Sampson v. Miglin

Decision Date29 March 1996
Docket NumberNo. 1-94-3348,1-94-3348
Citation664 N.E.2d 281,279 Ill.App.3d 270
Parties, 215 Ill.Dec. 884 Lou May SAMPSON, Plaintiff-Appellee and Cross-Appellant, v. Lee MIGLIN, Defendant-Appellant and Cross-Appellee.
CourtUnited States Appellate Court of Illinois

Appeal from the Circuit Court of Cook County; The Hon. Francis Barth, Judge Presiding.

Mayer, Brown & Platt of Chicago (Michael F. Kerr, James C. Schroeder and Laurie Gallancy), for cross-appellant.

Hinshaw & Culbertson of Chicago (D. Kendall Griffith, Kevin R. Sido and Adria East Mossing, of counsel), for cross-appellee.

Presiding Justice McNULTY delivered the opinion of the court:

Defendant, Lee Miglin, appeals from the trial court's judgment holding him liable to plaintiff, Lou May Sampson, for $544,223.50 in damages and $225,249 in costs and attorney fees. We find that the trial court overstated proven damages by $79,399.50 and, therefore, we modify the judgment. We affirm the award of costs and attorney fees.

In 1984 plaintiff bought a lot in Chicago's Gold Coast on which stood a five-unit apartment building. Defendant owned the building next door, which shared a masonry common wall with plaintiff's building. In January 1991, defendant began excavations to put in a basement as part of a complete remodeling of his building. He did not have a building permit, and he had not performed legally required investigations to determine the bearing capacity of the soil, the lateral pressure of adjacent soil, or the proper anchorage for the common wall.

On February 4, 1991, a tenant in plaintiff's building noticed a crack in the wall. Plaintiff spoke to workers on defendant's property, who said they would stop the work that was damaging the wall. They continued working without taking measures to protect plaintiff's building, and several days later plaintiff's other tenants called to tell her their doors did not open and close properly. The City of Chicago issued a stop work order before February 15, 1991. Plaintiff hired a structural engineer, who talked to defendant's contractor and looked at defendant's basement on February 15, 1991.

Defendant's contractor had attempted to underpin the common wall without the soil test or the supervision that building ordinances required. Defendant's architect later told plaintiff's engineer that the common wall had settled about one-half to three-quarters of an inch due to the lack of support during construction.

On March 8, 1991, plaintiff filed suit for a temporary restraining order and monetary damages. The court granted the restraining order and directed defendant to consult with plaintiff's structural engineer for proper stabilization of the common wall. Plaintiff hired Eugene Holland, a structural engineer who specialized in masonry remediation. Defendant hired a structural engineer on March 10, 1991, and that engineer worked with Holland throughout the subsequent construction. The city issued a building permit on April 30, 1991, after Holland and defendant's architect and engineer performed the preliminary investigations that should have preceded excavation and agreed on plans for proper bracing.

The trial court dismissed several counts of the complaint. Plaintiff proceeded to trial on counts charging negligence, violation of building ordinances, and violation of the Adjacent Landowner Excavation Protection Act (Excavation Act) (Ill.Rev.Stat.1991, ch. 111 1/2, par. 3300 et seq.). Defendant conceded violation of the ordinances and liability for damage to plaintiff's building prior to trial, but he contested the negligence count and the extent of the damages claimed.

The court found defendant liable for the $439,000 decrease in property value. The court awarded plaintiff almost $104,000 for out-of-pocket expenses, including about $98,000 for Holland's work. The court accepted plaintiff's calculation of $25,365 in rents lost up to the time of trial and awarded plaintiff $25,000 for the time and effort she spent working on problems defendant's construction caused. The total damages, thus, amounted to more than $593,000. The court reserved ruling on plaintiff's request for costs and attorney fees.

Defendant moved to vacate the award of Holland's fees because the judge at trial had said he would follow the same procedure for engineering fees as for attorney fees, permitting defendant to challenge the fee petitions in detailed evidentiary proceedings following the primary trial on damages. The court agreed and vacated the entire award of Holland's fees pending the hearing on attorney and engineering fees.

The court held that the Excavation Act and the Illinois Municipal Code (Ill.Rev.Stat.1991, ch. 24, par. 1-1-1 et seq.) supported the request for attorney fees, but not the request for expert witness fees. The court ordered plaintiff to strike from her petition fees for work experts did "solely to render opinions at trial," but permitted recovery of engineering fees incurred for working with defendant's engineers to stabilize the building and for determining "the extent of the damage to [plaintiff's] property or the nature of the necessary repairs." Plaintiff's attorneys then struck from the attorney fee petition all charges for work on dismissed counts and the negligence count.

Holland presented 23 pages of invoices, which included summary descriptions of work his firm performed and indicated who performed the work, for all the hours charged. Holland had crossed out the charges for work as an expert witness. The invoices included many aggregated entries and entries for conferences that did not describe the subjects discussed, as, for example, on April 2, 1991, Holland charged for 2.25 hours of work described as:

"Telecons with [plaintiff's attorney]; prepare letter to [defendant's structural engineer]; review drawings and prepare letter telecon to [defendant's structural engineer]."

He eliminated more than $40,000 for services as an expert witness, but left a total request of more than $55,000 for engineering work.

Holland testified in support of his petition, describing some of the indicated meetings, but leaving most entries without further explanation. Defendant did not, on cross-examination, ask for elucidation of most of the entries. Holland testified that his contract with plaintiff required plaintiff to pay him interest on balances she had not paid for 30 days. He sought more than $4,000 in interest on unpaid engineering fees.

Plaintiff's attorneys submitted more than 400 pages of detailed invoices, indicating the hours each attorney spent each day on the case, with summary descriptions of the work performed. Many of the entries aggregated several separate tasks and included no specification of the subject of conferences, especially when the conferences were between plaintiff and the attorneys. Thus, one attorney indicated that on March 11, 1991, he spent 5.5 hours on the case, for:

"Court appearance * * *; drafting agreed order with defendant's attorney; prepare correspondence to defendant's attorney regarding schedule for repairs; prepare correspondence to Gene Holland * * * and Lou Sampson regarding status." (Emphasis omitted.)

Each attorney testified in support of the petition, describing in detail some of the meetings listed, but providing no further explanation for the vast preponderance of the thousands of entries. Defendant did not, on cross-examination, request further information about most of the entries.

The trial court found details missing from Holland's bills and said:

"Standing alone the entries would probably not be sufficient to support a finding of reasonableness * * *. However, the entries do not stand alone. The proceedings conducted here including [the] availability of Eugene P. Holland to answer all questions overcomes * * * the inadequate entries."

In the court's opinion the interest charge was a "standard and reasonable element of the contract and * * * interest is recoverable from defendant."

The aggregate entries in the attorney fee petition were "adequate[,] particularly within the context of this case, to support a fee award. * * * [T]his court has heard the case throughout the years of litigation. It has had the opportunity to observe the preparedness and skill of plaintiff's attorneys. The court believes it is capable of exercising an informed discretion as to how the tasks performed related to the litigation, whether they were necessar[y] and, therefore, to determine whether they were reasonable and thus, compensable."

The court concluded that

"the status entries in this case describe adequately for purposes of supporting a billing conversations with plaintiff conducted to advise her of the current state of her legal matter. * * * Reasonable consultation with the client is a necessary and proper aspect of the professional relationship of attorney-client. * * * [I]n the absence of evidence that status conferences did not take place or had no constructive purpose the court will not disallow such billings."

The court disallowed fees incurred in preparation of and proceedings on the fee petitions. The total award included $225,249 for costs and attorney fees, and $44,851 plus $4,399.50 interest for Holland's engineering work. After amending the damage award, the court found defendant liable for a total of $769,472.50. Defendant appeals and plaintiff cross-appeals from the judgment.

Defendant, relying primarily on In re Marriage of Winton, 216 Ill.App.3d 1084, 159 Ill.Dec. 933, 576 N.E.2d 856 (1991), maintains that plaintiff did not present adequate evidence to justify the award of Holland's engineering fees. The trial court in Winton awarded the petitioner fees for the work of her expert witness, who performed no services apart from the preparation of his testimony. The appellate court reversed the award, holding that an award of expert witness fees must be supported by the same kind of detailed evidence needed...

To continue reading

Request your trial
17 cases
  • In re Estate of Bitoy
    • United States
    • United States Appellate Court of Illinois
    • September 30, 2009
    ... ... 696, 777 N.E.2d 499, quoting Sampson v. Miglin, 279 Ill.App.3d 270, 281, 215 Ill.Dec. 884, 664 N.E.2d 281 (1996), quoting Warren v. LeMay, 142 Ill. App.3d 550, 582, 96 Ill.Dec. 418, ... ...
  • Goldfine v. Barack
    • United States
    • United States Appellate Court of Illinois
    • June 28, 2013
    ...This court reviews a circuit court's award of attorney fees and costs for an abuse of discretion. Sampson v. Miglin, 279 Ill.App.3d 270, 281, 215 Ill.Dec. 884, 664 N.E.2d 281 (1996). ¶ 54 The trial court awarded plaintiffs $1,636,700.80 in attorney fees, which was calculated by applying a 4......
  • Clay v. County of Cook
    • United States
    • United States Appellate Court of Illinois
    • June 19, 2001
    ...Title & Trust Co., 248 Ill. App.3d 1065, 1072, 188 Ill.Dec. 379, 618 N.E.2d 949, 955 (1993). Accord, Sampson v. Miglin, 279 Ill.App.3d 270, 281, 215 Ill.Dec. 884, 664 N.E.2d 281, 289 (1996); Anderson, 274 Ill.App.3d at 1008, 211 Ill.Dec. 213, 654 N.E.2d at While Slutsky has presented extrin......
  • Guerrant v. Roth
    • United States
    • United States Appellate Court of Illinois
    • September 13, 2002
    ...excessive or] so inadequate as to amount to a clear abuse of discretion by the court.' [Citation.]" Sampson v. Miglin, 279 Ill.App.3d 270, 281, 215 Ill.Dec. 884, 664 N.E.2d 281, 288 (1996). Accordingly, we shall not disturb the trial court's decision as to these For the foregoing reasons, w......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT