Reedy Creek Imp. Dist. v. State Dept. of Environmental Regulation

CourtFlorida District Court of Appeals
Writing for the CourtJOANOS
CitationReedy Creek Imp. Dist. v. State Dept. of Environmental Regulation, 486 So.2d 642, 11 Fla. L. Weekly 814 (Fla. App. 1986)
Decision Date04 April 1986
Docket NumberNo. BG-279,BG-279
Parties11 Fla. L. Weekly 814 REEDY CREEK IMPROVEMENT DISTRICT, Appellant, v. STATE of Florida DEPARTMENT OF ENVIRONMENTAL REGULATION and Central Florida Utilities, Inc., Appellees.

Philip S. Parsons and Joseph W. Landers, Jr. of Landers, Parsons and Uhlfelder, Tallahassee, for appellant.

B.J. Owens and Deborah A. Getzoff, Asst. Gen. Counsel, State Dept. of Environmental Regulation, Tallahassee, for appellees.

Kathryn G.W. Cowdery and B. Kenneth Gatlin of Gatlin, Woods, Carlson and Girtman, Tallahassee, for appellee/cross appellant.

JOANOS, Judge.

This is an appeal and cross appeal from a final order entered by the Department of Environmental Regulation (DER) awarding a construction permit to Central Florida Utilities, Inc. (CFU). Reedy Creek Improvement District (RCID) presents two issues for our review: (1) whether equitable estoppel should apply to require or justify issuance of a permit to CFU, and (2) whether DER erred in rejecting conclusion of law number six relating to compliance with water quality standards and permitting requirements. The issue raised by CFU on cross appeal is whether RCID's appeal must be dismissed for lack of subject matter jurisdiction. We affirm.

The issues presented here had their inception with an enforcement action initiated by DER against Service Facilities, Inc. (subsequently purchased by CFU). In an order dated April 21, 1981, the Circuit Court of Osceola County found that the utility's Camelot Manor South sewage treatment plant had caused pollution by discharging effluent into the surface waters of Shingle Creek/Lake Tohopeliga Basin in violation of Section 403.161, Florida Statutes, a prior consent order and DER permit. CFU was directed to submit a complete application including designs, plans and schedule of implementation for an alternative system of effluent disposal. In the same order, DER was directed to expedite the application. In addition, the Circuit Court order required CFU to complete construction within fifteen months and expressly barred CFU from discharging any effluent into the Shingle Creek Basin after that fifteen month period.

In July 1982 CFU petitioned DER for dissolved oxygen (DO) alternative criteria and allowance of a mixing zone, if appropriate. With the petition was a report prepared by Dr. Crisman of the University of Florida Department of Environmental Engineering Sciences. This report indicated that Bonnett Creek, the waterway designated on CFU's application to receive the discharge from its new facility, was a waterway of extremely poor water quality. In Dr. Crisman's opinion, sewage discharge into Bonnett Creek, especially above the control structure, would have little detrimental impact on the stream system. Dr. Crisman emphasized, however, that his judgment was based solely on limited field data collected in a limited time frame.

On August 2, 1982, CFU applied to DER for a construction permit authorizing CFU to modify its Camelot Manor sewage treatment facility from 0.5 million gallons per day (MGD) capacity to a 1.5 MGD advanced water treatment (AWT) facility, which would discharge effluent into a manmade box cut canal portion of Bonnett Creek. DER issued notice of proposed agency action on September 23, 1982, and published notice of its proposed agency action in a local newspaper on September 29, 1982. No timely objections were filed, and on October 15, 1982, DER issued the requested permit to CFU. Pursuant to DER's approval of and agreement with RCID as a local pollution control program, a copy of the permit was sent to RCID as well as to CFU. 1

On November 3, 1982, RCID filed a petition for a formal administrative hearing to contest the issuance of the permit and a motion to stay the effect of the permit. CFU filed a motion to dismiss RCID's petition as untimely and a response to RCID's request for a stay. DER denied the motion for a stay, and transferred RCID's petition to the Department of Administrative Hearings (DOAH). After a hearing on the motion to dismiss, DER adopted the DOAH recommended order and dismissed the petition. RCID then filed notice of appeal with this court RCID took the position that since DER failed to provide it with a copy of CFU's application and afford it the opportunity to make written comments thereon, the proceeding should be started anew, thus allowing RCID to participate in proposed agency action pursuant to its agreement. This court agreed, and remanded the proceeding to DER with directions to furnish RCID a copy of the application, to allow RCID to participate in the permitting process by offering comments on the application and, if RCID had concerns about the proposed agency action, to contest the agency action in a formal evidentiary hearing. Reedy Creek Improvement District v. DER, 447 So.2d 313 (Fla. 1st DCA 1984).

DER, in compliance with the court's mandate, afforded RCID an opportunity to submit written comments regarding CFU's application for a permit. In those written comments, RCID concluded that--

The great weight of data, analysis and modeling show that water quality standards cannot be achieved following the proposed discharge by CFU. A site specific alternative criteria has not been justified, and even if granted, the applicant's own analysis shows it will not be achieved. For these reasons, Reedy Creek Improvement District opposes any action by the Department which will allow discharge into Bonnett Creek from the facilities proposed by CFU.

On March 28, 1984, DER noticed its intent to issue a permit to CFU which contained provisions and conditions nearly identical to those contained in the 1982 permit. On April 10, 1984, RCID petitioned for a formal administrative hearing pursuant to Section 120.57, Florida Statutes.

On July 20, 1984, shortly before the scheduled hearing, DER issued a notice of modification proposing to amend specific conditions 4 and 5 of the original permit and to add new specific conditions 9, 10, and 11--imposing more stringent effluent limitations and establishing lower discharge flows while the construction permit remained in effect.

The final hearing was held on July 24-26, 1984, and August 13, 14, 22 and 28, 1984. Evidence adduced at the hearing established that CFU entered into contracts obligating the Camelot Manor Plant to provide additional service and that it obtained $3 million in industrial development bonds to finance its advanced wastewater treatment plant. CFU's vice-president acknowledged that the bond obligations and service obligations were incurred after and with full knowledge that RCID had appealed DER's final order issuing the construction permit. He explained that the company was under a circuit court order to build a treatment facility within a specified time period, and the state had granted the permit initially. While the company realized there was some risk attendant upon moving forward with financing and construction, the feeling among company officials was that the company had to comply with the judicial order.

The field testing performed in this case was abbreviated due to DER's response to the circuit court order to consider CFU's application on an expedited basis. After hearing testimony from various experts, including DER personnel, the hearing officer concluded the methodology employed by DER was flawed, partly because it tended to bias the results in favor of lower dissolved oxygen values in the stream, which values were based on inadequate data and assumed dissolved oxygen readings at depth intervals which were not actually measured. In its proposed order, DER conceded that certain deficiencies in the testing and analysis were present, but considered that sufficient data had been compiled to insure that CFU can operate temporarily without endangering the environment. DER took the position that during the interim testing period, CFU would conduct extensive testing and evaluation, and the effluent limitations would be modified if necessary when an operating permit was sought by CFU.

The hearing officer found only partial compliance with statutory and rule requirements, and recommended denial of CFU's application for a construction permit. DER's final order adopted the hearing officer's findings of fact and conclusions of law, with certain exceptions. First, DER rejected the hearing officer's conclusion of law that the special circumstances permitting equitable estoppel are not present in this case. In making this determination, the Secretary stated:

I have carefully considered the potential impacts on the environment, and particularly on the water quality of Bonnett Creek and downstream bodies of water. CFU has now completed construction of the AWT plant. Thus the only effect of issuing a construction permit at this time would be to allow CFU to operate for a limited period of time to test the plant. Before CFU can actually begin full scale operation, it must obtain an operation permit from the Department. In conjunction with processing the application for an operation permit, the Department may impose more stringent effluent limitations and require any changes in the design of the plant necessary to meet those limits and assure compliance with applicable water quality standards.

................................................................................

* * *

I further find that it is within the Department's discretion to consider the water quality benefits which will accrue to Shingle Creek as a result of redirecting the Camelot Manor discharge from Shingle Creek to Bonnett Creek. The Department must operate in the real world and must sometimes choose an option, due to exceptional circumstances, which, while perhaps not the most desirable solution for the long term, affords reasonable solution for a limited period of time.

Next, DER rejected the hearing officer's conclusion that the proposed effluent...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
11 cases
  • County of Brevard v. Miorelli Engineering, Inc.
    • United States
    • Florida Supreme Court
    • October 23, 1997
    ...validity of contract which was entered into by its agents without the authority to do so); Reedy Creek Improvement Dist. v. State Dept. of Envtl. Regulation, 486 So.2d 642, 647 (Fla. 1st DCA 1986) (estoppel applied against the State to require issuance of permit when facility relied on prel......
  • Dep't of Transp. v. CSX Transp., Inc.
    • United States
    • Florida District Court of Appeals
    • December 11, 2013
    ...apply to ‘transactions that are forbidden by statute or that are contrary to public policy.’ ” Reedy Creek Improv. Dist. v. State Dep't of Envtl. Reg., 486 So.2d 642, 647 (Fla. 1st DCA 1986) (quoting Montsdoca v. Highlands Bank & Trust Co., 85 Fla. 158, 95 So. 666, 668 (1923)). Here, the in......
  • International Jai-Alai Players Ass'n v. Florida Pari-Mutuel Com'n, JAI-ALAI
    • United States
    • Florida District Court of Appeals
    • May 1, 1990
    ...Sullivan v. Northwest Fla. Water Management Dist., 490 So.2d 140 (Fla. 1st DCA 1986); Reedy Creek Improvement Dist. v. State, Dept. of Envtl. Reg., 486 So.2d 642 (Fla. 1st DCA 1986); North Ridge Gen. Hosp., Inc. v. NME Hosps., Inc., 478 So.2d 1138 (Fla. 1st DCA 1985); Florida Police Benevol......
  • Ball v. Florida Podiatrist Trust
    • United States
    • Florida District Court of Appeals
    • May 7, 1993
    ...deference. Citizens of State of Florida v. Wilson, 568 So.2d 1267, 1271 (Fla.1990); Reedy Creek Improvement Dist. v. Department of Environmental Regulation, 486 So.2d 642, 648 (Fla. 1st DCA 1986). The regulatory framework in this case contrasts with section 440.57(5), Florida Statutes, whic......
  • Get Started for Free
1 books & journal articles
  • Legal theories & defenses
    • United States
    • James Publishing Practical Law Books Florida Causes of Action
    • April 1, 2022
    ...or that are contrary to public policy. Reedy Creek Improvement District v. State of Florida Department of Environmental Regulation , 486 So.2d 642, 647 (Fla. 1st DCA 1986). See also Montsdoca v. Highlands Bank & Trust Co. , 95 So. 666, 668 (Fla. 1923). 2. Exemptions: See Florida Statutes §§......