Project Map, Inc. v. United States, 31-73.

Decision Date14 November 1973
Docket NumberNo. 31-73.,31-73.
Citation486 F.2d 1375
PartiesPROJECT MAP, INC. v. The UNITED STATES.
CourtU.S. Claims Court

John S. Nolan, Washington, D. C., Atty. of record, for plaintiff.

Russell W. Koskinen, Washington, D. C., with whom was Acting Asst. Atty. Gen., Irving Jaffe, for defendant.

Before DAVIS, SKELTON and KUNZIG, Judges.

ON DEFENDANT'S AND PLAINTIFF'S MOTION FOR SUMMARY JUDGMENT

PER CURIAM:

This case implicates three contracts plaintiff Project Map, Inc. has had with the Department of Labor. The contractor sues to recover $26,166.42 admittedly due it under Contract 0424. The defendant has withheld that sum from the amount concededly owing under that agreement because, on the other two contracts (Contracts 0401 and 0430), the contracting officer determined that plaintiff had been overpaid by at least that figure. In each instance this determination of overpayment was appealed to the Department's Board of Contract Appeals, and both disputes are still pending before that tribunal. The contractor says that there is no dispute as to Contract 0424, on which it is suing, and therefore it should now be paid the full sum due under that agreement. The Government admits that there is no controversy as to 0424 but asserts a right to set off, on that agreement, amounts it claims owing to it under the other two contracts. Both sides have moved for summary judgment.

Part III of Dale Ingram, Inc. v. United States, 475 F.2d 1177, 1188, 201 Ct. Cl. 56, 76 (March 1973), dealt with precisely the same problem. In that instance, too, the defendant withheld payment of a sum awarded by the Board of Contract Appeals on one contract because there was then pending before the Board a dispute as to another of the contractor's agreements under which the contracting officer had held the contractor indebted to the Government in a larger sum. That plaintiff, just like Project Map, Inc., argued that the failure to pay the conceded sum was a breach of contract entitling the claimant to immediate judgment. The court squarely rejected this contention "because the Government has a right of off-set with respect to the decision of the contracting officer on the other contract now pending before the Board in which he held that the plaintiff is indebted to the Government in the sum of a figure greater than that withheld. The decision of the contracting officer in this regard is final and binding until and unless it is reversed or changed by the Board or by this court should the case be appealed here from the Board. Consequently, the Government has the right to withhold the sum withheld awarded to the plaintiff in this case until the other appeal has been finally decided." 475 F.2d at 1188, 201 Ct.Cl. at 76.

Dale Ingram, Inc. is dispositive here. We do not agree with plaintiff that that holding was counter to 31 U.S.C. § 227,1 a provision which is limited to prescribing the procedure for offsets against court judgments obtained against the Federal Government. The section does not deal with the federal right of set-off prior to the entry of a court judgment, nor does it suggest in any way that the set-off rights of the Federal Government, unlike those of other creditors, are confined to the single remedy of set-off after a judgment has been obtained. On the contrary, in United States v. Munsey Trust Co., 332 U.S. 234, 239, 67 S.Ct. 1599, 1602, 91 L.Ed. 2022 (1947), the Supreme Court said that "the government has the same right `which belongs to every creditor, to apply the unappropriated moneys of his debtor, in his hands, in extinguishment of the debts due him.'" See, also, Madden v. United States, 371 F.2d 469, 470, 178 Ct.Cl. 121, 122-123 (1967). There is no intimation that this right is restricted solely to a debt which is admitted by the debtor, and that has not been the practice either of the Government or of the private commercial world.

If 31 U.S.C. § 227 has any bearing at all, its underlying policy serves to support the ruling in Dale Ingram, Inc. The section declares that, in the circumstances to which it applies, the Comptroller General, once the alleged debtor disputes his obligation, shall cause legal proceedings to be begun to try out the issue — but only "if such debt is not already in suit." The premise is simply that there should be an impartial determination of the disputed debt. But that is exactly what is happening in Dale Ingram, Inc., as well as in the present case. In both instances, the controversial debt is "already in suit" in the sense that the Board of Contract Appeals (and perhaps ultimately a court) will decide whether the money is properly owing by the contractor. There is thus bound to be an...

To continue reading

Request your trial
11 cases
  • Cecile Industries, Inc. v. Cheney
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • June 15, 1993
    ...e.g., United States v. Munsey Trust Co., 332 U.S. 234, 239, 67 S.Ct. 1599, 1602, 91 L.Ed. 2022 (1947); Project Map, Inc. v. United States, 486 F.2d 1375, 1376, 203 Ct.Cl. 52 (1973); Madden v. United States, 371 F.2d 469, 470, 178 Ct.Cl. 121 (1967). This right extends to offsets between sepa......
  • NCLN20, Inc. v. United States
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • July 21, 2011
    ...the debtor "extends to offsets between separate contracts which the debtor may have with the Government."); Project Map, Inc. v. United States, 486 F.2d 1375, 1375 (Ct. Cl. 1973) (allowing the Government to offset debts of one contract against paymentsdue in another contract). With respect ......
  • NCLN20, Inc. v. United States
    • United States
    • U.S. Claims Court
    • July 21, 2011
    ...the debtor "extends to offsets between separate contracts which the debtor may have with the Government."); Project Map, Inc. v. United States, 486 F.2d 1375, 1375 (Ct. Cl. 1973) (allowing the Government to offset debts of one contract against paymentsdue in another contract). With respect ......
  • Centron Corp. v. United States
    • United States
    • U.S. Claims Court
    • October 18, 1978
    ...to him.'" United States v. Munsey Trust Co., 332 U.S. 234, 239, 67 S.Ct. 1599, 1602, 91 L.Ed. 2022 (1947); Project Map, Inc. v. United States, 486 F.2d 1375, 203 Ct.Cl. 52 (1973); Trinity Universal Ins. Co. v. United States, 382 F.2d 317, 320 (5th Cir.1967), cert. denied, 390 U.S. 906, 88 S......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT