Schliess v. City of Grand Rapids

Decision Date03 June 1902
Citation90 N.W. 700,131 Mich. 52
CourtMichigan Supreme Court
PartiesSCHLIESS v. CITY OF GRAND RAPIDS.

Error to superior court of Grand Rapids; Richard L. Newnham, Judge.

Action on a building contract by Henry Schliess against the city of Grand Rapids. From a judgment for plaintiff, defendant brings error. Affirmed.

In November, 1898, plaintiff made a contract with the defendant city to build the foundation walls for a municipal electric lighting plant. By the charter of the city (title 9, �� 13 14, 30) the board of public works is intrusted with the control of the erection and contruction of such buildings. The board is also authorized to determine and designate the kind and quality of material to be used. When it has so determined, it is required to make an estimate of the probable cost, and report the same to the common council. If approved, a contract is then made, signed by the mayor and the president of the board of public works. The contract was made November 12th, and the work was to be done within 60 days. Those portions of the contract which counsel deemed material are as follows: 'Build the foundation walls (colored blue on plans and sections) up to grade line of thickness shown of native field boulders, to be of selected large size first quality stone, not less than 12 inches in thickness by 15 inches in length, laid to line on both sides well bounded and fitted together.' 'No part of this contract will be accepted unless it complies fully with these specifications in the fullest sense of its terms.' 'The contractor shall (if so directed by the architect) furnish horse manure, and cover all the newly built stonework during cold weather, to prevent its being injured by freezing.' 'The contractor agrees that the materials to be used and the work to be performed shall at all times be subject to the inspection and approval of the board of public works, or authorized agent of said city, and, in case any material is rejected, it shall be immediately removed from the premises, and not again brought thereon. The contractor agrees that he will at all times give his personal attention to the work, and that he will employ none but competent workmen on the work covered by this contract. The contractor agrees that the board of public works of said city shall determine finally all questions as to the proper performance of his contract, and that the said board may declare this contract forfeited at any time for the nonperformance of any part thereof, and may proceed to complete the same without delay. It is further understood that the liability of the contractor under this contract shall in no way be lessened by reason of the board availing itself of the provisions herein contained. The contractor agrees to commence said work within ten days after signing this contract, and to prosecute the same with all due diligence, and finish the same in sixty working days, for the sum of six thousand eight hundred and sixty-five dollars, the amount named in this proposal for the work, now on file in the office of said board; and that for each and every day that elapses beyond the number of working days mentioned in said proposal for the completion of this contract the said board may deduct from any money due the contractor the sum of ten dollars, in addition to the per diem of the inspectors employed on the work. It is mutually agreed between the parties that no deviation from the contract can be authorized by any inspector of the work, and that the city is in no way bound to accept work not in accordance with the specifications, although such work may not have been objected to by the inspector. The city hereby agrees to pay the sum aforesaid in article 6 under the restrictions and limitations herein contained, and to make payments from time to time in the manner indicated in article 7, on account of the performance of this contract, upon estimates of the amount of work actually performed and materials actually used thereon. The amount so paid shall be such as the board of public works find to be just. Fifteen per cent. of such estimates may be retained until the acceptance of the work, and it is agreed that no part of the retained percentage shall be paid to the contractor before the final acceptance of the work, except upon the written consent of the bondsmen. It is mutually understood that the intent of the contract is to secure first-class construction workmanship, and materials, and the contractor hereby agrees to furnish the same, and be governed in all things by the regulations herein contained, whether specifically expressed or implied, and by instructions given by the board of public works, not inconsistent with this contract. The contractor agrees that his responsibility shall in no way be lessened by reason of either party hereto availing itself of any provisions herein contained.' The work was begun November 16th, was continued until January 18th, when the architect ordered the work stopped on account of the severe cold weather. About five-sixths of the work at this time was completed. The wall appears to have been built in sections and the larger part of it was completed to the top. Work was resumed by order of the architect February 22d. The weather became too cold, and, under orders of the architect, work was again suspended until March 17th. On that day the board served a notice upon the plaintiff and his sureties to complete the job within 10 days thereafter. He at once resumed work, and the job was nearly completed by the 5th of April. Soon after this it was discovered that the mortar was killed by freezing, and it became necessary to take down and rebuild a portion of the wall. A dispute arose between the parties as to the responsibility for the condition of the walls. Plaintiff claimed that he had complied with the conditions of his contract; that the work was done under the direction of the architect and inspector, as well as members of the board of public works; that weekly estimates had been made by the architect and inspector, and approved by the architect and the board, and payments made in accordance with the terms of the contract. Defendant claimed that the plaintiff had not complied with the terms of his contract; that the mortar was not as provided; that some smaller stones were used than the contract provided; and that manure was not used, at required, for the protection of the walls. Plaintiff made a proposition to rebuild the unsafe parts of the walls at a given price. This was accepted by a unanimous vote of the board. At a subsequent meeting this resolution of acceptance was rescinded, and the board declared the contract forfeited, and proceeded to rebuild. Plaintiff brought this suit to recover the amount due him under the contract, claiming performance on his part.

Moses Taggart, for appellant.

Knappen, Kleinhans & Knappen, for appellee.

Counsel for the plaintiff are not satisfied with the statement of facts made in appellant's brief, and say that they 'are so insufficient and inaccurate as to justify a restatement.' This involves the examination by this court of a long record to determine and make a statement of facts. This requires labor which ought not to be imposed upon us. The material facts, so far as the questions before us are involved, are not in dispute, and appear in the following instructions of the court: 'It is undisputed that plaintiff began the performance of his contract within the time required thereby; that on or about December 16th the board of public works ordered the plaintiff to proceed more rapidly with the work, and notified him that it must be completed within the time provided by the contract. It is undisputed that from the time of said notice plaintiff proceeded with the contract, and continued in its performance until about January 18th, when he was stopped by orders from the architect, on the ground that the weather was too cold to lay stone. It is likewise undisputed that at the time the plaintiff was stopped by the architect about five-sixths of the wall had been laid up. It is likewise undisputed that from about the 18th day of January until at least the 23d day of February the weather was so unusually and exceedingly cold that the freezing of the earth, water pipes, and so forth, was greater than for many previous years. It is also undisputed that the weather from January 18th to February 23d, and some of the weather after the latter date, was so cold as to kill cement mortar laid up in walls above the ground which had not yet dried out. It is also undisputed that from the time the plaintiff began work in November until he was stopped in January the weather was too cold to permit the drying out of the mortar. It is undisputed that in April it was found that all mortar laid above the level of the ground before January 18th, and some laid after March 17th, was frozen and killed. It is likewise undisputed that about March 15th the board of public works ordered the plaintiff to complete the construction of the work within 10 days; that said plaintiff did proceed under such order, and completed said work, aside from pointing and plastering the walls and a small part of the coffer dam and the intake pipe. It is likewise undisputed that for a portion of the time during which work was done...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT