S. Utah Wilderness Alliance v. U.S. Dep't of the Interior
Decision Date | 31 March 2017 |
Docket Number | Case No. 2:15-ev-00194-JNP-EJF. |
Citation | 250 F.Supp.3d 1068 |
Parties | SOUTHERN UTAH WILDERNESS ALLIANCE, Natural Resources Defense Council, and The Wilderness Society, Plaintiffs, v. UNITED STATES DEPARTMENT OF THE INTERIOR, United States Bureau of Land Management, and Ahmed Mohsen, in his official capacity as Price Field Office Manager, Defendants, and XTO Energy, Inc. Intervenor–Defendant. |
Court | U.S. District Court — District of Utah |
David T. Garbett, Stephen H. Bloch, Joseph J. Bushyhead, Southern Utah Wilderness Alliance (SLC), Salt Lake City, UT, for Plaintiffs.
Jared C. Bennett, US Attorney's Office (UT), Salt Lake City, UT, for Defendants.
Bret A. Sumner, Theresa M. Sauer, Andrew K. Glenn, Pro Hac Vice, Beatty & Wozniak PC, Denver, CO, David P. Bolda, Beatty & Wozniak PC, Highland, UT, for Intervenor–Defendant.
Before the court is a Motion for Review of Agency Action (Docket No. 62) filed by Plaintiffs Southern Utah Wilderness Alliance, Natural Resources Defense Council, and The Wilderness Society (collectively "Plaintiffs"). Plaintiffs challenge the United States Bureau of Land Management's ("BLM") decision to issue four oil and gas lease parcels in the November 2011 Oil and Gas Lease Sale ("2011 Lease Sale"), and its subsequent decision to approve the Horse Bench NE 24 Pad Seven–Well Project ("Seven–Well Project" or the "Project"). Plaintiffs' suit names the United States Department of the Interior, BLM, and the Price Field Office Manager for BLM, Ahmed Mohsen, (collectively "BLM") as defendants. XTO Energy, Inc. ("XTO Energy"), which purchased the leases and submitted the proposal for the Seven–Wells Project, intervened as a defendant. As explained below, the court affirms the agency's action regarding the 2011 Lease Sale and dismisses Plaintiffs' claims regarding the Seven–Well Project as moot.
Plaintiffs assert that BLM's actions violated the National Environmental Policy Act of 1969 ("NEPA"), 42 U.S.C. § 4321 et seq. , and the Federal Land Policy and Management Act of 1976 ("FLPMA"), 43 U.S.C. § 1701 et seq. Consequently, before addressing the substance of Plaintiffs' claims, the court outlines the statutory framework of NEPA and FLPMA below.
Before an agency may take any "major Federal action [ ] significantly affecting the quality of the human environment," NEPA requires a thorough evaluation of potential environmental impacts. See 42 U.S.C. § 4332(2)(C) ; Utah Envtl. Congress v. Russell , 518 F.3d 817, 820 (10th Cir. 2008). "NEPA dictates the process by which federal agencies must examine environmental impacts, but does not impose substantive limits on agency conduct." Russell , 518 F.3d at 821 (citing Fuel Safe Wash. v. Fed. Energy Regulatory Comm'n , 389 F.3d 1313, 1323 (10th Cir. 2004) ). Thus, NEPA's primary mandates are keyed to the agency decisionmaking process itself, rather than the substantive outcome of that process:
First, NEPA forces government agencies to ‘consider every significant aspect of the environmental impact of a proposed action.’ Second, NEPA mandates that government agencies inform the public of the potential environmental impacts of proposed actions and explain how their decisions address those impacts.
Citizens' Comm. to Save Our Canyons v. U.S. Forest Serv. , 297 F.3d 1012, 1021–22 (10th Cir. 2002) (internal citations omitted) (quoting and citing Balt. Gas & Elec. Co. v. Nat. Res. Def. Council , 462 U.S. 87, 97, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983) ). Thus, NEPA "requires federal agencies to pause before committing resources to a project and consider the likely environmental impacts of the preferred course of action as well as reasonable alternatives." N.M. ex rel. Richardson v. Bureau of Land Mgmt. , 565 F.3d 683, 703 (10th Cir. 2009) (citing 42 U.S.C. § 4331(b) ).
In this pre-project "pause," an agency must first determine whether a proposed project will in fact "significantly affect[ ] the quality of the human environment" and therefore require further in-depth environmental impact analysis under § 4332(2)(C). Where the extent of environmental impact is initially unclear, an agency must prepare an initial environmental assessment ("EA"). See 40 C.F.R. § 1501.4(b) ; Silverton Snowmobile Club v. U.S. Forest Serv. , 433 F.3d 772, 780 (10th Cir. 2006). The EA is "a concise public document that briefly provides sufficient evidence and analysis for determining the appropriate next step." W. Watersheds Project v. Bureau of Land Mgmt. , 721 F.3d 1264, 1269 (10th Cir. 2013) (internal quotations omitted) (quoting Russell , 518 F.3d at 821 ).
If the agency finds that the action will not significantly affect the human environment (and is thus not a major action), it makes a "Finding of No Significant Impact" (or "FONSI"). If it finds the action will significantly affect the environment, it is then required to prepare a more extensive analysis in the form of an ‘environmental impact statement’ (or ‘EIS').
Utah Shared Access All. v. U.S. Forest Serv. , 288 F.3d 1205, 1207 (10th Cir. 2002) (citing Airport Neighbors All. v. United States , 90 F.3d 426, 429 (10th Cir. 1996) ).
Relevant here, any EIS or EA must "incorporate a range of reasonable alternatives, but the depth of discussion and analysis required is different depending on whether the document is an EIS or an EA." W. Watersheds Proj. , 721 F.3d at 1274 (emphasis in original). For instance, an EIS must present alternatives to the proposal so as to "provid[e] a clear basis for choice among options by the decisionmaker and the public." 40 C.F.R. § 1502.14. Accordingly, an EIS must "[r]igorously explore and objectively evaluate all reasonable alternatives," "briefly" explain any alternatives eliminated from consideration, "[d]evote substantial treatment to each alternative considered in detail[,]" "include reasonable alternatives not within the jurisdiction of the agency[,]" address the "alternative of no action[,]" and, inter alia , discuss "appropriate mitigation measures not already included in the proposed action or alternatives." § 1502.14(a) – (f). By contrast, an EA is a "concise public document" that must include, inter alia , only "brief discussions ... of the environmental impacts of the proposed action and alternatives" to the proposal. § 1508.9(a)–(b).
N.M. ex rel. Richardson , 565 F.3d at 704 (internal quotations omitted).
FLPMA "creates a ‘versatile framework’ for governing ... BLM's management of [public] lands." Utah Shared Access All. v. Carpenter , 463 F.3d 1125, 1128 (10th Cir. 2006) (quoting Rocky Mountain Oil & Gas Ass'n v. Watt , 696 F.2d 734, 737–38 (10th Cir. 1982) ). The Act provides for management of public lands "under principles of multiple use and sustained yield." 43 U.S.C. § 1732(a). As the Supreme Court observed:
"Multiple use management" is a deceptively simple term that describes the enormously complicated task of striking a balance among the many competing uses to which land can be put, "including, but not limited to, recreation, range, timber, minerals, watershed, wildlife and fish, and [uses serving] natural scenic, scientific and historical values."
Norton v. S. Utah Wilderness All. , 542 U.S. 55, 58, 124 S.Ct. 2373, 159 L.Ed.2d 137 (2004) (alterations in original) (quoting § 1702(c)). To balance these competing uses and achieve "sustained yield," § 1732(a), "FLPMA contains comprehensive inventorying and land use planning provisions" that ultimately "ensure that the ‘proper multiple use mix of retained public lands' [is] achieved." Rocky Mountain , 696 F.2d at 739 ; Norton , 542 U.S. at 58, 124 S.Ct. 2373 ( ).
These provisions specifically require the BLM to "develop, maintain, and, when appropriate, revise land use plans" to guide and control its management of public lands. See 43 U.S.C. § 1712(a). "These land use plans, which the BLM regulations denote ‘resource management plans' (‘RMPs') ... project both the present and future use of the land." Utah Shared Access , 463 F.3d at 1129 (internal citations omitted) (citing 43 C.F.R. § 1601.0–5(n) and 43 U.S.C. § 1701(a)(2) ). "Generally, a land use plan describes, for a particular area, allowable uses, goals for future condition of the land, and...
To continue reading
Request your trial-
SFF-Tir, LLC v. Stephenson
... ... dissolved, if you want your check, just send us your canceled certificates. Tr. at 173:17–22 ... Consonus, Inc. , 2005 WL 2263950 (D. Utah 2005) (Benson, J.) the United States District ... without approval by the Secretary of the Interior"; the Court rejected this argument, because the ... ...
-
Am. Petroleum Inst. v. U.S. Dept of Interior
... ... Petroleum Council, Petroleum Alliance of Oklahoma, Southeast ... Oil & Gas Association, Utah Petroleum ... program, the reasoning of JTB Tools requires us to ... conclude that where an appellate court has “exclusive ... leases.” S. Utah Wilderness All. v. United States ... Dep't of the Interior , 250 F.Supp.3d ... ...
-
Pub. Emps. for Envtl. Responsibility v. Nat'l Park Serv.
...as moot where the policy memorandum at issue had expired and was thus no longer in effect); S. Utah Wilderness All. v. U.S. Dep't of the Interior, 250 F. Supp. 3d 1068 (D. Utah 2017) (finding that where a permit was no longer operative, the alleged injury to Plaintiffs rendered by a NEPA vi......
-
Swomley v. Schroyer
...as in responses to public comments and objections. This is sufficient in the context of an EA. S. Utah Wilderness All. v. U.S. Dep't of the Interior , 250 F. Supp. 3d 1068, 1074 (D. Utah 2017) ("[T]he depth of discussion and analysis required is different depending on whether the document i......