School District No. 1 of Clark County v. McCurley
Decision Date | 11 April 1914 |
Docket Number | 18,625 |
Citation | 142 P. 1077,92 Kan. 53 |
Parties | SCHOOL DISTRICT NO. 1 OF CLARK COUNTY, Appellee, v. G. F. MCCURLEY et al. (THE MASSACHUSETTS BONDING AND INSURANCE COMPANY, Appellant) |
Court | Kansas Supreme Court |
Decided January, 1914.
Appeal from Clark district court; GORDON L. FINLEY, judge.
Judgment affirmed.
SYLLABUS BY THE COURT.
1. BUILDING CONTRACT -- Surety Company -- Construction of Surety Bond. A bonding company engaged in the business of insuring the performance of contracts of others for pay is not a "favorite of the law" in the sense the term is applied to accommodation sureties.
2. SAME--No Notice of Contractor's Default to Bonding Company--No Damage--Liability. Such a company is not relieved of all liability upon a bond given by it to secure the performance of a builder's contract by reason of the failure of the obligee to give notice, according to the terms of the bond, of a failure of the builder to complete the building within the time specified, where such failure resulted in no actual loss or prejudice to the bonding company, notwithstanding the bond provides that no liability shall attach to the company unless such notice be given within a certain time after the default.
W. W. Harvey, of Ashland, D. A. Murphy, of Kansas City, Mo., and W. S. McClintock, of Topeka, for the appellant.
Francis C. Price, of Ashland, for the appellee.
OPINION
This action was brought by the school district to recover on the bond of the bonding company which insured the performance of the contract on the part of McCurley, the contractor, for the building of an addition to the schoolhouse of the appellee at Ashland.
After various motions and amendments to the pleadings were made and ruled upon, the case was tried in the district court to a jury, a motion for new trial made and overruled, and a judgment rendered in favor of the school district and against the bonding company for $ 2271.70. The bonding company appeals. Many assignments of error are made, but only four are urged in argument. In fact the appellant seems to argue all of these assignments of error together.
To save space we will refer to the contract between the school district and the contractor as the building contract, and to the bond given by the appellant as the insurance contract. It is urged that one of the provisions of the building contract was that the building should be completed by November 15, 1908. The bond provided that no liability should attach to the surety unless, in the event of any default on the part of the principal, the appellee should immediately, upon knowledge thereof and not later than thirty days after such default, deliver to the bonding company, at its office in Boston, written notice thereof.
It is conceded that the building contract was not completed November 15, 1908, and that no notice thereof was given to the bonding company within the time prescribed. On the part of the appellant it is claimed that this is a complete bar to the appellee's right of recovery. On the part of the appellee it is contended that no damage or loss is shown to have occurred to appellant by reason of the failure to give the notice, and hence the failure to give notice thereof constitutes no defense whatever to the action.
On the trial the jury found that the building was fully completed February 20, 1909, about three months after the time specified in the contract.
The appellee, conceding the facts upon which the contention is made, alleges that the bonding company suffered nothing by reason of the failure of notice, and this is the principal question in the case--whether the notice was so far a condition precedent to the right of the school district to recover as to defeat its action, or whether, if it appears that the insurer was not injured by lack of notice, it is still liable to pay.
A marked distinction is recognized by many of the courts as to the application of the rule as between contracts of an accommodation surety and the contract of a paid surety. As to the contracts of an accommodation surety, made dependent upon a condition precedent, the courts all agree that the strict letter of the contract will be enforced; but as to the contract of a paid surety, many of the courts, especially in the later decisions, inquire whether the surety was injured by the default of the condition, and if so, they enforce it only to the extent of the injury. In Hull v. Bonding Co., 86 Kan. 342, 120 P. 544, it was held that the rule that sureties are favorites of the law does not apply to corporations engaged in the business of furnishing bonds for profit.
In support of its contention the appellant cites Insurance Co. v. Thorp, 48 Kan. 239, 28 P. 991, in which it was held that the failure of an insured to give notice of the loss or damage by fire within sixty days after a loss has occurred, according to the contract, debarred the right of recovery. Also, Insurance Co. v. Russell, 65 Kan 373, 69 P. 345, which held valid a stipulation in a fire insurance policy that the policy should become void if the premises should become vacant without the consent of the company indorsed on the policy. Also, Insurance Co. v. Knerr, 72 Kan. 385, 83 P. 611, in which it was held that the failure to keep the books and invoices of the insured securely locked in a fire-proof safe, as provided in the policy, barred an action thereon. The reasons for these decisions, and others of like character, are obvious. In the Thorp case the failure to give the notice interfered with the right of the company to secure evidence of the character and extent of the loss. In the Russell case the vacancy presumably increased the hazard of loss and practically furnished a motive on the part of the insured to have a fire occur. The case of Fire Association v. Taylor, 76 Kan. 392, 91 P. 1070, although containing an expression which seems pertinent here, is not so in fact. The question there was the interpretation of an ambiguous contract. The case of The Y. M. C. A. v. Ritter, 90 Kan....
To continue reading
Request your trial-
Southern Surety Co. v. MacMillan Co.
...opinion that the judgment should be reversed with instructions to enter judgment for the Surety Company. 1 School Dist. No. 1 of Clark County v. McCurley, 92 Kan. 53, 142 P. 1077, Ann. Cas. 1916B, 238; Community Bldg. Co. v. Maryland Casualty Co. (C. C. A. 9) 8 F.(2d) 678, a decision render......
-
National Union Fire Ins. Co. of Pittsburgh, Pennsylvania v. F.D.I.C.
...this court decided that the rule applied to notice provisions in fidelity bonds as well as in insurance contracts. School District v. McCurley, 92 Kan. 53, 142 P. 1077 (1914). Then, according to the district court, when this court was called on to decide whether the rule applied to proof of......
-
City of Montpelier v. National Surety Co
... ... the March Term, 1922, Washington County, Butler, J., ... presiding. Verdict for the ... thereunder. Section 1 of the franchise specifies the terms ... and ... 219, 38 S.Ct. 57; Phelps v ... School Dist. , 302 Ill. 193, 134 N.E. 312, 21 A. L ... 408, 107 N.E. 298; School District v ... McCurley , 92 Kan. 53, 142 P. 1077, ... ...
-
New Amsterdam Casualty Co. v. US SHIPPING BOARD, ETC.
...Rep. 290; Ætna Indemnity Co. v. Waters, 110 Md. 673, 73 A. 712; United Surety Co. v. Summers, 110 Md. 95, 72 A. 775; School District v. McCurley, 92 Kan. 53, 142 P. 1077, Ann. Cas. 1916B, 238; Illinois Surety Co. v. Huber, 57 Ind. App. 408, 107 N. E. 298; Molin v. New Amsterdam Casualty Co.......