Rosenfeld v. City Paper Co.

Decision Date13 May 1988
Citation527 So.2d 704
PartiesDonald ROSENFELD v. CITY PAPER COMPANY. 87-14.
CourtAlabama Supreme Court

Gary L. Blume, Tuscaloosa, for appellant.

Gary P. Weinstein of Sirote, Permutt, McDermott, Slepian, Friend, Friedman, Held & Apolinsky, Birmingham, for appellee.

JONES, Justice.

With respect to whether the trial court erred in granting summary judgment to the promisee (appellee) of a promissory note in face of the promisor's (appellant's) answer setting up "duress" and "lack of consideration," we affirm. Our affirmance on this issue is mandated, because the promisor's counter affidavit, in opposition to the promisee's motion for summary judgment, fails to raise a genuine issue of material fact, and thus the promisee is entitled to a judgment as a matter of law. Rule 56, A.R.Civ.P.

The remaining issue presented is whether the trial court erred in entering judgment for the full amount of the note, plus interest and attorney's fee, where, in the absence of an acceleration clause, only two of five annual installments, as provided by the note, were due at the time of the entry of judgment. With respect to this issue, we reverse and remand with instructions to the trial court to enter a judgment in an amount equal to the sum of two accrued annual installments, plus interest from the date each installment was due and an attorney fee computed at 28% of the accrued installments.

The pertinent language of the note reads as follows:

"In the event that the relationship between [Rosenfeld/payor] and [CPC/payee] terminates, regardless of the reason for such termination, the outstanding balance then due on the obligation expressed herein shall be due and payable, without interest, in five (5) equal annual installments, beginning one year from the date of termination of the relationship between the parties." (Emphasis added).

City Paper Company agrees that the note contains no acceleration clause, and that the case law, generally speaking, supports Rosenfeld's contention that "acceleration of the maturity of unaccrued payments" is not to be read into payment contracts by implication. For a collection of the cases so holding, see 10 C.J.S., Bills & Notes § 529 at 1160 (1938). Rather, pointing to Rosenfeld's "repudiation of the entire obligation," City Paper Company seeks to have this Court join a minority of jurisdictions that apply the doctrine of anticipatory breach as an exception to the general rule of nonacceleration. Because of our rejection of the application of the "anticipatory breach" doctrine to unilateral contracts for the payment of money only, we need not decide whether Rosenfeld's deposition testimony amounts to a "repudiation."

The parties agree that Alabama has long recognized that a party to a bilateral contract may elect to treat the contract as absolutely breached and sue at once when the other party repudiates his obligations under the contract. See Box v. Metropolitan Life Insurance Co., 232 Ala. 447, 168 So. 220, 222 (1936), and the other cases cited therein. Likewise, the parties agree that the "application of the anticipatory breach doctrine" issue, in a unilateral or installment payment contract case, is one of first impression.

We agree that the precise issue here presented is one of first impression; however, it is interesting to note that Box, supra, the very case cited by City Paper Company for Alabama's acceptance of the "anticipatory breach" doctrine, makes it clear that the doctrine's application in that case was in the context of a bilateral contract.

More compelling, however, is the rationale that distinguishes the two separate contracts with respect to the application of the doctrine. "Anticipatory breach" has a field of operation where the nondefaulting parties remain liable for certain obligations under a bilateral contract. To require the nondefaulting party to continue the discharge of his contractual duties, in face of a clear, unequivocal repudiation of the contract by the defaulting party, is a senseless requirement that unduly penalizes the nondefaulting party.

The majority of jurisdictions faced with this issue have drawn the distinction and have not allowed the "anticipatory breach" doctrine to apply to unilateral contracts, particularly for the payment of money only. 1 The "settled" rule was succinctly expressed by Justice Cardozo in Smyth v. United States, 302 U.S. 329 at 356, 58 S.Ct. 248 at 253 (1937):

"[T]he doctrine of anticipatory breach has in general no application to unilateral contracts, and particularly to such contracts for the payment of money only."

Some of the cases cited above reference Professor Williston's treatise for the rationale that rejects the application of the "anticipatory breach" doctrine to...

To continue reading

Request your trial
9 cases
  • Busse v. Paul Revere Life Ins. Co.
    • United States
    • United States Appellate Court of Illinois
    • June 30, 2003
    ...is equal to the amount of money owing up to the time the breach is established, i.e., the date of trial. See, e.g., Rosenfeld v. City Paper Co., 527 So.2d 704 (Ala.1988); Franklin Society Federal Savings & Loan Ass'n v. Far-Pap Corp., 57 A.D.2d 607, 393 N.Y.S.2d 782 (1977); Greguhn v. Mutua......
  • Central States v. Basic American Industries
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • June 5, 2001
    ..."will not intercede to rescue the promisee from the consequences of the absence of an acceleration clause." Rosenfeld v. City Paper Co., 527 So. 2d 704, 706 (Ala. 1988); cf. First State Bank v. Jubie, 86 F.3d 755, 760 (8th Cir. 1996). That gets it backwards. Acceleration clauses are inserte......
  • Gerstenecker v. Gerstenecker
    • United States
    • Alabama Supreme Court
    • May 19, 2017
    ...payments Julie had missed at the time the judgment was entered against her.In making her argument, Julie relies on Rosenfeld v. City Paper Co., 527 So.2d 704 (Ala. 1988), and Meigs v. Estate of Mobley, 134 So.3d 878 (Ala. Civ. App. 2013). In Meigs, it was undisputed that an oral contract ex......
  • Meigs v. Estate of Mobley
    • United States
    • Alabama Court of Civil Appeals
    • June 21, 2013
    ...limited the judgment to the monthly payments that had accrued at the time the judgment was entered. Meigs cites Rosenfeld v. City Paper Co., 527 So.2d 704, 705 (Ala.1988), for the proposition that acceleration of unaccrued payments is not to be read into payment contracts by implication. In......
  • Request a trial to view additional results