Rule v. Anderson
Decision Date | 04 December 1911 |
Citation | 142 S.W. 358,160 Mo. App. 347 |
Parties | RULE et al. v. ANDERSON et al. |
Court | Missouri Court of Appeals |
A building contract provided for the making of changes in the plans and a method by which the contractor would be entitled to compensation for extra work in consequence thereof. A bond guaranteeing performance by the contractor stipulated that the obligee should notify the surety immediately on the making of any changes in the plans. The contract was made a part of the bond. Changes consisting in substitution of one kind of material for another, and in omitting work, and in additional work, were made; but the surety was not notified thereof. The cost of the extra work in consequence of the changes amounted to $16.25, and the reduction of the contract price in consequence of changes amounted to $49. The surety was engaged in the business of suretyship for hire. Held that, since the changes did not materially affect the risk, the surety was not discharged from liability because of the failure of the obligee to give notice thereof.
2. PRINCIPAL AND SURETY (§ 100) — DISCHARGE OF SURETY.
The rule that where changes in a building contract, made without the consent of the surety of the contractor, affect the identity of the contract, the surety is discharged, though the changes do not increase the risk of the surety, does not apply where the surety is engaged in the business of suretyship for hire, and in such a case mere immaterial variations or unsubstantial deviations, which do not prejudice the right of the surety, do not discharge it.
3. PRINCIPAL AND SURETY (§ 59)—INDEMNITY INSURANCE — CONTRACTS — CONSTRUCTION.
The contracts of surety companies, conditioned on the performance by others of contracts, are contracts of indemnity, and, since they are prepared by the companies, the stipulations therein must be strictly construed, and no unreasonable right of forfeiture must be allowed.
4. APPEAL AND ERROR (§ 169)—QUESTIONS REVIEWABLE—QUESTIONS NOT RAISED IN TRIAL COURT.
A point not raised in the trial court will not be considered on appeal.
5. PRINCIPAL AND SURETY (§ 20) — CONTRACTS—VALIDITY.
The rule that a bond by a contractor to secure the performance of the contract, which recites that it is executed by the contractor as principal and by another as surety, is void as to the surety if not signed by the principal, does not apply to a contract of indemnity created by a surety company engaged in the business of suretyship for hire, and, where a surety company signs a bond to secure performance of a building contract and collects and retains the premium charged for the bond, it cannot repudiate liability on the ground that the bond was not signed by the contractor.
6. PRINCIPAL AND SURETY (§ 129)—BREACH —WAIVER BY SURETY.
Where the manager of a surety company, executing a bond conditioned on the performance by a contractor of a building contract, knew of the failure of the contractor to complete the building within the time fixed in the contract and acquiesced in the course pursued by the owner in permitting the contractor to continue work, the company waived a forfeiture of the bond based on the failure of the owner to give written notice of the breach of the contract.
Appeal from Circuit Court, Jackson County; John G. Park, Judge.
Action by Alice H. Rule and another against R. H. Anderson and another. From a judgment for defendants, plaintiffs appeal. Reversed and remanded.
Boyle & Howell, for appellants. Botsford, Deatherage & Creason, for respondents.
This suit is on a builder's bond executed by defendant, a surety company, as a surety for hire. A jury was waived by agreement, and, after hearing the evidence, the court made and filed findings of fact and conclusions of law on which it rendered judgment for the defendants. Plaintiffs appealed.
The facts of the case thus may be stated: Plaintiffs are husband and wife, and in August, 1904, acting for himself and as the agent of his wife, the husband entered into a contract with defendant Anderson, by the terms of which Anderson, who is a contractor, agreed to do the carpenter work and provide the materials therefor for an apartment building to be erected on lots in Kansas City owned by Mrs. Rule. The work was to be done according to plans and specifications in the office of the architect employed by plaintiffs, and the contractor was to be paid $4,102.25 for the work at stated times and on the architect's certificates. November 20, 1904, was fixed as the date for the completion of the work.
Among other provisions of the contract, which was in writing, were the following:
Defendant the National Surety Company is a New York corporation engaged in the business of guaranteeing the fidelity of employés and contractors and authorized to transact business in this state. It maintains an office in Kansas City in charge of a district manager, and on October 4, 1904, at the request of Anderson, executed a bond at that office by the hand of the manager by which, in consideration of a premium paid by Anderson, it undertook to guarantee the performance of Anderson's contract with plaintiffs. The building contract was referred to and made a part of the bond.
Among the stipulations of the bond were the following:
The work was not completed until January, 1905, and plaintiff failed to give written notice of this default of Anderson until January 21, 1905. In answer to this notice, defendant's vice president in New York wrote plaintiffs as follows: ...
To continue reading
Request your trial-
State v. American Surety Co. of New York
... ... court, and in overruling a petition or motion for the removal ... of a cause the rule of respondent ouster obtains, and the ... order should be that defendant plead further within the time ... fixed by the court, and until the ... v. Pauly, 170 ... U.S. 133, 18 S.Ct. 552, 42 L.Ed. 977; Hull v ... Massachusetts etc. Ins. Co., 86 Kan. 342, 120 P. 544; ... Rule v. Anderson, 160 Mo.App. 347, 142 S.W. 358.) ... "In ... an action on a joint and several bond, all or any of the ... sureties may be sued." ( State ... ...
-
Missouri, Kansas & Texas Railway Co. v. American Surety Company of New York
... ... bond for a consideration. Barton v. Title Guaranty ... Co., 192 Mo.App. 564; Lackland v. Surety Co., ... 256 Mo. 133; Rule v. Anderson, 160 Mo.App. 347; ... Boppart v. Surety Co., 140 Mo.App. 675; Grocery ... Co. v. Guaranty Co., 130 Mo.App. 421, 429; Roark v ... ...
-
State ex rel. Elberta Peach & Land Company v. Chicago Bonding & Surety Company
... ... title, it is not necessary to decide. It is apparent, ... therefore, that the manner of instituting this suit by him is ... governed by the rule generally and [279 Mo. 548] ordinarily ... applicable in such cases. "The weight of authority ... clearly supports the proposition that the ... had the legal title to the bank credit. [Michie on Banks and ... Banking, sec. 130 (d); Anderson v. Walker, 49 S.W ... 937; [279 Mo. 550] Union School Twp. v. Bank, 102 ... Ind. 464, 2 N.E. 194.] And the bank was bound to pay his ... ...
-
City of Montpelier v. National Surety Co
... ... consideration of the questions presented. The defendant's ... argument proceeds upon the theory that the rule of ... strictissimi juris applies. It is well settled, ... however, that while the contract of an individual surety, or ... a voluntary surety ... Agnew , 264 Ill. 288, 106 ... N.E. 252; Springfield Lighting Co. v ... Hobart , 98 Mo.App. 227, 68 S.W. 942; Rule ... v. Anderson , 160 Mo.App. 347, 142 S.W. 358; Van ... Buren County v. American Sur. Co. , 137 Iowa ... 490, 115 N.W. 24, 126 A. S. R. 290; Bross v ... ...