PSE Consulting, Inc. v. Frank Mercede & Sons, Inc.

Decision Date13 January 2004
Docket Number(SC 16839).
Citation838 A.2d 135,267 Conn. 279
PartiesPSE CONSULTING, INC. v. FRANK MERCEDE AND SONS, INC., ET AL.
CourtConnecticut Supreme Court

Borden, Norcott, Katz, Palmer and Vertefeuille, Js. R. Bradley Wolfe, with whom were Mary Anne A. Charron and, on the brief, Durwin P. Jones, for the appellant (defendant National Fire Insurance Company of Hartford).

Raymond A. Garcia, with whom were Frederick E. Hedberg and, on the brief, Jane I. Milas, for the appellee (named defendant).

Matthew M. Horowitz filed a brief for the Surety Association of America as amicus curiae.

Opinion

KATZ, J.

This appeal concerns the rights of a surety, pursuant to an indemnity agreement, to indemnification for payments made in settling a claim against a surety bond. The sole parties in this appeal are National Fire Insurance Company of Hartford (National) and Frank Mercede and Sons, Inc. (Mercede), the two defendants in the underlying action.1 National, a commercial surety company, appeals2 from the judgment of the trial court, rendered after a jury trial, in favor of Mercede on National's cross complaint seeking indemnification and on Mercede's counter cross complaint seeking damages arising from a breach of the implied covenant of good faith and fair dealing.

On appeal, National claims that the trial court improperly: (1) disregarded the terms of an indemnity agreement executed by National and Mercede by instructing the jury that National had the burden of proving, as an element of its claim for indemnification, that its payments to the plaintiff, PSE Consulting, Inc. (PSE); see footnote 1 of this opinion; pursuant to a payment bond were proper; (2) failed to direct a verdict for National when the jury improperly found that National's payments to PSE had not been made in satisfaction of PSE's claim under the payment bond; (3) instructed the jury concerning the implied covenant of good faith and fair dealing; (4) admitted into evidence an e-mail message protected by the attorney-client privilege, as well as testimony pertaining to a settlement agreement between National and a third party unrelated to this action; (5) submitted Mercede's special defenses of waiver and estoppel to the jury, and refused to direct a verdict for National as to those special defenses, when the jury reasonably could not have found for Mercede; and (6) refused to set aside the verdict when the jury inconsistently had found that National had breached the implied covenant of good faith and fair dealing but not the indemnity agreement. We affirm the judgment of the trial court.

The jury reasonably could have found the following facts. In October, 1996, National and Mercede executed a general agreement of indemnity (indemnity agreement), whereby National agreed to issue surety bonds on Mercede's behalf, and Mercede agreed to indemnify National for any expenses that National might incur as a result of issuing those bonds. In May, 1997, Mercede was hired as a general contractor to construct an assisted living facility in Stamford (project). As security for the contract, Mercede furnished the owner of the project with a labor and materials payment bond (payment bond). The payment bond was issued by National, on behalf of Mercede as the principal and in favor of the owner as obligee, whereby National and Mercede agreed to be jointly and severally responsible for the payment of all labor, materials and equipment furnished for use in the construction of the project. Mercede executed a written subcontract with Dominion Bridge, Inc. (Dominion), for the manufacture and erection of structural steel. Dominion, in turn, entered into an oral sub-subcontract with PSE, whereby PSE agreed to erect steel structures for $1.5 million. This sub-subcontract between Dominion and PSE was never reduced to writing, however, and PSE never executed a formal subcontract with Mercede.

PSE began work on the project in November, 1997. Soon thereafter, PSE became concerned about the volume of work that it was performing on the project, and sought further assurance that it would be paid for that work. Consequently, PSE, Dominion and Mercede executed a joint check agreement, whereby Mercede agreed to issue checks made payable jointly to Dominion and PSE in satisfaction of their sub-subcontract. The joint check agreement provided that Mercede would pay for amounts "up to the contract amount [of $1.5 million], plus any extra charges determined and agreed upon subsequent to the date hereof." This joint check agreement also provided for a retainage of 10 percent.3

Between January and August, 1998, PSE continued to work on the project and to submit invoices to Dominion. Dominion then forwarded the invoices to Mercede, and Mercede issued joint checks pursuant to the joint check agreement. A representative of PSE signed a release form upon receipt of each joint check, whereby PSE waived any potential claims it may have had against Mercede. At the time of Mercede's final payment under the joint check agreement on July 20, 1998, Mercede had made six joint payments totaling $1,323,000.

Dominion filed for bankruptcy in September, 1998. Shortly thereafter, PSE sent a letter to Mercede, stating that Dominion still owed PSE more than $600,000, and demanding that Mercede immediately pay this "undisputed" amount, "plus interest, and excluding other claims for delays, etc. that will be coming shortly." Mercede refused to make any further payments without confirmation from Dominion as to the validity of PSE's claim.

On October 13, 1998, PSE formally notified National of its claim for $1,123,551 against the payment bond. National thereafter assigned the claim to Laurence P. Jortner, surety claims analyst for National's parent corporation, CNA Surety. On November 2, 1998, Jortner sent a letter to PSE, in response to the claim, communicating National's position that "a number of bona fide or otherwise unresolved disputes exist between your company and either [Mercede] or Dominion," and that much of PSE's claim was "likely to be subject to reasonable defenses by [Mercede] or [National]." Jortner also requested that PSE submit further documentation in support of its claim. PSE complied with this request shortly thereafter.

National took no further action until February, 1999, when Jortner met with several representatives of Mercede to discuss defenses to the claim. At this meeting, Mercede's representatives told Jortner that they were disputing the claim in its entirety, including PSE's claims for payment for extra work and for the $150,000 retainage.

Additionally, in February, 1999, Jortner was contacted by Robert Dunn, counsel for PSE. On February 13, Dunn sent a letter to Jortner, and a copy of that letter to the insurance commissioner, claiming that National had breached its obligations under paragraph six of the payment bond to pay undisputed amounts and to explain the basis for any disputed amounts within forty-five days of the receipt of a claim.4 Jortner immediately responded that National was conducting a detailed investigation, and that, "[a]s of now, [PSE's] claim is fully disputed by [Mercede] and [National] believes that [Mercede] has provided it with, at [a] minimum, bona fide legal defenses regarding [PSE's] claim." PSE subsequently filed a formal complaint with the insurance commissioner.

Soon thereafter, National shifted its position on the PSE claim. In May, 1999, Jortner again met with representatives of Mercede. This time, Jortner suggested that either National or Mercede make a payment to PSE in the amount of $177,000 ÔÇö representing the $150,000 retainage plus a $27,000 balance remaining on the original contract. Mercede agreed to pay the $27,000 remaining balance, but maintained that it would not pay the $150,000 retainage because the project owner had not yet paid that amount to Mercede. Mercede continued to dispute PSE's claims for payment for extra work.

In August, 1999, PSE filed the original complaint in the underlying action against Mercede and National, seeking damages from Mercede for breach of contract, and claiming that National had acted in bad faith and had committed violations of the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes ž 42-110a et seq. Unbeknownst to Mercede, National's counsel contacted PSE's counsel to discuss the possibility of a settlement of PSE's bad faith and CUTPA claims against National. National and PSE, however, did not reach an agreement at that time.

In September, 2000, almost two years after PSE initially had filed its formal notice of a claim against the payment bond, National conducted its independent investigation of the claim. At that time, Jortner enlisted Raymond Lemming, National's in-house chief engineer, to evaluate the fair market value of PSE's work on the project. Lemming concluded that PSE's work had a fair market value of approximately $927,913. That value was based, however, on PSE's work under the base contract and did not include PSE's claimed extra work.

Thereafter, National persistently attempted to settle PSE's claims. In April, 2001, Jortner attended a settlement meeting with counsel for National and counsel for PSE. No representatives of Mercede were present at this meeting. In October, 2001, National made a payment to PSE in the amount of $200,000. According to Jortner, this payment represented the $150,000 retainage plus an additional $50,000, constituting three years of interest at 10 percent. The payment was made at the time of Jortner's deposition, and Mercede, who had no prior knowledge of the settlement negotiations, objected to the payment.

On October 31, 2001, Jortner wrote a letter to Mercede, demanding that Mercede reimburse National for the $200,000 payment and either comply with the settlement of the remainder of PSE's claims, or deposit collateral of $500,000 with National, in accordance with National's rights under the...

To continue reading

Request your trial
128 cases
  • State v. Swinton
    • United States
    • Connecticut Supreme Court
    • May 11, 2004
    ...judge the credibility of witnesses nor substitute our judgment for that of the trier of fact. See PSE Consulting, Inc. v. Frank Mercede & Sons, Inc., 267 Conn. 279, 312, 838 A.2d 135 (2004) ("[i]ssues of credibility are uniquely within the province of the jury"); State v. Francis, supra, 26......
  • Capstone Bldg. Corp. v. Am. Motorists Ins. Co., SC 18886
    • United States
    • Connecticut Supreme Court
    • June 11, 2013
    ...of express duties are necessary to maintain a bad faith cause of action. In PSE Consulting, Inc. v. Frank Mercede & Sons, Inc., 267 Conn. 279, 306, 838 A.2d 135 (2004), the performance bond contained mandatory terms obligating the surety to "send an answer to [the principal] within forty-fi......
  • Jacob Doe v. Hartford Roman Catholic Diocesan Corp.
    • United States
    • Connecticut Supreme Court
    • July 7, 2015
    ...is a clear indication to the contrary, a jury is presumed to follow the court's instructions"; PSE Consulting, Inc. v. Frank Mercede & Sons, Inc., 267 Conn. 279, 335, 838 A.2d 135 (2004); we decline to join the defendant in speculating on whether the jury "appreciate[d] the significance of ......
  • NORTHEAST CT. ECON. ALLIANCE v. ATC P'SHIP
    • United States
    • Connecticut Supreme Court
    • December 14, 2004
    ...court's consideration of the availability of public funds for abuse of discretion. Id.; see also PSE Consulting, Inc. v. Frank Mercede & Sons, Inc., 267 Conn. 279, 332, 838 A.2d 135 (2004) "Relevant evidence is evidence that has a logical tendency to aid the trier in the determination of an......
  • Request a trial to view additional results
3 books & journal articles
  • Chapter 10
    • United States
    • Full Court Press Business Insurance
    • Invalid date
    ...Insurance Co. v. Brighton School District, 940 P.2d 348 (Colo. 1997). Connecticut: PSE Consulting, Inc. v. Frank Mercede & Sons, Inc., 267 Conn. 279, 838 A.2d 135 (2004). Illinois: Fischer v. Fidelity & Deposit Company of Maryland, 125 Ill. App.3d 632, 80 Ill. Dec. 880, 466 N.E.2d 332 (Ill.......
  • MASTERING ESSENTIAL ASPECTS OF THE ATTORNEY-CLIENT PRIVILEGE, WORK PRODUCT IMMUNITY, AND LAWYERS' ETHICAL DUTY OF CONFIDENTIALITY
    • United States
    • FNREL - Special Institute Due Diligence in Oil & Gas and Mining Transactions (FNREL)
    • Invalid date
    ...a corporation."). [56] In re Pac. Pictures Corp., 679 F.3d 1121, 1126 (9th Cir. 2012); PSE Consulting, Inc. v. Frank Mercede & Sons, Inc., 838 A.2d 135, 167 (Conn. 2004); Ctr. Partners, Ltd. v. Growth Head GP, LLC, 981 N.E.2d 345, 356 (Ill. 2012); In re Bryan, 61 P.3d 641, 656 (Kan. 2003); ......
  • CHAPTER 11 Surety Bonds
    • United States
    • Full Court Press Insurance for Real Estate-Related Entities
    • Invalid date
    ...Insurance Co. v. Brighton School District, 940 P.2d 348 (Colo. 1997). Connecticut: PSE Consulting, Inc. v. Frank Mercede & Sons, Inc., 267 Conn. 279, 838 A.2d 135 (2004). Illinois: Fischer v. Fidelity & Deposit Company of Maryland, 125 Ill. App.3d 632, 80 Ill. Dec. 880, 466 N.E.2d 332 (Ill.......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT