Samuel Plumley v. United States No 35 United States v. Samuel Plumley No 36

Decision Date06 January 1913
Docket NumberNos. 35 and 36,s. 35 and 36
Citation57 L.Ed. 342,226 U.S. 545,33 S.Ct. 139
PartiesSAMUEL M. PLUMLEY, Appt., v. UNITED STATES. NO 35. UNITED STATES, Appt., v. SAMUEL M. PLUMLEY. NO 36
CourtU.S. Supreme Court

Messrs. George A. King, and William B. King for Samuel M. plumley.

Mr. William W. Scott, Assistant Attorney, and Mr. John Q. Thompson, Assistant Attorney General, for the United States.

Mr. Justice Lamar delivered the opinion of the court:

In October, 1888, P. H. McLaughlin & Company contracted to build the Naval Observatory in Washington for $307,811. After most of the work had been done, the contract was forfeited for failure to make satisfactory progress. 37 Ct. Cl. 150. The government advertised for bids to complete the work. After examining the contract and documents Plumley agreed to complete the building in accordance with the McLaughlin contract, and 'duly authorized changes' by June 1st, 1892, for the sum of $25,840. Having finished the work, he sued the government for damages by delay and for extra work amounting to $12,813. The court rendered judgment in his favor for $502 insurance paid during the period he was delayed in finishing the work. All of the other items were disallowed. Both parties appealed.

1. The largest item is a claim for extra compensation for installing a ventilator system, which McLaughlin agreed to do for a given sum. The proposed change and this offer were submitted by the architect to the Bureau of Equipment, with the statement that, if approved, McLaughlin would enter into a formal written contract to do the work for the prices named. The plans and bid were approved. McLaughlin was directed to proceed, and did some work thereon. Later his contract was forfeited. Plumley (and his partner, Davis, a former member of McLaughlin & Company) knew these facts at the time the bid was made to complete the work, but when required to build the ventilating system, Plumley insisted that it was not within McLaughlin's original contract, and not a 'duly authorized change' because no written contract had been signed by both parties, as required by the terms of the contract. This contention was rejected by the architect, and, on appeal, by the Secretary of the Navy. The court of claims at first sustained this position, but on a rehearing held that Plumley was estopped from claiming that the change had not been duly authorized, and, under his contract to complete the work, was bound to finish what McLaughlin had begun. Beyond this the contract provided that if there was any discrepancy between plans and specifications, or between the contract of McLaughlin and the contract of Plumley, the matter should be referred to the Secretary, Plumley agreeing 'to abide by his decision in the premises.' The Secretary decided against him, and under the circumstances his construction is binding on the contractor.

2. This same provision prevents a recovery for the drain pipe included in the original...

To continue reading

Request your trial
60 cases
  • McCullough v. Clinch-Mitchell Const. Co.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • May 22, 1934
    ...in the Supreme Court United States v. Mason & Hanger Co., 260 U. S. 323, 326, 43 S. Ct. 128, 67 L. Ed. 286; Plumley v. United States, 226 U. S. 545, 548, 33 S. Ct. 139, 57 L. Ed. 342; Ripley v. United States, 223 U. S. 695, 701, 704, 750, 32 S. Ct. 352, 56 L. Ed. 614; Chicago, S. F. & C. Ra......
  • United States v. Goltra Goltra v. United States
    • United States
    • U.S. Supreme Court
    • February 3, 1941
    ...U.S. 476, 492, 57 S.Ct. 244, 81 L.Ed. 360. 17 Hawkins v. United States, 96 U.S. 689, 697, 24 L.Ed. 607; Plumley v. United States, 226 U.S. 545, 547, 33 S.Ct. 139, 140, 57 L.Ed. 342; Yuhasz v. United States, 7 Cir., 109 F.2d 467, 468; Burton Coal Co. v. United States, 60 Ct.Cl. 294, 312; Lut......
  • State Hwy. Comm'n v. Green-Boots Const. Co.
    • United States
    • Oklahoma Supreme Court
    • July 8, 1947
    ...Const. Co. v. Virginian Ry. Co., 86 W. Va. 440, 103 S.E. 293. We quote a pertinent paragraph from the case of Plumley v. U.S., 226 U.S. 545, 33 S.Ct. 139, 140, 57 L.Ed. 342: "The other items for extra work were properly disallowed. The contract provided that changes increasing or diminishin......
  • Tobin Quarries v. Central Nebraska Public P. & I. Dist., Civil Action No. 57.
    • United States
    • U.S. District Court — District of Nebraska
    • January 8, 1946
    ...v. John McShain, Inc., 308 U.S. 512, 520, 60 S.Ct. 134, 84 L.Ed. 437, which reaffirmed its earlier rulings in Plumley v. United States, 226 U.S. 545, 33 S.Ct. 139, 57 L.Ed. 342, and Merrill-Ruckgaber Co. v. United States, 241 U.S. 387, 36 S.Ct. 662, 60 L.Ed. 1058. Upon this point generally,......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT