d at 139, 224 N.E.2d at 603), must be strictly construed with reference to all requirements upon which such liens depend (First Federal, 97 Ill.2d at 246, 73 Ill.Dec. at 456, 454 N.E.2d at 316; Aluma Systems, 206 Ill.App.3d at 838, 151 Ill.Dec. at 625, 564 N.E.2d at 1287). Once a contractor has complied with the statutory prerequisites, however, the Mechanics' Liens Act should be liberally construed in order to carry out its remedial purpose. (First Federal, 97 Ill.2d at 246, 73 Ill.Dec. at 456, 454 N.E.2d at 316; Aluma Systems, 206 Ill.App.3d at 839, 151 Ill.Dec. at 625, 564 N.E.2d at 1287.) This purpose is to permit a lien upon premises where a benefit has been received by the owner and where the value or condition of the property has been increased or improved by reason of the furnishing of labor and materials. (First Federal, 97 Ill.2d at 246, 73 Ill.Dec. at 456, 454 N.E.2d at 316; Abbott Electrical Construction Co. v. Ladin (1986), 144 Ill.App.3d 974, 981, 98 Ill.Dec. 924, 929, 494 N.E.2d 1251, 1256.) As our supreme court has stated:

"The doctrine of strict construction was never meant to be applied as a pitfall to the unwary, in good faith pursuing the path marked by the statute, nor as an ambuscade from which an adversary can overwhelm him for an immaterial misstep. Its function is to preserve the substantial rights of those against whom the remedy offered by the statute is directed, and it is never employed otherwise." (United Cork Cos. v. Volland (1937), 365 Ill. 564, 572, 7 N.E.2d 301, 305, 73 Ill.Dec. at 459; see also First Federal, 97 Ill.2d at 251, 454 N.E.2d at 319.)

Here we have just such a case of a technicality being used to defeat a valid lien. Under the holdings of Abbott Electrical and National Wrecking Co. v. Midwest Terminal Corp. (1st Dist. Aug. 7, 1991), Nos. 1-87-1899, 1-88-2587, 1-88-3600, 1-89-0279, rehearing granted (March 5, 1992), plaintiff's failure to give defendants a sworn statement does not operate to bar his mechanics' lien...

To continue reading

Request your trial
7 cases
  • Premier Elec. Const. Co. v. American Nat. Bank of Chicago
    • United States
    • United States Appellate Court of Illinois
    • December 13, 1995
    ...must be strictly construed because mechanic's liens are a statutory creation. (Prior v. First Bank & Trust Co. of Mount Vernon (1992), 231 Ill.App.3d 331, 332, 173 Ill.Dec. 267, 596 N.E.2d 891.) Once the statutory requirements are met, however, the Act should be liberally construed to carry......
  • Westcon/Dillingham Microtunneling v. Walsh Const. Co.
    • United States
    • United States Appellate Court of Illinois
    • March 30, 2001
    ...a lien exists under section 23 is not a matter within the discretion of a trial court. See Prior v. First Bank & Trust Co., 231 Ill.App.3d 331, 333, 173 Ill.Dec. 267, 596 N.E.2d 891 (1992). In this case, the court's order was similar to a mandatory injunction, ordering the clerk to release ......
  • First Bank of Roscoe v. Rinaldi
    • United States
    • United States Appellate Court of Illinois
    • May 26, 1994
    ...subcontractors; as such, its technical and procedural requirements must be strictly construed. (Prior v. First Bank & Trust Co. (1992), 231 Ill.App.3d 331, 333, 173 Ill.Dec. 267, 596 N.E.2d 891.) The lien is valid only if each of the statutory requirements is scrupulously observed. (Watson ......
  • Contract Development Corp. v. Beck
    • United States
    • United States Appellate Court of Illinois
    • January 27, 1994
    ...subcontractors. As such, its technical and procedural requirements must be strictly construed. (Prior v. First Bank & Trust Co. (1992), 231 Ill.App.3d 331, 333, 173 Ill.Dec. 267, 596 N.E.2d 891.) Once the lien claimant has complied with the statutory requirements, the Act should be liberall......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT