R & S Const. Co., a Div. of Robbins & Stearns Co., Inc. v. BDL Enterprises, Inc.

Decision Date01 July 1993
Citation500 N.W.2d 628
PartiesR & S CONSTRUCTION COMPANY, A DIVISION OF ROBBINS & STEARNS COMPANY, INC., a South Dakota Corporation, Plaintiff, v. BDL ENTERPRISES, INC., a Corporation, Defendant and Appellant, and TSP Two, Inc., a Corporation, Defendant and Appellee. 17898.
CourtSouth Dakota Supreme Court

Ronald W. Banks, Banks, Johnson and Colbath, Rapid City, for defendant and appellant.

Edward C. Carpenter, Costello, Porter, Hill, Heisterkamp and Bushnell, Rapid City, for defendant and appellee.

SABERS, Justice.

Owner, who was determined liable to builder for additional costs of construction, claims architect should bear greater responsibility for those construction costs attributable to architect's negligence. We agree and reverse and remand.

FACTS

On October 24, 1985, BDL Enterprises, Inc. (BDL) contracted with TSP Two, Inc. (TSP), an architectural firm, for TSP to provide architectural services for the design and construction of the Twin City Mall (Mall or project) in Lead, S.D. The project was to be conducted under a "fast track/design build" approach. Although this term was not defined within the contract, according to expert testimony, a fast track project is where the design and construction periods overlap. A design build project is where the design and construction functions are done by one entity.

On TSP's recommendation, BDL contracted with general contractor, R & S Construction Co. (R & S), on November 21, 1985. This contract also referred to the "fast-track system" of construction with supervision by TSP as the representative of BDL. Under the terms of the contract, R & S was to be reimbursed for total project costs including material, labor, subcontractor costs, sales taxes and all other costs, plus 7 1/2% of the total project cost for overhead and 4 1/2% for profit. The project was estimated to cost "somewhere in the neighborhood of $2,500,000." An exhibit attached to the contract attempted to define the scope of the project. The trial court found that it did not.

During the next seven months, BDL encountered numerous problems in negotiating and securing financing, defining the scope and size of the project, and locating and securing potential tenants, including its anchor tenant, Nash-Finch. Several design and construction schedules were not met and TSP was forced to redraw plans due to the changes BDL was continually making. Because of these, and numerous other problems, BDL temporarily shut the project down in February, 1986.

On July 3, 1986, BDL and R & S entered into another construction contract. This contract purported to be a "stipulated sum" contract, but the trial court found it was not. Although this contract also attempted to define the scope of the project, it was based upon incomplete drawings and specifications. The trial court again found that the scope was not defined because it was not known at the time of contracting.

A budget was attached to the contract which provided for "internal line item adjustments." This phrase, however, and its applicability to the project, was not defined. BDL testified that it believed a maximum price of $2,414,363 was guaranteed. R & S testified that, according to its understanding, it was only liable for the unit prices it had bid. The contract also contained change order provisions. Written change orders were not issued until many of the changes were made and the work completed. This was after the project had exceeded its budget.

During the construction phase, problems developed and the scope of the project changed substantially. BDL's delays and revisions resulted in added costs which were termed "internal line item adjustments." TSP prepared over 31 separate site plans due to the changing requirements of BDL. The trial court found that due to BDL's delay, indecision, and revision of the project, TSP was always behind with the necessary plans, which were found deficient at times. The trial court found that the project was behind schedule even before it started, assigning fault to both BDL and TSP. This, in turn, delayed the construction by R & S and substantially increased the costs of completing the project.

PROCEDURAL HISTORY

R & S sued BDL for breach of contract or recovery in quantum meruit, asking for damages of $438,809 and prejudgment interest. R & S also sued TSP for negligence in the design of the project and in preparation of the contract documents. R & S dismissed this claim against TSP following the trial.

TSP cross-claimed against BDL for indemnity, a balance due of $54,637.29, architectural fees of 4.565% of the cost of extra work by R & S, and prejudgment interest. TSP's indemnity claim against BDL became moot when R & S dismissed its action against TSP.

BDL denied the claims of R & S and counterclaimed for breach of contract, seeking $786,815.88 in damages against R & S. BDL also denied the cross-claim of TSP and counterclaimed for breach of contract for architectural services and negligence in the design and preparation of the project plans. BDL sought indemnification by TSP for the claims of R & S.

The trial court found R & S entitled to quantum meruit against BDL in the sum of $375,627.18, plus prejudgment interest. TSP recovered $25,572.11 for extra work, $13,519.22 for increased construction, and prejudgment interest against BDL. This award was reduced by TSP's share of the expenses of winter heat and snow and muck removal and TSP's pro rata share of overhead, excise taxes, and loss of profits. The trial court held for BDL on its cross-claim against TSP for breach of contract and awarded BDL $29,411.16 for damages, $17,819 for TSP's share of the repair work, and prejudgment interest. R & S and BDL reached a settlement after the filing of the Notice of Appeal.

BDL raises three issues on appeal:

1. Whether damages recovered by R & S for construction delays and extra work should be allocated between BDL and TSP.

2. Whether TSP is entitled to additional fees for increased construction costs attributable to its own negligence.

3. Whether TSP is liable to BDL for additional overhead, excise taxes and lost profits.

STANDARD OF REVIEW

The standard of review of a trial court's findings of fact is set forth in SDCL 15-6-52(a):

[T]his court shall not set aside findings of fact unless found to be clearly erroneous and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses.... In applying the clearly erroneous standard we must bear in mind that our function is not to decide factual issues de novo. The question for the appellate court is not whether it would have made the same findings the trial court did, but whether on the entire evidence it is left with a definite and firm conviction that a mistake has been committed.

Ex rel. A.D., 416 N.W.2d 264, 267 (S.D.1987) (citations omitted). "A trial court's findings of fact and decision are presumed correct and we will not seek reasons to reverse." Insurance Agents, Inc. v. Zimmerman, 381 N.W.2d 218, 219 (S.D.1986) (citations omitted). Damage awards are in themselves, findings of fact, and are also reviewed under the clearly erroneous standard. Conclusions of law are reviewed de novo, Permann v. S.D. Dept. of Labor, Unemp. Ins. Div., 411 N.W.2d 113, 117 (S.D.1987), and must be supported by findings of fact. Knodel v. Bd. of Cty. Comm'rs of Pennington Cty., 269 N.W.2d 386, 390 (S.D.1978) (citation omitted).

TSP'S LIABILITY FOR DAMAGES

The trial court found that TSP was responsible with BDL for expenses of winter heat and snow and muck removal and a pro rata share of overhead, excise taxes, and loss of profits attributable thereto. No appeal was taken from this determination. The trial court refused to find TSP partially liable to R & S for damages arising out of the Nash-Finch space, the installation of 18-gauge steel, the increased height of the building, and the application of stucco during the winter months. The court felt that these claims "more directly reflect costs of labor and materials which enhance the Mall's value, and therefore, should be awarded against the owner." BDL claims this was error.

Nash-Finch Space

The trial court found BDL liable to R & S for an additional $56,952.95 of expense incurred by R & S to finish the interior of the Nash-Finch store. TSP had an equipment layout prepared by Nash-Finch in its possession prior to the signing of the contract between BDL and R & S. TSP failed to include it within the contract documents or make it available to R & S prior to the contract signing. BDL claims that TSP should be held liable to BDL for this mistake. Trial testimony indicated that R & S would have been able to accurately estimate the cost to finish the Nash-Finch space with the equipment layout. The trial court noted in its memorandum decision that

[t]he plans provided to R & S by TSP upon which the cost estimates were based were not complete and were not the best available. TSP had prepared an exhibit, the Nash-Finch plan and design, and failed to give it to R & S. As a result, very relevant information pertinent to the scope of the project was withheld from R & S at a crucial stage in the relationship between these parties. This, despite the fact that throughout all of the preliminary meetings, BDL was continuously stressing the project cost and budget.

Installation of 18-Gauge Wall Studs

R & S also claimed additional expense for the installation of 18-gauge metal wall studs. R & S had prepared the construction budget utilizing the estimated cost of...

To continue reading

Request your trial
8 cases
  • First Dakota Nat. Bank v. Maxon
    • United States
    • South Dakota Supreme Court
    • October 17, 1994
    ... ... 1987 on a contract for deed to J & J Hotels, Inc. (J & J), a corporation formed by Jack Schaefer ... Schaefer and John Parker that money unless you co-sign it." Maxon explained that "co-signing ... v. BDL Enterprises, 500 N.W.2d 628, 630 (S.D.1993); Insurance ... (quoting Stearns, Law of Suretyship § 6.3 (1951)). The Cooper ... ...
  • Guardianship of Rich, Matter of
    • United States
    • South Dakota Supreme Court
    • July 27, 1994
    ... ... R & S Construction v. BDL Enterprises, 500 N.W.2d 628, 630 (S.D.1993); In re Estate of ... only withdraw funds without liability to his co-depositor when in fact he is the real owner of ... Steele Const. Co., 368 N.W.2d 610, 614 (S.D.1985). Award of ... ...
  • Talley v. Talley
    • United States
    • South Dakota Supreme Court
    • July 16, 1997
    ... ... the instruments as one contract." GMS, Inc. v. Deadwood Social Club, Inc., 333 N.W.2d 442, ... Thurston v. Cedric Sanders Co., 80 S.D. 426, 429-30, 125 N.W.2d 496, 498 ... R & S Construction Co. v. BDL Enterprises, 500 N.W.2d 628, 630 (S.D.1993); Insurance ... ...
  • Appeal of Sioux Valley Hosp. Ass'n
    • United States
    • South Dakota Supreme Court
    • March 16, 1994
    ... ... SDCL 15-26A-48; Sioux Enterprises v. Tri-State Refining, 456 N.W.2d 774, 777 ... Wolff v. Royal Ins. Co. of America, 472 N.W.2d 233 (S.D.1991); In re ... of tax payer right." Matter of Pam Oil, Inc., 459 N.W.2d 251, 255 (S.D.1990). We do not ... ...
  • Request a trial to view additional results
1 books & journal articles
  • Design-build Contracts for Colorado Highway Construction: New Contractual Issues-part I
    • United States
    • Colorado Bar Association Colorado Lawyer No. 29-2, February 2000
    • Invalid date
    ...27. 21. Rubin and Wordes, "Risky Business," 14 J. of Mgmt. in Engineering, No. 6 (Nov./Dec. 1998) at 36, 40. 22. Id. at 37. 23. Id. 24. 500 N.W.2d 628 (S.D. 25. See, e.g., "South Carolina Department of Transportation, Project Scope, Widening of SC Route 170" at 3 (June 9, 1999), available f......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT