Roost Project, LLC v. Andersen Constr. Co.

Decision Date04 February 2020
Docket NumberCase No. 1:18-cv-00238-CWD
Citation437 F.Supp.3d 808
Parties The ROOST PROJECT, LLC, a California limited liability company, Plaintiff/Counterdefendant, v. ANDERSEN CONSTRUCTION COMPANY, an Oregon corporation, Defendant/Counterclaimant.
CourtU.S. District Court — District of Idaho

Bradley J. Dixon, Kersti Harter Kennedy, Givens Pursley LLP, Boise, ID, for Plaintiff/Counterdefendant.

Christopher P. Graham, Brassey Crawford, PLLC, Boise, ID, Steven Zwierzynski, Seifer, Yeats, Zwierzynski & Gragg, LLP, Portland, OR, for Defendant/Counterclaimant.

MEMORANDUM DECISION AND ORDER

Honorable Candy W. Dale, United States Magistrate Judge

INTRODUCTION

This case involves a dispute regarding the respective rights, obligations, and liabilities of the parties arising out of and relating to construction of The Fowler building in downtown Boise, Idaho. The Roost Project, LLC (Roost) and Andersen Construction Company (ACCO) entered into a contract (the Construction Agreement) to build The Fowler in December 2015. The project was delayed for a host of different reasons resulting in The Fowler being finished eight months after the initial contract completion date. As a result, Roost initiated this action against ACCO raising contract and tort claims. ACCO denies those claims and has filed counterclaims against Roost.

Presently before the Court are the parties cross motions for partial summary judgment, Roost's motion to amend the complaint to add punitive damages, and ACCO's motion to strike. The motions are fully briefed. The Court conducted a hearing on December 12, 2019. After careful consideration of the record, the parties' briefing and supporting materials, and oral argument, the Court finds there are several genuine issues of material fact in this case which preclude summary judgment. The Court will therefore deny both summary judgment motions. The Court will also deny the motion to add punitive damages. The motion to strike will be granted in part and denied in part.

FACTS1
1. The Construction Agreement

On December 11, 2015, Roost and ACCO entered into the Construction Agreement to build The Fowler, a mixed-use building predominately developed as a residential apartment complex. (Dkt. 10-1.) The substantial completion date for the project was in June 2017. (Dkt. 10-2, Ex. B.) The project broke ground on February 5, 2016, and was substantially completed on February 21, 2018, eight months after the contract completion date. The parties disagree over which party breached and which party performed under the Construction Agreement and whether either party is otherwise liable for or entitled to damages outside of the contract.

Roost contends ACCO breached several terms of the Construction Agreement and is not entitled to any relief. Generally, Roost argues ACCO failed to deliver the project on time and failed to provide the project schedule updates, reports, and notices required by the Construction Agreement. Further, Roost argues ACCO mismanaged the project, misrepresented the project's status, and concealed information about the project from Roost. ACCO disputes Roost's claims, countering that it performed under the terms of the Construction Agreement, did not misrepresent or conceal information, properly managed the project, and that Roost failed to act in good faith by refusing to approve changes and equitable adjustments to the project schedule.

Several provisions of the Construction Agreement are implicated by the parties' positions in this case. The following are particularly relevant.

A. Contractor's General Representations and Warranties

Section 5.9 states, in relevant part:

Contractor makes the following express representations and warranties to Owner, which are continuing during the term of this Agreement:
5.9.2 Contractor has thoroughly and carefully examined the Contract Documents (as a contractor, not a licensed design professional), and has found them to be complete, coordinated and suitable for Contractor's performance of the Work in accordance with this Agreement.
5.9.3 Contractor has thoroughly and carefully examined the Project Schedule and has found it to be complete and to provide suitable time for Contractor's performance of the Work in accordance with this Agreement.
5.9.6 Contractor is familiar with the local and other conditions which may be material to Contractor's performance of its obligations under the Contract Documents (including, but not limited to transportation, seasons and climates, access, the handling and storage of materials and fuel and availability and quality of labor and materials). Contractor has thoroughly and carefully examined the market conditions related to the Work, including the availability and pricing of materials, labor, supplies and all other things necessary for the performance of the Work and found them to be adequate for Contractor to perform the Work as provided in the Contract Documents.

(Dkt. 10-1 at § 5.9.)

B. Project Schedule Notifications, Delays, and Changes

The Construction Agreement states that ACCO will keep Roost "fully informed of Contractor's performance of the Work so Owner can have timely and meaningful opportunities to review and input" and "Contractor will promptly notify Owner of any actions or decisions required of Owner for Contractor to timely and properly perform the Work, and any deadlines pertaining thereto to prevent delays in the Work." (Dkt. 10-1 at § 5.2.1 and § 5.2.2.) Article 8.1 addresses the project schedule, stating:

Contractor will commence performance of the Work upon Owner's notice to proceed and will diligently and expeditiously continue its performance until all Work has been fully completed. The dates in the Project Schedule are of the essence and will not be exceeded by Contractor without Owner's prior consent or as permitted in Section 8.3.2. If and when Contractor has reason to believe that any date in the Project Schedule may not be met, Contractor will make appropriate recommendations to Owner to keep the Work on schedule, bring the Work back on schedule and/or mitigate potential impacts of a delayed performance. Contractor represents and warrants to Owner that the Substantial Completion Deadline provides a reasonable time for completing the entire Work, including the time specified for the review of Contractor Submittals by Owner and Governmental Authorities.

Delays and extensions of time to the project schedule are covered by Article 8.3 which requires the Contractor to diligently avoid delays in timely performance and to immediately notify the Owner of any matter wholly or partially preventing or delaying timely performance and provide regular reports concerning the same. (Dkt. 10-1 at § 8.3.1.) Section 8.3.2, in particular, sets for the process for the Contractor to make a claim for an equitable adjustment to the project schedule where "the critical path of the Contractor's performance is wholly or partially prevented or delayed due to" certain listed circumstances. (Dkt. 10-1 at § 8.3.2.)

Changes in the work by the Owner are addressed in Article 10 of the Construction Agreement which sets forth the procedures for change orders and change directives. (Dkt. 10-1 at § 10.2, § 10.3.) Article 17 covers resolution of claims, setting forth the process for the Contractor to make a claim and setting forth the parties' rights and responsibilities in resolving a claim.

2. Construction of The Fowler

Between groundbreaking in February 2016 and July 2016, ACCO's superintendent, Tom Hayes, provided project schedule updates to Roost on February 16, March 28, April 22, and June 27. Hayes provided a master schedule update on July 20, 2016 which reported a new substantial completion date of June 16, 2017, a delay of a few days from the original contract completion date. ACCO attributed the delay to problems with the project's design and the concrete subcontractor's lack of adequate manpower and quality control issues. (Dkt. 40 at 9-12.)

Roost alleges the project schedule, from its inception, was not buildable and the Hayes updates made unrealistic predictions, did not provide the information required by the Construction Agreement, and concealed the true status of the project which was already behind schedule because of ACCO's mismanagement, poor scheduling, and failure to account for the local labor market. (Dkt. 36 at 9-12.) ACCO disputes that it concealed information about the project, arguing the schedules contained information about the project's delays and that ACCO believed the project was still buildable by the June 2017 completion date despite the delays. (Dkt. 40 at 8-13.) Further, ACCO maintains Roost knew of the problems delaying the project, as it had unfettered access to monitor and physically observe the construction progress and the delays were discussed with Roost in meetings, field reports, and emails. (Dkt. 40 at 6-12.)

In July 2016, Carl Benjamin replaced Hayes as ACCO's superintendent on the project. (Dkt. 40 at ¶ 28.) In early September 2016, Benjamin issued new master schedules. Roost alleges the new master schedules contained none of the information from the prior schedules, making it impossible to monitor the status of the project and, further, that the September 2016 schedules were unreasonable and concealed project information. (Dkt. 36 at 12-14, 25.) Roost further claims that, during the fall of 2016, it requested project information from ACCO but received no official schedule updates as required by the Construction Agreement, and the reports it did receive from ACCO concealed important information about the project's delays. (Dkt. 36 at 12-23, 25.) During this time, the summer/fall of 2016, ACCO argues the project was delayed by subcontractor labor shortage issues and disputes that it concealed information about the project; ACCO maintains that Roost was aware of the issues delaying the project. (Dkt. 40 at 13-17.) Regardless of the delays, ACCO asserts it still believed it could complete the project by the June 2017 substantial...

To continue reading

Request your trial
5 cases
  • Greenstein v. Comm'r of Revenue
    • United States
    • Tax Court of Minnesota
    • September 24, 2021
    ... ... evidence for this purpose. See Roost Project, LLC v ... Andersen Constr. Co. , 437 F.Supp.3d 808, 818-19 ... ...
  • Kinnebrew v. W. Wholesale Supply, Inc.
    • United States
    • U.S. District Court — District of Idaho
    • June 23, 2021
    ...the burden to show no material fact is in dispute and a favorable judgment is due as a matter of law." Roost Project, LLC v. Andersen Constr. Co., 437 F. Supp. 3d 808, 817 (D. Idaho 2020) (Dale, M.J.), reconsideration denied, Case No. 18-cv-00238-CWD, 2020 WL 3895757 (D. Idaho July 10, 2020......
  • Weig v. Stanley (In re Sleestak, LLC)
    • United States
    • U.S. Bankruptcy Court — District of Idaho
    • July 24, 2023
    ... ... injury.'" Roost Project, LLC v. Andersen Constr ... Co. , 437 F.Supp.3d 808, 824 ... ...
  • Davis v. Blast Props.
    • United States
    • U.S. District Court — District of Idaho
    • February 3, 2023
    ... ... Idaho Oct. 26, ... 2009); Roost Project v. Anderson Construction ... Company , 437 F.Supp.3d 808, ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT