Riley Const. Co., Inc. v. Schillmoeller & Krofl Co.

Decision Date19 December 1975
Docket NumberNos. 50--52,s. 50--52
Citation236 N.W.2d 195,70 Wis.2d 900
PartiesRILEY CONSTRUCTION COMPANY, INC., Respondent, v. SCHILLMOELLER & KROFL COMPANY, Defendant, Argonaut Insurance Company, a Foreign Corporation, Appellant. ARNOLD P. JOHNSON, INC., Respondent, v. SCHILLMOELLER & KROFL COMPANY, INC., Defendant, Argonaut Insurance Company, a Foreign Corporation, Appellant. Stanley J. MATSON, Respondent, v. SCHILLMOELLER & KROFL COMPANY, INC., Defendant, Argonaut Insurance Company, a Foreign Corporation, Appellant.
CourtWisconsin Supreme Court

Arvid A. Sather, Madison, for appellant.

Phillips, Richards & Mayew, Kenosha, for respondents.

WILKIE, Chief Justice.

This appeal involves three summary judgments in favor of the plaintiff-subcontractors, Riley Construction Company, Arnold P. Johnson, Inc., and Stanley J. Matson, against the defendant-surety, Argonaut Insurance Company, on a payment bond given by the insurance company and the general contractor, Schillmoeller & Krofl Company, Inc.

Summary judgment should not have been granted. It was reversible error for the trial court to impose liability upon Argonaut as surety without even considering whether or not the principal under the bond, the general contractor, was liable for payment under the subcontract. Consideration of the general contractor's defense to liability under the subcontract would necessarily involve factual issues and, thus, make summary judgment an inappropriate remedy.

The general contractor entered into a contract on July 14, 1971, with the owner and developer of land located in Kenosha, Wisconsin. The contract provided for the construction of condominium apartments to be known as Harbor Villa. Subsequently, the general contractor made contracts with the three subcontractors for various work to be done on the project. The agreement with Riley was made on July 8, 1971; the agreement with Johnson, on July 21, 1971; and the agreement with Matson, on September 24, 1971. All three contracts contained the same provisions regarding payment:

'General Contractor agrees to pay Subcontractor, if Sub-contractor shall fulfill to the satisfaction of General Contractor and Architect and complete every agreement on its part herein contained, for the performance of the contract, price of . . . as follows:

"During the satisfactory progress of the work and after receipt of satisfactory evidence of Sub-contractor's payment for labor and material furnished by Sub-contractor, on or before the 10th day of each month, Ninety per cent (90%) of the value of labor and materials wrought into the building up to the 1st day of each month as estimated by General Contractor and subject to the approval of Architect, less aggregate amount of previous payments, if any, after such equivalent payment has been received by General Contractor from Owner. Final payment shall be due within thirty (30) days after completion of the building or project and after final payment is made by Owner to General Contractor. No claim for extras will be allowed unless authorized in advance in writing by General Contractor.'

The general contractor and the insurance company, as principal and surety, respectively, gave a payment bond on November 9, 1971, which provided in relevant part as follows:

'NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:

'. . .

'2. The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90 days) days after the date on which the last of such claimant's work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Owner shall not be liable for the payment of any costs or expenses of any such suit.'

The three subcontractors afterwards performed the work they had agreed to, and there is no question that it was completed according to the specifications of the subcontracts. However, the owner never paid the general contractor the full amount for this work. The general contractor, relying upon the subcontractual provision of no payment until equivalent amounts were received from the owner, in turn did not pay the subcontractors the full amount for their work.

On July 2, 1973, the three subcontractors, as claimants under the bond, commenced separate legal actions against the general contractor and the insurance company. Riley sought judgment in the amount of $54,579.43; Johnson, in the amount of $13,873.92; and Matson, in the amount of $6,310. These actions were consolidated for trial and the subcontractors were granted summary judgment against the insurance company alone.

I. Liability of the Surety.

In its answer to the complaint, and in its affidavit in opposition to the motion for summary judgment, the surety asserted the defense that it was not liable on the bond because the principal-general contractor was not liable on the subcontracts for the payment of which the bond was given. The basis of this defense was the subcontractual provision that payment was not to be made to the subcontractors until a certain time after it was received from the owner. The surety (as had the general contractor in its answer) argued that this provision established a condition precedent, and did not merely fix a time for payment. During the argument on the motion for summary judgment, the surety also offered to provide specific evidence at a later trial regarding the circumstances under which the subcontract was made, which would show that the general contractor and the subcontractor intended to share the risk of nonpayment by the owner.

The trial court, however, limited its consideration to the provisions of the surety bond. It refused to allow the surety to assert a defense which the general contractor had under the subcontracts, and to even consider these subcontracts or the liability of the general contractor thereunder. The basis for its grant of summary judgment was its interpretation of the surety bond, exclusive of the subcontracts it was given to secure. The trial court decided that the surety became absolutely liable for payment to the subcontractors after ninety days had passed without payment by the general contractors, irrespective of whether the general contractor was liable to the subcontractors under the subcontracts.

But the law of suretyship is to the contrary. Because the surety's obligation is derived from that of the principal debtor, the liability of the surety is ordinarily measured by the liability of the principal. If the principal is not liable to the claimant, then the surety is not liable either. In addition, the surety may normally set up any defense available to the principal. 1 Although Wisconsin has never enunciated these precise rules, cases decided in other jurisdictions have unanimously followed them. 2 In Wisconsin this court has long adhered to a rule which is thoroughly consistent with these rules, namely, that the bond and the contract which it secures should be construed together. 3 Thus, the conclusion is inescapable that the trial court erred in refusing to consider the subcontracts, the liability of the general contractor thereunder, and the defense of the general contractor, as asserted by the surety.

The trial court also erred in its interpretation of the surety bond itself. It construed the bond to mean that, if the claimants were not paid within ninety days after completion of the work, then the surety became automatically and absolutely liable for full payment, with no need for consideration of other matters. Section 2 of the bond makes it clear, however, that the passage of ninety days only confers upon the claimants the right to sue the principal or the surety or both. In this suit it must be determined whether the sums sought by the claimants are 'justly due.' While in most cases this would be a perfunctory matter involving only proof that the contract work had been completed, in the instant case it necessarily requires a determination of the validity of the general contractor's and surety's defense. In other words, it requires a decision as to whether the payment provisions of the subcontract create a condition precedent, or merely fix a time for payment. But this decision was not made or the matter considered by the trial court.

Our view of what the trial court should have done before entering judgment against the surety is also consonant with the procedure envisioned by the Wisconsin construction lien law. Sec. 289.035(1) of that law provides that the payment bond shall be conditioned for the payment of labor and material claims to every person 'entitled thereto.' Sub. (2), in a manner analogous to the payment bond in question here, provides in relevant part:

'Any party in interest may, not later than one year after the completion of the contract, maintain an action in his own name against the prime contractor and the sureties upon the bond...

To continue reading

Request your trial
16 cases
  • Koch v. Construction Technology, Inc.
    • United States
    • Tennessee Supreme Court
    • May 20, 1996
    ...380 (Tex.App.1990); Amelco Electric v. Donald M. Drake Co., 20 Wash.App. 899, 583 P.2d 648 (1978); Riley Constr. Co. v. Schillmoeller & Krofl Co., 70 Wis.2d 900, 236 N.W.2d 195 (1975).2 While the insolvency of the owner is probably the most common risk to which the subcontractor would be ex......
  • Capitol Steel Fabricators, Inc. v. Mega Construction Co.
    • United States
    • California Court of Appeals Court of Appeals
    • October 28, 1997
    ...380, 383-384; Amelco Elec. v. Donald M. Drake Co. (1978) 20 Wash.App. 899, 583 P.2d 648, 649-650; Riley Const. v. Schillmoeller & Krofl Co. (1975) 70 Wis.2d 900, 236 N.W.2d 195, 198-200; Rest.2d Contracts, § 227, & com. b, pp. However, the present case involves a subcontract which unambiguo......
  • Watson Const. Co. v. Reppel Steel & Supply Co., Inc.
    • United States
    • Arizona Court of Appeals
    • June 12, 1979
    ...389 N.Y.S.2d 348, 357 N.E.2d 1003 (1976) (subcontractor entitled to summary judgment). Contra Riley Construction Co., Inc. v. Schillmoeller & Krofl Co., 70 Wis.2d 900, 236 N.W.2d 195 (1975) (provisions ambiguous, therefore summary judgment not appropriate); Mascioni v. I. B. Miller, Inc., 2......
  • Maynard v. Port Publications, Inc.
    • United States
    • Wisconsin Supreme Court
    • October 28, 1980
    ...she cites College Mobile Home Park & Sales v. Hoffmann, 72 Wis.2d 514, 241 N.W.2d 174 (1976), and Riley Construction Co. v. Schillmoeller & Krofl Co., 70 Wis.2d 900, 236 N.W.2d 195 (1975). These cases were decided under the old summary judgment procedure, outlined in sec. 270.635, Stats., 1......
  • Request a trial to view additional results
2 books & journal articles
  • Table of Cases
    • United States
    • Washington State Bar Association Washington Construction Law Deskbook (WSBA) Table of Cases
    • Invalid date
    ...1984): 19.2(3)(a) WISCONSIN_________________________________________________________ Riley Constr. Co. v. Schillmoeller and Krofl Co., 70 Wis. 2d 900, 236 N.W.2d 195 (1975): 10.2(3) WYOMING__________________________________________________________ Anderson Excavating and Wrecking Co. v. Cer......
  • §10.2 Contract Provisions
    • United States
    • Washington State Bar Association Washington Construction Law Deskbook (WSBA) Chapter 10
    • Invalid date
    ...period of time after the work was completed. Id. at 903-04 (citing Riley [Page 10-5] Constr. Co. v. Schillmoeller and Krofl Co., 70 Wis. 2d 900, 236 N.W.2d 195 (1975)). There are no Washington cases that deal with or interpret "pay if paid" Contractors on Washington public projects must com......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT