Save Our Invaluable Land (SOIL), Inc. v. Needham, 75-1511

Citation542 F.2d 539
Decision Date29 September 1976
Docket NumberNo. 75-1511,75-1511
Parties, 6 Envtl. L. Rep. 20,800 SAVE OUR INVALUABLE LAND (SOIL), INC., et al., Appellants, v. Colonel William R. NEEDHAM et al., Appellees, and City of Olathe, Kansas, et al., Intervenor-Appellees.
CourtUnited States Courts of Appeals. United States Court of Appeals (10th Circuit)

Arthur A. Benson, II, Kansas City, Mo., for appellants.

Eva R. Datz, Dept. of Justice, Washington D.C. (Peter R. Taft, Asst. Atty. Gen., Washington D.C., E. Edward Johnson, U. S. Atty., Roger K. Weatherby, Asst. U. S. Atty., Topeka, Kan., and Jacques B. Gelin, Dept. of Justice, Washington D.C., on the brief), for federal appellees.

F. Philip Kirwan, Kansas City, Mo. (Lyman Field, Kansas City, Mo., Joseph H. McDowell, Kansas City, Kan., Margolin & Kirwan, Washington D.C., of counsel; Rogers, Field, Gentry, Benjamin & Robertson, Kansas City, Mo., on the brief), for intervenor-appellees.

Before McWILLIAMS, BARRETT and DOYLE, Circuit Judges.

McWILLIAMS, Circuit Judge.

This is a suit to enjoin the Corps of Engineers from constructing the Hillsdale Dam on the Big Bull Creek in Miami County, Kansas. The action was instituted by Save Our Invaluable Land (SOIL), Inc., a non-profit organization organized under the laws of Kansas, whose members are, in the main, landowners who reside in the area of the proposed dam site. The gist of the complaint is that the Corps of Engineers has not complied with the requirements of the Federal Water Pollution Control Act, the National Environmental Policy Act, and the Water Supply Act. Named as parties defendant, in addition to the Corps of Engineers, were various administrative officers of the Environmental Protection Agency. By answer the federal defendants alleged compliance with the several acts of Congress with which we are here concerned, and attached to the answer a copy of the final Environmental Impact Statement (EIS) prepared by the Corps of Engineers in November 1971, and filed with the Council on Environmental Quality on February 2, 1972.

Trial of this matter was to the court, sitting without a jury, and after a four-day trial the judge found in favor of the defendants and dismissed the action. The trial court made elaborate findings and conclusions, consisting of some 43 pages. SOIL now appeals. We affirm.

On appeal SOIL raises essentially three points: (1) the trial court erred in finding that Section 102(b)(3) of the 1972 Amendments to the Federal Water Pollution Control Act did not apply to the Hillsdale Dam; (2) the trial court erred in concluding that the Corps's EIS met the requirements of the National Environmental Policy Act of 1969, and that the Corps otherwise met the requirements of the Fish and Wildlife Coordination Act of 1958; and (3) the trial court erred in concluding that the inclusion of storage for water supply as a project purpose met the requirements of the Water Supply Act of 1958, as amended. We shall discuss these several matters seriatim.

I. 1972 Amendments to the Federal Water Pollution Control Act

SOIL initially argues that the trial court erred in holding that Section 102(b)(3) of the 1972 Amendments to the Federal Water Pollution Control Act did not apply to the Hillsdale Dam. That section, which appears as 33 U.S.C. § 1252(b)(3), reads as follows:

(3) The need for, the value of, and the impact of, storage for water quality control shall be determined by the Administrator, and his views on these matters shall be set forth in any report or presentation to Congress proposing authorization or construction of any reservoir including such storage.

The above quoted statute needs to be set in a bit of historical context. Prior to the 1972 amendments, storage of water for the purpose of controlling the quality of a stream was one method, though not the only one, authorized by Congress in its attack on the problem of water pollution. Under this particular approach water was stored to be released when the natural flow in a stream was low, thereby augmenting the stream flow and diluting the pollution entering the stream below the storage facility. This low flow augmentation did nothing to eliminate pollution, as such, but was only designed to keep pollution at acceptable levels.

In 1972 Congress shifted the emphasis to an elimination of the so-called point sources of pollution. Illustrative of this changed approach to the water pollution problem is 33 U.S.C. § 1252(b)(1), which reads as follows:

(b)(1) In the survey or planning of any reservoir by the Corps of Engineers, Bureau of Reclamation, or other Federal agency, consideration shall be given to inclusion of storage for regulation of streamflow, except that any such storage and water releases shall not be provided as a substitute for adequate treatment or other methods of controlling waste at the source.

The Hillsdale Dam was authorized by Congress in 1954 as one segment of a nine-part reservoir system in the Osage-Marias des Cygnes River Basin in Kansas. In 1961, and again in 1966, the project was deferred for further study. The restudy was finally completed and the project entered the advanced engineering and design phase with Congress appropriating funds for such planning for fiscal years 1968 through 1972. On August 25, 1972, Congress appropriated funds to initiate construction of the dam. The 1972 Amendments to the Federal Water Pollution Control Act became law on October 18, 1972. It was in this setting that the trial court held that 33 U.S.C. § 1252(b)(3) did not apply to the Hillsdale Dam. Under the circumstances, we agree.

In the instant case one of the purposes of the Hillsdale Dam was admittedly water quality control. Other purposes were flood control, water supply, recreation, and fish and wildlife. And each of these purposes, as well as other matters, was taken into consideration in arriving at a final cost/ benefit ratio. It is SOIL's position that the Corps of Engineers failed to comply with 33 U.S.C. § 1252(b)(3) in that the EPA Administrator did not determine the need for, the value of, and the impact of storage for water control, nor were his views on these matters set forth in "any report or presentation to Congress proposing authorization or construction of any reservoir including such storage," as mentioned in the statute. As indicated, both the Corps, as well as the EPA, are of the view that § 1252(b)(3) does not apply to the Hillsdale Dam inasmuch as the authorization for the dam and its construction had cleared Congress before the enactment of § 1252(b)(3).

As above indicated, we are of the view that § 1252(b)(3) does not apply to the Hillsdale Dam. In support thereof, see, for example, Cape Henry Bird Club v. Laird, 359 F.Supp. 404 (W.D.Va.1973), aff'd on appeal, 484 F.2d 453 (4th Cir. 1973). In its affirmance the Fourth Circuit held that neither § 1252(b)(1) nor (3) applied to the dam there under consideration, because "(t)he dam is neither in the survey or planning stage, nor is it before Congress for authorization or construction. Those stages have long passed." The foregoing applies to the instant case with equal vigor, even though actual construction of the Hillsdale Dam was delayed by temporary impoundment of budgeted funds. The issue is not whether the Corps because of such delay could have complied with § 1252(b)(3), if it chose to do so. Rather the issue is whether under the circumstances, the Corps, and the EPA, were required to comply with § 1252(b) (3). We think they were not.

In further support of our holding, see also Environmental Defense Fund v. Tennessee Valley Authority, 371 F.Supp. 1004 (E.D.Tenn.1973), aff'd, 492 F.2d 466 (6th Cir. 1974). To the same effect, see Sierra Club v. Froehlke, 392 F.Supp. 130 (E.D.Mo.1975), where that court flatly declared that "the plain language of the statute (33 U.S.C. § 1252(b)(1) and (3)) indicates that it is applicable only to projects which are in the planning or preauthorization stages."

We do not regard State of Ohio ex rel. Brown v. Callaway, 497 F.2d 1235 (6th Cir. 1974) to be apposite to the present problem. There the problem was primarily one of intervention. In any event, we believe that the result reached by the Fourth Circuit in Cape Henry Bird Club is the proper one and more properly fits the particular facts of our case.

As indicated, the interpretation we have given § 1252(b)(3) concerning its applicability to Hillsdale Dam is the interpretation which has heretofore been adopted by both EPA and the Corps. The interpretation given a statute by the administrative agency charged with its administration is entitled to weight. Such fact fortifies us in our conclusion that the interpretation which we give § 1252(b)(3) is " 'correct,' to the extent that any particular interpretation of a complex statute such as this is the 'correct' one." Train v. Natural Resources Defense Council, 421 U.S. 60, 95 S.Ct. 1470, 43 L.Ed.2d 731 (1975).

II. Sufficiency of the Environmental Impact Statement (EIS)

SOIL contends that the Corps has not complied with 42 U.S.C. § 4332(A)(B) and (C). Sections (A) and (B) are, in a sense, declarations of policy, and to effectuate such policies, Section (C) requires that an environmental impact statement be filed on all major federal actions, and lists five specific matters to be...

To continue reading

Request your trial
17 cases
  • Citizens for Environmental Quality v. US
    • United States
    • U.S. District Court — District of Colorado
    • 24 August 1989
    ...should the courts in evaluating an EIS engage in hindsight judgement by way of second guessing. See also, Save Our Valuable Land (Soil), Inc. v. Needham, 542 F.2d 539 (10th Cir. 1976); cert. denied, 430 U.S. 945, 97 S.Ct. 1580, 51 L.Ed.2d 792 The requirements of 42 U.S.C. § 4332 are mandato......
  • Sierra Club v. Hodel
    • United States
    • U.S. District Court — District of Utah
    • 30 November 1987
    ...should look for adequacy and completeness in an impact statement, not perfection. Id. at 1004. See also, Save Our Invaluable Land (SOIL), Inc., v. Needham, 542 F.2d 539 (10th Cir.1976). Although the court holds that no EIS has to be prepared, it feels that the uncertainty surrounding possib......
  • Philadelphia Council of Neighborhood Organizations v. Coleman
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • 12 September 1977
    ...to reverse. A number of courts have emphasized that NEPA does not require perfection in an EIS. See Save Our Invaluable Land (Soil), Inc. v. Needham, 542 F.2d 539, 543 (10th Cir. 1976).77 In Natural Resources Defense Council, Inc. v. Morton, 148 U.S.App.D.C. 5, 458 F.2d 827 (1972), the Cour......
  • Holy Cross Wilderness Fund v. Madigan
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • 3 April 1992
    ...the subject matter involved in the five respective areas?Johnston v. Davis, 698 F.2d at 1091 (quoting Save Our Invaluable Land (SOIL), Inc. v. Needham, 542 F.2d 539, 542 (10th Cir.1976), cert. denied, 430 U.S. 945, 97 S.Ct. 1580, 51 L.Ed.2d 792 (1977)).10 The Fund also argues in its Reply B......
  • Request a trial to view additional results
1 books & journal articles
  • Addressing barriers to watershed protection.
    • United States
    • Environmental Law Vol. 25 No. 4, September 1995
    • 22 September 1995
    ...Hoffman, 566 F.2d 1060 (8th Cir. 1977) Cache River-Bayou DeView Channelization Project); Save Our Invaluable Land (SOIL), Inc. v. Needham, 542 F.2d 539 (10th Cir. 1976) (Hillsdale Dam Project), cert. denied, 430 U.S. 945 (1977); Environmental Defense Fund, Inc. v. Armstrong, 487 F.2d 814 (9......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT