Rio Rancho Estates, Inc. v. Beyerlein

Decision Date03 November 1981
Docket NumberNo. 80-1357,80-1357
Citation662 F.2d 700
PartiesRIO RANCHO ESTATES, INC. and Amrep Construction Corporation at Rio Rancho, Plaintiffs-Appellees, v. Gary T. BEYERLEIN and Robert Holmes, d/b/a Superior Builders, Defendants-Appellants.
CourtU.S. Court of Appeals — Tenth Circuit

Jerrald J. Roehl and Ronald W. Henkel, of Jerrald J. Roehl & Associates, Albuquerque, N. M., for plaintiffs-appellees.

Herbert A. Delap, of Shafroth & Toll, Denver, Colo., for defendants-appellants.

Before BARRETT and LOGAN, Circuit Judges, and CHILSON *, District Judge.

CHILSON, District Judge.

This action was commenced in the District Court for the County of Sandoval, New Mexico, on July 12, 1978, and was thereafter removed to this court on the ground of diversity of citizenship.

Plaintiff, Rio Rancho Estates, Inc., (Rio Rancho) was the owner and developer of a large tract of land located in Sandoval County, New Mexico. Plaintiff, Amrep Construction Corporation, (Amrep) was the general contractor for the construction of houses on the Rio Rancho land. Amrep subcontracted certain portions of the construction In February 1978, Amrep entered into four additional subcontracts, one for framing, one for concrete, one for plumbing, and one for painting of houses to be constructed in the Star Heights addition of the Rio Rancho development. It is the 1978 contracts which give rise to this litigation.

to the defendants, Beyerlein and Holmes, d/b/a Superior Builders (Superior) beginning in the summer of 1977. Between July 1977 and January 1978, Amrep and Superior entered into a number of subcontracts which were completed by Superior and accepted by plaintiffs.

In May 1978, Amrep, because of alleged poor quality of the work of the defendants under the 1978 framing contract, terminated the framing contract. The defendants then refused to continue the work under the other three contracts (concrete, plumbing, and painting) and filed 163 liens on various houses in the Star Heights Addition.

Thereupon, plaintiffs instituted this action to cancel the liens and for compensatory and punitive damages for the defendants' breach of these contracts.

Defendants counterclaimed for foreclosure of the liens and for compensatory and punitive damages.

After trial, the trial court made findings of fact and concluded that the plaintiffs were entitled to recover from defendants the sum of $102,936.72, and entered judgment in favor of the plaintiffs and against the defendants in that amount. The claims of both parties for punitive damages was denied.

Defendants appealed.

Defendants allege four grounds for reversal and remand for a new trial.

1. The trial court committed error by not making a factual determination as to the standard of acceptable work established by the course of dealings between the parties.

2. Plaintiffs' acceptance of defendants' work product is a bar to damages and renders plaintiffs' termination wrongful.

3. It was error to limit defendants' recovery for the reasonable value of labor and materials only to the amount actually claimed in their lien.

4. Plaintiffs did not follow the contractual provision which were a condition precedent to the recovery of back charges against the defendants.

The defendants' contentions should be considered in the light of the trial court's findings of fact and the rule of law which requires that the trial court's findings of fact shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses. Rule 52(a), Federal Rules of Civil Procedure; Raulie v. United States, 400 F.2d 487 (10th Cir. 1968) and Rudd Paint and Varnish Co. v. White, 403 F.2d 289 (10th Cir. 1968).

The pertinent part of the court's findings of fact are as follows:

It appears from the evidence that the Defendants were performing work for Plaintiffs as early as July 1, 1977. And from the period from July 1, 1977 to July 1, 1978, questions arose as to Defendants' ability to satisfactorily perform the contract projects assigned to them by Plaintiffs. It further appears that Defendants' workmanship substantially declined after January 1978.

The construction manager for Amrep inspected the construction project daily. He found that the framing was unacceptable. The walls were not plumbed, spaces remained around the doors, houses were out of level, and plates on the frames were not nailed. When money was held back by Plaintiffs because of these deficiencies, Defendants agreed to institute quality control, but this did not last too long.

The State Building Inspector, Herbert McClure, on inspection, found that the quality of Defendants' work was very poor. He also found framing and roof decks to be inferior. He cited constant trouble with the plumbing work. Finally, he red-tagged one house as representative A main complaint was the inadequacy of the headers installed by Superior. It is clear from the evidence that the Uniform Building Code does not specifically address the manner of installation of headers; that the standards for the installation of headers is left to the discretion of the inspecting official. Accordingly, the Court finds that the standards imposed by inspector McClure were not unreasonable.

of 80 houses with similar problems. These problems were not limited to crooked studs, unsquare corners, walls not plumbed, improperly installed headers and improper and faulty installation of plywood. He found shingles irregularly angled and improperly nailed. He met with Plaintiffs' representatives and ordered them to correct the same. Plaintiffs thereupon demanded corrective action of Defendants, but Defendants failed to respond. It was McClure's opinion, which is accepted by the Court, that Defendants' work did not meet the standard required of the industry in the community. McClure's opinion is supported by witness Bassett, a state building inspector, who also found Superior's work to be substandard.

It appears from the evidence that Defendants did not meet acceptable building standards as early as January, 1978. The job finally was shut down by Mr. McClure in April 1978, after his giving Defendants ample time to correct cited deficiencies. When Defendants were unable or unwilling to correct the deficiencies, Plaintiffs terminated the framing contract.

Defendants' own witness, Stan Adams, previously employed by Plaintiff, supported Plaintiffs' claim of poor workmanship. Adams cited lack of supervision by Superior as the cause of 'very bad construction.' This is further borne out by evidence that Holmes was responsible for the day-to-day operation; and that he spent only about 20-50% of his time in New Mexico. And it also was Adams' testimony that the contract was terminated because of Defendants' inability to perform because of lack of manpower. Adams stated that he terminated the contract with Defendants because their work was not getting any better and that Plaintiffs could not put up with the poor workmanship of Defendants.

After Plaintiffs terminated the framing contract on approximately May 22, 1978, Superior abandoned the job site. Defendant Holmes justifies the abandonment on the basis that the remaining contracts would prove unprofitable without the framing contract.

DEFENDANTS' FIRST CONTENTION

Defendants contend the trial court committed error in failing to make a factual determination of the standard of acceptable work established by the course of dealings of the parties, including the quality of the work accepted by plaintiffs under the 1977 contracts.

In its findings, the trial court reviewed the course of the dealings of the parties which consisted of a number of subcontracts entered into in 1977 and the last series of subcontracts entered into in 1978.

In the 1977 and 1978 contracts, defendants warranted "that all work under the subcontract shall be of good quality." The 1977 contracts were completed, paid for, and plaintiffs make no claim in this action that the work performed under the 1977 contracts was not of good quality.

Neither the pleadings nor the pre-trial order discloses that any party claimed that the work performed under the 1977 contracts was not of good quality nor do the defendants cite any evidence raising such an issue during the course of the trial.

We conclude that upon the record before it, the trial court's findings were sufficient.

SECOND CONTENTION

Defendants' second contention is that the plaintiffs accepted defendants work under both the 1977 and 1978 contracts and by such acceptance are barred from recovery of damages for the poor quality and defective workmanship found by the trial court.

As a basis for this contention, defendants state in their brief:

The clear weight of the evidence showed that in one of the trades, framing, Superior's performance was poor throughout the entire period prior to termination. Amrep continued to pay for all of Superior's work in all trades. This continued for ten months. Amrep's acceptance of this performance operated as a promise, by Amrep, to pay for all work done by Superior.

Contrary to the foregoing statement, the evidence is overwhelming that Amrep did not accept and did not pay for all of the work that was performed under the 1978 contracts.

The trial court found that defendants' workmanship substantially declined after 1978 and in its findings specifically pointed out the work which was defective.

Amrep refused to accept and pay for the defective work and demanded that the defendants correct it. Amrep's refusal to accept and pay for the defective work led to defendants' filing liens on plaintiffs' property and this litigation.

The trial court was...

To continue reading

Request your trial
9 cases
  • In re Strong, Bankruptcy No. 01-35854F.
    • United States
    • U.S. Bankruptcy Court — Eastern District of Pennsylvania
    • August 31, 2004
    ... ... a prior mortgage loan that the plaintiffs had with Parkway Mortgage, Inc. ("Parkway") 1 N.T. at 87; Ex. Tab-34. 4 The plaintiffs primarily sought ... on the issue and could have offered rebuttal evidence); Rio Rancho Estates, Inc. v. Beyerlein, 662 F.2d 700, 704-05 (10th Cir.1981) ... ...
  • Geffner v. Linear Rotary Bearings, Inc.
    • United States
    • U.S. District Court — Eastern District of New York
    • September 1, 1996
    ... ... 9 See supra Findings of Fact ¶¶ 10-11; Rio Rancho Estates, Inc. v. Beyerlein, 662 F.2d 700, 705 (10th Cir.1981); Save Lake Washington v. Frank, ... ...
  • Johnson v. U.S. Comm'r, CIVIL ACTION NO. 6:17-1371
    • United States
    • U.S. District Court — Western District of Louisiana
    • February 11, 2019
  • Johnson v. Berryhill
    • United States
    • U.S. District Court — District of South Carolina
    • February 19, 2019
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT