Sciaba Const. Corp. v. Frank Bean, Inc.

Decision Date30 June 1997
Docket NumberNo. 95-P-1400,95-P-1400
Citation43 Mass.App.Ct. 66,681 N.E.2d 288
PartiesSCIABA CONSTRUCTION CORPORATION v. FRANK BEAN, INC. & another. 1
CourtAppeals Court of Massachusetts

Owen Gallagher, Charlestown, for plaintiff.

Carol A. Griffin, Boston, for Frank Bean, Inc.

Fain P. Gildea, Brockton, for Thermal Insulation Corporation.

Before KASS, KAPLAN and GREENBERG, JJ.

KASS, Justice.

On its face, the language contained in subcontracts entered into by Sciaba Construction Corp. (Sciaba), a general contractor, and Frank Bean, Inc. (Bean), and Thermal Insulation Corp. (Thermal), subcontractors, egregiously violates G.L. c. 149, § 29C. That statute declared void a provision in a subcontract that requires the subcontractor to indemnify the general contractor for damages that the subcontractor did not cause. Section 29C has been the subject of much discussion of late in our cases. See Jones v. Vappi & Co., 28 Mass.App.Ct. 77, 81-82, 546 N.E.2d 379 (1989); Harnois v. Quannapowitt Dev., Inc., 35 Mass.App.Ct. 286, 288, 619 N.E.2d 351 (1993); Callahan v. A.J. Welch Equip. Corp., 36 Mass.App.Ct. 608, 611-612, 634 N.E.2d 134 (1994); M. DeMatteo Constr. Co. v. A.C. Dellovade, Inc., 39 Mass.App.Ct. 1, 3-4, 652 N.E.2d 635 (1995); Herson v. New Boston Garden Corp., 40 Mass.App.Ct. 779, 785-788, 667 N.E.2d 907 (1996); Collins v. Kiewit Constr. Co., 40 Mass.App.Ct. 796, 797-800, 667 N.E.2d 904 (1996); Miley v. Johnson & Johnson Orthopaedics, Inc., 41 Mass.App.Ct. 30, 31-34, 668 N.E.2d 369 (1996); Erland Constr. Co. v. Park Steel Corp., 41 Mass.App.Ct. 919, 919-920, 671 N.E.2d 953 (1996). Sciaba contends that the offending language, if examined beneath its face and in context, takes on innocent meaning. We do not think Sciaba's subcutaneous analysis persuasive and affirm the allowance by a judge of the Superior Court of a motion for summary judgment in favor of the subcontractors.

1. The accident. Sciaba had a general contract with the city of Boston to renovate the L Street Bathhouse. It let a subcontract for heating, ventilation and air conditioning to Bean which, in turn, subcontracted insulation work to Thermal. On December 28, 1987, Anthony Lusardi, an employee of Thermal, was injured at the construction site when he fell into a hole that had been covered with a sheet of plywood. Lusardi brought a third-party action (see G.L. c. 152, § 15) in Superior Court against Sciaba and Bean. Negligence issues were resolved in favor of Bean. A jury found that Sciaba had been negligent and, after Lusardi's percentage of negligence as found by the jury had been factored in (see G.L. c. 231, § 85), a judgment was entered in favor of Lusardi for $675,000, plus interest from December 26, 1990. This appeal concerns only Sciaba's claim for indemnification against Bean and Thermal.

2. The indemnity provision. First, it is well to bear in mind the pertinent text from G.L. c. 149, § 29C, inserted by St.1984, c. 484, § 43, and amended by St.1985, c. 228, § 3:

"Any provision for or in connection with a contract for construction ... which requires a subcontractor to indemnify any party for injury to persons or damage to property not caused by the subcontractor or its employees, agents or subcontractors, shall be void."

Second, we turn our attention to the text, so far as pertinent, of the indemnity provision incorporated in the subcontract Sciaba made with Bean and that made, in turn, by Bean with Thermal:

"13.2. Indemnification. The contractor shall assume the defense of and hold the Owner, Architect, their officers, agents and employees harmless from all suits and claims against them, ... and by or from any act or omission or neglect of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder (emphasis supplied)."

It is the unconditional indemnity demanded by the italicized language that offends G.L. c. 149, § 29C. The indemnification text quoted above does not appear in the subcontracts but appears, rather, in the general conditions of the general contract between the city of Boston, as owner, and Sciaba, as general contractor. The text was engrafted--and there is the rub--onto the subcontracts by § (1)(a) of the form subcontract 2 which provides:

"The Subcontractor agrees to be bound to the Contractor by the terms of the hereinbefore described plans, specifications (including all general conditions stated therein) and addenda ..., and to assume to the Contractor all the obligations and responsibilities that the Contractor by those documents assumes to the City of Boston, Public Facilities Commission ..., except to the extent that provisions contained therein are by their terms or by law applicable only to the Contractor (emphasis supplied)."

Among the obligations assumed by the general contractor to the city was the unconditional indemnity.

3. Discussion. In what we think is a contorted reading of the indemnification clause, Sciaba suggests that, as incorporated in the subcontracts, the unconditional indemnity applies only to relations between subcontractors and sub-subcontractors and, therefore, does not implicate § 29C. Nothing supports that construction except that Sciaba wishes it so. There is nothing about the case that impels us to abandon the generally trustworthy approach of interpreting a contractual provision in accordance with its plain meaning. Kelly v. Dimeo, Inc., 31 Mass.App.Ct. 626, 629, 581 N.E.2d 1316 (1991). We read the phrase "any Subcontractor" in the indemnity clause to mean precisely that,...

To continue reading

Request your trial
9 cases
  • North American Site Dev. V. Mrp Site Dev., No. 03-P-829.
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • May 16, 2005
    ...See Miley v. Johnson & Johnson Orthopaedics, Inc., 41 Mass.App.Ct. 30, 32, 668 N.E.2d 369 (1996); Sciaba Constr. Corp. v. Frank Bean, Inc., 43 Mass.App.Ct. 66, 69-70, 681 N.E.2d 288 (1997); Joseph Francese, Inc. v. DOS Concrete Servs., Inc., 47 Mass.App.Ct. 367, 369 n. 3, 713 N.E.2d 984 (19......
  • Robbins v. Krock
    • United States
    • Appeals Court of Massachusetts
    • November 13, 2008
    ...which is "used as a function word to indicate the maximum or whole of a number or quantity." See Sciaba Constr. Corp. v. Frank Bean, Inc., 43 Mass.App. Ct. 66, 69, 681 N.E.2d 288 (1997) (interpreting "`any Subcontractor' in the indemnity clause to mean precisely that, any subcontractor, whe......
  • Larrabee v. Mass. Comm'n Against Discrimination
    • United States
    • Appeals Court of Massachusetts
    • November 19, 2019
    ...Mass. Regs. § 1.04(4) (1999).Further, the word "any" in the regulation "mean[s] precisely that." Sciaba Constr. Corp. v. Frank Bean, Inc., 43 Mass. App. Ct. 66, 69, 681 N.E.2d 288 (1997). A broad construction also comports with the statutory presumption favoring disclosure under the public ......
  • American Insurance Co. v. Siena Construction Corp., 034929
    • United States
    • Massachusetts Superior Court
    • October 9, 2007
    ... ... Insurance Company, as subrogee for Lyme Properties, Inc. v. Siena Construction Corp. et al. No. 034929Superior ... 476, 478 (1986); see ... Sciaba Construction Corporation v. Frank Bean, Inc., 43 ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT