Romero Excavation and Trucking, Inc. v. Bradley Const., Inc.

Decision Date20 February 1996
Docket NumberNo. 22714,22714
Citation913 P.2d 659,1996 NMSC 10,121 N.M. 471
PartiesROMERO EXCAVATION AND TRUCKING, INC., Plaintiff-Appellee, v. BRADLEY CONSTRUCTION, INC., Defendant-Appellant.
CourtNew Mexico Supreme Court
OPINION

FROST, Justice.

¶1 This interlocutory appeal addresses an issue of first impression in New Mexico: Whether a general contractor for a state construction project violated the New Mexico Subcontractors Fair Practices Act, NMSA 1978, §§ 13-4-31 to -42 (Repl.Pamp.1992) 1 [hereinafter the Act], when it substituted itself for the subcontractor listed in the bid submitted to the State. The district court found no material issues of fact in dispute and concluded as a matter of law that the general contractor, Defendant-Appellant Bradley Construction, Inc. (Bradley), violated the Act when it substituted itself for the subcontractor, Plaintiff-Appellee Romero Excavation and Trucking, Inc. (Romero). We conclude that Bradley's actions did violate the Act.

I. FACTS

¶2 In 1991 New Mexico State University (NMSU) solicited bids to build a vocational student services building in Alamogordo. Bradley successfully bid for the general contract. Section 13-4-34(A) of the Act requires contractors to list for each subcontractor, the name, location, and nature of work to be performed. Thus, in its bid to NMSU Bradley listed Romero as the subcontractor that would perform the earthwork on the project. Romero had submitted a subcontractor bid to Bradley for the earthwork, which conformed with the manner of excavation and fill Romero had performed for Bradley in the past on other projects. Bradley and Romero did not execute a written subcontract. After NMSU awarded Bradley the general contract, Bradley determined that the NMSU project would require a different, more costly method of excavation and fill. Bradley consequently decided to perform the earthwork itself. It notified NMSU in writing of its intention, but it never received a response from NMSU, nor did it obtain NMSU's affirmative approval of the change. Bradley nonetheless proceeded to perform the earthwork.

¶3 In 1992 Romero filed a civil complaint against Bradley, alleging both that Bradley had breached a contract with Romero and that Bradley had violated the Act. The parties filed stipulated facts and cross-motions for partial summary judgment on the issue of liability. The district court granted partial summary judgment for Romero. In February 1995 the district court certified for interlocutory appeal the question whether Bradley had violated the Act by substituting itself for Romero on the public works contract. We granted Bradley's application for appeal under the New Mexico provisions governing interlocutory appeals, NMSA 1978, § 39-3-4 (Repl.Pamp.1991) and SCRA 1986, 12-203 (Repl.Pamp.1992). We affirm.

II. STANDARD OF REVIEW

¶4 " 'Summary judgment is proper if there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law.' If the facts are undisputed and only a legal interpretation of the fact remains, summary judgment is the appropriate remedy." Board of County Comm'rs v. Risk Management Div., 120 N.M. 178, 179, 899 P.2d 1132, 1133 (1995) (citation omitted) (quoting Koenig v. Perez, 104 N.M. 664, 665, 726 P.2d 341, 342 (1986)). In this case, partial summary judgment was proper because the facts regarding liability were undisputed. The parties stipulated to the facts and, on review, are bound by the facts as stipulated. See Haaland v. Baltzley, 110 N.M. 585, 588, 798 P.2d 186, 189 (1990) ("Facts stipulated to are not reviewable on appeal.").

¶5 Consequently, we review the trial court's decision to determine whether Romero was entitled to judgment as a matter of law. "The meaning of statutory language is a matter of law, not a question of fact." Dynacon, Inc. v. D & S Contracting, Inc., 120 N.M. 170, 177, 899 P.2d 613, 620 (Ct.App.1995) (interpreting the Act). We need not defer to the trial court's conclusions of law. C.R. Anthony Co. v. Loretto Mall Partners, 112 N.M. 504, 510, 817 P.2d 238, 244 (1991). Instead, we determine whether the trial court correctly applied the law to the facts of the case. Sunwest Bank, N.A. v. Colucci, 117 N.M. 373, 375, 872 P.2d 346, 348 (1994). We conclude that in this case the trial court was correct.

III. INTERPRETATION OF THE ACT

¶6 We first must interpret the Act to determine its meaning and underlying legislative intent. At the outset, we note, "When reviewing statutes, our primary goal is to give effect to the intent of the legislature." Draper v. Mountain States Mut. Casualty Co., 116 N.M. 775, 777, 867 P.2d 1157, 1159 (1994). To this end, "[w]e examine the act in its entirety, construing each section in connection with every other section." Id.

¶7 The New Mexico Legislature enacted the Act in 1988. See 1988 N.M. Laws, ch. 18. In the Act, the legislature set out the following finding, which provides insight into the legislative intent:

The legislature finds that the practices of bid shopping and bid peddling in connection with the construction, alteration and repair of public works projects often result in poor quality of material and workmanship to the detriment of the public, deprive the public of the full benefits of fair competition among contractors and subcontractors and lead to insolvencies and loss of wages to employees.

Section 13-4-32.

¶8 Although the Act itself does not define the evils of bid shopping and bid peddling, the Court of Appeals, when interpreting the Act, explained:

By requiring prime contractors who bid on a public works project to disclose the subcontractors they will use on the project, the Act restricts the practices known as bid shopping and bid peddling. "Bid shopping is the use of the low bid already received by the general contractor to pressure other subcontractors into submitting even lower bids. Bid peddling, conversely, is an attempt by a subcontractor to undercut known bids already submitted to the general contractor in order to procure the job."

Dynacon, 120 N.M. at 171, 899 P.2d at 614 (quoting Southern Cal. Acoustics Co. v. C.V. Holder, Inc., 71 Cal.2d 719, 79 Cal.Rptr. 319, 325 n. 7, 456 P.2d 975, 981 n. 7 (Cal.1969) (en banc)); see also Tekton, Inc. v. Builders Bid Serv., Inc., 676 F.2d 1352, 1353 n. 1 (10th Cir.1982) (defining bid shopping and bid peddling).

¶9 Dynacon is the only reported New Mexico case interpreting the Act. While its holding is not dispositive of this case, it does offer persuasive support for our holding. Dynacon concerned a school construction proposal that consisted of two different projects or "lots," each requiring separate bids. The school asked for bids on Bid Lot 1 alone and also for bids on Bid Lots 1 and 2 combined. Apparently the general contractor in Dynacon would have used a roofing subcontractor named Dynacon if it won both lots, but a different roofer named Frontier if it won only the first lot. However in its bid it listed only Dynacon. The general contractor was awarded Bid Lot 1 alone and sought to have Dynacon replaced by Frontier. Dynacon, 120 N.M. at 173, 899 P.2d at 616.

¶10 The Court of Appeals concluded that, under the Act, the general contractor could have listed both Frontier and Dynacon in its original bids and then specified that Dynacon would do the roofing if both lots were awarded and that Frontier would be the roofer if only the first lot were awarded. Id. at 174, 899 P.2d at 617 (discussing Section 13-4-34(A)(2)). However, the Court decided that the Act preludes the substitution of one subcontractor for another, after the bid is awarded, except under specific enumerated circumstances. See § 13-4-36(A). In other words, under the facts of Dynacon, Frontier could replace Dynacon only if both subcontractors were listed in the original bid; because only Dynacon was named, and because none of the enumerated circumstances applied, the contractor could only use Dynacon as its roofing subcontractor. Dynacon, 120 N.M. at 174-76, 899 P.2d at 617-19 (discussing Section 13-4-36(A)(5)). Thus Dynacon stands for the general principle, applicable in this case, that, once a bid has been awarded, a general contractor may not insert a substitute for a subcontractor except with using agency consent and for statutorily enumerated reasons.

¶11 The Act requires "[a]ny person submitting a bid" to list "each subcontractor under subcontract to the contractor" who will work on the public works construction project. Section 13-4-34(A). Under the Act, " 'contractor' means the prime contractor on a public works construction project who contracts directly with the using agency," and " 'subcontractor' means a contractor who contracts directly with the contractor." Section 13-4-33(A), (B). The Act also provides, "The contractor shall list only one subcontractor for each category as defined by the contractor in his bid." Section 13-4-34(A). If a contractor does not list a subcontractor for a particular portion of the work, then the general contractor shall perform that work itself. Section 13-4-38. Thus, the Act prevents bid shopping and bid peddling by forcing the contractor to commit, when it submits its bid to the using agency, either to use a specified subcontractor or to perform the work itself. Under the Act, " 'using agency' means any state agency or local public body requiring services or construction." Section 13-4-33(E).

¶12 The Act further prevents bid shopping and bid peddling by prohibiting the contractor from making subcontractor substitutions after the using agency accepts the contractor's bid. Once the using agency accepts a contractor's bid, the Act requires that no contractor:

shall substitute any person as subcontractor in place of the subcontractor listed in...

To continue reading

Request your trial
31 cases
  • Presidential Hospitality, LLC v. Wyndham Hotel Grp., LLC
    • United States
    • U.S. District Court — District of New Mexico
    • July 2, 2018
    ...... limited liability company; Ace Development, Inc., a New Mexico Corporation and Sam Blue, ...-interest considerations." Atlantic Marine Const. Co., Inc. v. U.S. Dist. Court for Western Dist. ..., development, engineering services, excavation or other improvement to real property including ... See Romero Excavation and Trucking, Inc. v. Bradley Const., ......
  • Morris v. Brandenburg, Docket No. 33,630
    • United States
    • Court of Appeals of New Mexico
    • August 11, 2015
    ...(internal quotation marks and citation omitted)); Romero Excavation & Trucking, Inc. v. Bradley Constr., Inc., 1996-NMSC-010, ¶ 5, 121 N.M. 471, 913 P.2d 659 (stating that the appellate court does not defer to district court's legal conclusions but "determine[s] whether the [district] court......
  • Morris v. Brandenburg, 33,630
    • United States
    • Court of Appeals of New Mexico
    • August 11, 2015
    ...(internal quotation marks and citation omitted)); Romero Excavation & Trucking, Inc. v. Bradley Constr., Inc.,Page 1391996-NMSC-010, ¶ 5, 121 N.M. 471, 913 P.2d 659 (stating that the appellate court does not defer to district court's legal conclusions but "determine[s] whether the [district......
  • Morris v. Brandenburg
    • United States
    • Court of Appeals of New Mexico
    • August 11, 2015
    ...appeal” (internal quotation marks and citation omitted)); Romero Excavation & Trucking, Inc. v. Bradley Constr., Inc., 1996–NMSC–010, ¶ 5, 121 N.M. 471, 913 P.2d 659 (stating that the appellate court does not defer to district court's legal conclusions but “determine[s] whether the [distric......
  • Request a trial to view additional results
1 books & journal articles
  • Setting Up for a Successful Project: Subcontractor Bidding Issues
    • United States
    • ABA General Library The Construction Lawyer No. 40-1, January 2020
    • January 1, 2020
    ...was unauthorized as inconsistent with the purpose of the New Mexico statute. Romero Excavation & Trucking, Inc. v. Bradley Constr., Inc., 121 N.M. 471, 475 (1996). 69. CAL. PUB. CONT. CODE § 4106. 70. See, e.g ., N.M. STAT. ANN. § 13-4-34; NEV. REV. STAT. ANN. § 338.141; OR. REV. STAT. ANN.......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT