Project B.A.S.I.C. v. Kemp

Decision Date30 July 1991
Docket NumberNo. 91-1612,PHOENIX-GRIFFIN,91-1612
Citation947 F.2d 11
PartiesPROJECT B.A.S.I.C., Plaintiff, Appellee, v. Jack KEMP, Secretary of Housing and Urban Development, et al., Defendants.GROUP II, LTD., et al., Plaintiff, Appellee, v. Jack KEMP, Secretary of Housing and Urban Development, et al., Defendants. Jack Kemp, Secretary of Housing and Urban Development, and United States Department of Housing and Urban Development, Defendants, Appellants. . Heard
CourtU.S. Court of Appeals — First Circuit

Page 11

947 F.2d 11
PROJECT B.A.S.I.C., Plaintiff, Appellee,
v.
Jack KEMP, Secretary of Housing and Urban Development, et
al., Defendants.
PHOENIX-GRIFFIN GROUP II, LTD., et al., Plaintiff, Appellee,
v.
Jack KEMP, Secretary of Housing and Urban Development, et
al., Defendants.
Jack Kemp, Secretary of Housing and Urban Development, and
United States Department of Housing and Urban
Development, Defendants, Appellants.
No. 91-1612.
United States Court of Appeals,
First Circuit.
Heard July 30, 1991.
Decided Oct. 17, 1991.

Page 13

John F. Daly, Atty., Appellate Staff, Civil Div., U.S. Dept. of Justice, with whom Stuart M. Gerson, Asst. Atty. Gen., Michael Jay Singer, Atty., Appellate Staff, Lincoln C. Almond, U.S. Atty., John W. Herold, Associate Gen. Counsel (HUD), Howard M. Schmeltzer, Asst. Gen. Counsel (HUD), and Richard M. Price, Trial Atty. (HUD), Washington, D.C., were on brief, for defendants, appellants.

Robert B. Mann, with whom Mann & Mitchell, Providence, R.I., was on brief, for plaintiffs, appellees Phoenix-Griffin Group II, Ltd., et al.

Steven Fischbach, with whom Judith Kay and Rhode Island Legal Services, Providence, R.I., were on brief, for plaintiff, appellee Project B.A.S.I.C.

Before TORRUELLA and SELYA, Circuit Judges, and YOUNG, * District Judge.

SELYA, Circuit Judge.

This is an appeal from a court order holding the Secretary of Housing and Urban Development (HUD) in civil contempt and imposing monetary sanctions. 1 We granted a stay and expedited appellate proceedings. We now reverse.

I. BACKGROUND

We begin by tracing the contours of the two earlier proceedings which together gave rise to the present appeal.

A. The Original Litigation (PB-I and PB-II).

Simmering hostilities erupted into public view when Project B.A.S.I.C. (BASIC), a tenant-advocacy organization, asked the federal district court to enjoin the Providence Housing Authority (PHA) from tearing down certain portions of an antiquated public housing project known as Hartford Park, located in Providence, Rhode Island. The district court denied BASIC's motion for a preliminary injunction prohibiting the scheduled demolition. Project B.A.S.I.C. v. Kemp, 721 F.Supp. 1501, 1518 (D.R.I.1989) (PB-I ). We affirmed that denial without a published opinion. PHA proceeded to pulverize the structures.

There was more to PB-I, however, than the request for prohibitory injunctive relief. Thus, in addition to denying the prohibitory restrainer, the district court also entered the following decree:

IT IS HEREBY ORDERED that the PHA proceed as soon as possible to begin construction of the 240 public housing units, funded by HUD, needed to replace the 240 units lost due to the past and planned demolition of the highrises at Hartford Park. The PHA is ordered to complete construction of all 240 units of replacement housing within 23 months

Page 14

of the date of this Opinion [July 17, 1989].

PB-I, 721 F.Supp. at 1515. In a separate appeal, we ruled that the legal grounds adduced by the district court to justify this mandatory injunction (which we shall refer to as the 1989 Order) were inadequate to that end. Project B.A.S.I.C. v. O'Rourke, 907 F.2d 1242, 1243-47 (1st Cir.1990) (PB-II ). We noted, nonetheless, that the 1989 Order might be supportable on other grounds. Id. at 1247-49. For this reason, and mindful of the prospect that "the parties may ... no longer disagree about the order," id. at 1249, we did not vacate the 1989 Order but left it "in place provisionally," with directions to the district court to "reconsider the legal basis for its order if [the parties] request it to do so." Id.

On remand, no such request was made. Rather, the litigants' energies appear to have been expended principally on an amicable resolution of the underlying problems which had, in the first instance, fomented the law suit. In April 1991, with the district court's approval, the parties entered into a series of settlement stipulations and consent orders designed to resolve the main dispute over the construction of replacement public housing.

B. The Second Litigation (Phoenix-I).

Much of the replacement housing was being developed by Phoenix-Griffin Group II, Ltd. and built by its affiliate, LTG Construction Co., as the general contractor. Both Phoenix-Griffin and LTG are owned by Lloyd T. Griffin. All are plaintiffs in the second litigation and appellees here. We refer to them collectively as Phoenix and to the second litigation as Phoenix-I.

During the course of Phoenix's work, a substantial question arose as to whether Phoenix had paid the wage rates required by federal law. The United States Department of Labor (DOL) requested HUD to withhold $500,000 in funds pending resolution of the question. When HUD announced its intention to withhold--or to direct PHA to withhold--$500,000 from the next payment due Phoenix, Phoenix sued both HUD and PHA. It sought injunctive relief, damages, and other remedies, asserting that husbanding the funds was arbitrary and capricious, violated specific laws and regulations, abridged Phoenix's constitutional rights, and threatened Phoenix with irreparable harm. Among other things, Phoenix asserted that, without access to the $500,000, it would be prevented from paying down its revolving line of credit, thus causing its lead bank to close the spigot. Phoenix feared that it would be unable to complete construction in progress if further advances were denied.

A hearing on Phoenix's request for a preliminary injunction was held on June 6, 1991. The stated purpose of the hearing was to determine if HUD and/or PHA should be enjoined from withholding payments due to Phoenix under existing contracts. At the hearing, the district judge suggested that HUD, which had directed the holdback, might be in contempt of the 1989 Order. He asked HUD to brief the topic.

Four days after HUD's brief was served, the court filed a memorandum decision under a dual caption referring to both the new and old cases. Project B.A.S.I.C. v. Kemp, 768 F.Supp. 21 (D.R.I.1991). 2 The court stated that its "clear intention at the time of the [1989 Order] was to bind HUD as well as the PHA." The court remarked that HUD had been an active participant in the litigation leading up to, and following, entry of the 1989 Order, including the earlier appeal. Characterizing HUD's decision to withhold $500,000 as the product of an interagency turf battle between HUD and DOL--a characterization which HUD emphatically contests--the court ruled that HUD could, and should, have avoided flouting the 1989 Order by issuing a change order to make funds available to Phoenix, notwithstanding DOL's administrative directive. Hence, HUD could not assert that compliance with the 1989 Order was an impossibility.

Page 15

In the end, the court found that HUD was fully subject to the 1989 Order and had violated it. The court concluded that, "[u]ntil such time as HUD has done everything within its power to move the [replacement housing] project toward completion" as per the preexisting time schedule, the court would not find HUD to have complied with the outstanding order. 768 F.Supp. at 25 (emphasis in the original). The court gave HUD three days within which to resume making payments in the ordinary course. If HUD failed to do so within the three-day period, thus purging itself of the contempt, then:

In order to coerce compliance with my order, I will initially fine the agency $250,000. I...

To continue reading

Request your trial
122 cases
  • Cobell v. Norton
    • United States
    • U.S. District Court — District of Columbia
    • 17 Septiembre 2002
    ... ... to comply with the Court's Order of December 21, 1999, to initiate a Historical Accounting Project; (2) committing a fraud on the Court by concealing the Department's true actions regarding the ... Id. at 1289; Project B.A.S.I.C. v. Kemp, 947 F.2d 11, 16-17 (1st Cir.1991) (noting that in order for a party to be held in civil contempt, ... ' involves the actual accounting then the scope of the required accounting-even at its most basic level-is a matter that need not be addressed today. On this point, the government is incorrect. The ... ...
  • Gilday v. Dubois
    • United States
    • U.S. Court of Appeals — First Circuit
    • 5 Junio 1997
    ... ... turn, mindful that it was for Gilday to establish by " 'clear and convincing evidence[,]' " Project B.A.S.I.C. v. Kemp, 947 F.2d 11, 16 (1st Cir.1991) (quoting Langton v. Johnston, 928 F.2d 1206, ... litigation context, including the particular circumstances surrounding its formation and the basic purposes it was designed to serve. See ITT Continental Baking Co., 420 U.S. at 238 (construing ... ...
  • Heaney v. Lamento (In re Whiz Kids Dev., LLC)
    • United States
    • U.S. Bankruptcy Court — District of Massachusetts
    • 17 Noviembre 2017
    ... ... The Arts Council was the funding source for the project and was the entity that ultimately purchased the property from Heaney in 2017. Marotta credibly ... v. Kemp , 947 F.2d 11, 16 (1st Cir. 1991), and it is sufficient that the court order violated be "specific ... ...
  • Chao v. Gotham Registry, Inc.
    • United States
    • U.S. Court of Appeals — Second Circuit
    • 24 Enero 2008
    ... ... ]ny ambiguity in the law should be resolved in favor of the party charged with contempt."); Project B.A.S.I.C. v. Kemp, 947 F.2d 11, 16 (1st Cir.1991) (stating prudential rule that ambiguities in ... ...
  • Request a trial to view additional results
3 books & journal articles
  • Criminal Contempt
    • United States
    • Colorado Bar Association Colorado Lawyer No. 51-11, December 2022
    • Invalid date
    ...terms of the order were clear and unambiguous, and that proof of noncompliance was clear and convincing."); Project B.A.S.I.C. v. Kemp, 947 F.2d 11, 17 (1st Cir. 1991) ("For a party to be held in contempt, it must have violated a clear and unambiguous order that left no reasonable doubt as ......
  • The spatial bias of federal housing law and policy: concentrated poverty in urban America.
    • United States
    • University of Pennsylvania Law Review Vol. 143 No. 5, May 1995
    • 1 Mayo 1995
    ...in a lawsuit challenging replacement housing on the ground that it would be constructed in areas of minority concentration), rev'd, 947 F.2d 11 (1st Cir. 1991); George Judson, Uproar in New Haven on Public Housing Role, N.Y. TIMES, Sept. 30, 1991, at B1 (describing community opposition to P......
  • Appellate stays in civil cases: Florida and federal courts offer more security flexibility than believed, but stay violations still have teeth.
    • United States
    • Florida Bar Journal Vol. 86 No. 10, December 2012
    • 1 Diciembre 2012
    ...power of Supreme Court, independent of statutory authority, to punish for contempt of court). (47) See Project B.A.S.I.C. v. Kemp, 947 F.2d 11, 16 (1st Cir. 1991) ("[C]ivil contempt will lie only if the putative contemnor has violated an order that is clear and unambiguous."); Lantz, 440 So......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT