Reid v. MILES CONSTRUCTION CORPORATION
Decision Date | 11 September 1962 |
Docket Number | No. 16887.,16887. |
Citation | 307 F.2d 214 |
Parties | Gary H. REID and Trinity Universal Insurance Company, Appellants, v. MILES CONSTRUCTION CORPORATION and Great American Indemnity Company of New York (Defendants) and Banco Land Company et al. (Intervenors), Appellees. |
Court | U.S. Court of Appeals — Eighth Circuit |
William Andress, Jr., Dallas, Tex., made argument for appellants and A. L. Barber, of Barber, Henry, Thurman & McCaskill, Little Rock, Ark., with him on the brief.
Edward Lester and Robert Shults, of Wright, Lindsey, Jennings, Lester & Shults, Little Rock, Ark., made argument for appellees and filed brief.
Before VOGEL and RIDGE, Circuit Judges, and DEVITT, District Judge.
This is an appeal from a judgment of the District Court in favor of the defendants on their counterclaim for damages resulting from the claimed breach of a construction subcontract in connection with the building of a Capehart Housing Project at the Little Rock, Arkansas, Air Force Base.
Diversity of citizenship and the requisite amount in controversy are established.
One of the appellants, Gary H. Reid, a masonry subcontractor, originally instituted a declaratory judgment action against the prime contractor, Miles Construction Corporation, one of the appellees, to determine whether Miles had breached its subcontract by underpaying a progress payment.
Subsequently, the pleadings on both sides were amended so that Reid sought recovery of damages against Miles and its surety for the claimed breach of the subcontract, and Miles and its subsidiaries sought by counterclaim to recover against Reid and his surety for damages allegedly occasioned by Reid's refusal to complete the subcontract.
The District Court entered judgment for the defendants for the amount asserted in their counterclaim, representing the cost of completion of the subcontracts, plus, in the case of Trinity Universal Insurance Company, the statutory penalty of 12% and reasonable attorneys' fees. This appeal followed.
The principal issue is one of fact — who breached the contract, Reid or Miles? Judge Young, the trial Judge, found that Reid did. Here is his reasoning in support of that finding and of his determination as to the extent of damages, as set out in an unreported memorandum decision:
To continue reading
Request your trial-
In re Technology for Energy, Corp.
...since "penalty" often comes up in bond cases when it does not refer to the dollar amount of the bond. See, e.g., Reid v. Miles Const. Co., 307 F.2d 214 (8th Cir. 1962); Massachusetts Bonding & Ins. Co. v. United States, 97 F.2d 879 (9th Cir. 1938); Dean v. Seco Elec. Co., 35 Oh.St.3d 203, 5......
-
R.J. Bob Jones Excavating Contractor, Inc. v. Firemen's Ins. Co. of Newark, New Jersey
...on construction bonds. See, e.g., Ray Ross Constr. Co., Inc. v. Raney, 266 Ark. 606, 587 S.W.2d 46 (1979) (citing Reid v. Miles Constr. Corp., 307 F.2d 214 (8th Cir.1962), and Trinity Universal Ins. Co. v. Smithwick, 222 F.2d 16 (8th Cir.), cert. denied, 350 U.S. 837, 76 S.Ct. 74, 100 L.Ed.......
-
Vern Barnett Const. Co., Inc. v. J. A. Hadley Const. Co., Inc.
...on contractor's bonds by the Eighth Circuit Court of Appeals in Trinity universal Ins. Co. v. Smithwick, 222 F.2d 16 and Reid v. Miles Construction Corp., 307 F.2d 214, where the sureties contended that proper demand to justify allowance of penalty and attorney's fees had not been made. App......
-
Ray Ross Const. Co., Inc. v. Raney, 79-124
...contractor's bonds by the Eighth Circuit Court of Appeals in Trinity Universal Ins. Company v. Smithwick, 222 F.2d 16 and Reid v. Miles Construction Corp., 307 F.2d 214, where the sureties contended the proper demand to justify allowance of penalty and attorneys' fees had not been In holdin......