Seaboard Surety Co. v. United States

Decision Date07 October 1946
Docket NumberNo. 45519.,45519.
Citation67 F. Supp. 969
PartiesSEABOARD SURETY CO. v. UNITED STATES.
CourtU.S. Claims Court

Bernard J. Gallagher, of Washington, D. C. (M. Walton Hendry, of Washington, D. C., on the brief), for plaintiff.

E. E. Ellison, of Washington, D. C., and John F. Sonnett, Asst. Atty. Gen. (Robert Burstein, of Washington, D. C., on the brief), for defendant.

Before WHALEY, Chief Justice, and LITTLETON, WHITAKER, JONES, and MADDEN, Judges.

LITTLETON, Judge.

The only question now pressed in this case is whether plaintiff, as surety on a payment bond given pursuant to the act of August 24, 1935, 49 Stat. 793, 40 U.S. C.A. § 270a et seq., and the requirements of a contract with defendant, had an equitable lien on the portion of the contract price represented by the retained percentage in the hands of defendant after plaintiff had, by reason of the default of the contractor, paid certain claims of laborers and materialmen and had completed the contract. This question arose by reason of the fact that before defendant made payment of the balance due under the contract, including the retained percentage, the principal contractor, who had been declared in default, became indebted to the Government for certain taxes and had on May 10, 1938, made a general assignment for the benefit of its creditors. Plaintiff claims that it acquired an equitable lien on the retained percentage prior to the general assignment of May 10 which was superior to the preference or priority claimed by defendant under Section 3466 of the Revised Statutes, 31 U.S.C.A. § 191. On February 9, 1939, the Government under a claim of priority offset the amount of taxes due from the principal contractor against the amount of the retained percentage of $2,800 and paid to plaintiff the balance thereof, including $903.86, final contract balance. The amount of the offset for taxes due was $1,862.62, and plaintiff seeks to recover this amount.

No distraint was issued by defendant for the taxes, but defendant filed a claim with the trustees named in the assignment for the benefit of creditors, which it later withdrew on February 9, 1939, when it deducted the amount of said taxes from the balance due under the contract with the Peterson Construction Company, as set forth above.

The Peterson Construction Company (hereinafter sometimes referred to as Peterson) and the defendant, acting through the Bureau of Reclamation, Department of the Interior, entered into the contract in suit, No. 12r-6316, dated July 14, 1936. This contract called for performance of certain excavation and earthwork in connection with the All-American Canal System, Boulder Canyon project. The original contract price was $54,862.50, which appears to have been increased to $56,261.21.

In June, or in the early part of July, 1937, Peterson defaulted under the contract and under the payment bond by reason of its inability to pay the amounts due by it for certain claims for labor and material in the amount of $13,462.83. Peterson further defaulted in performance of the contract work, and its right to proceed further under the contract was terminated July 28, 1937. The plaintiff, as surety on the performance bond, completed the contract on August 17, 1937, and a contract balance of $3,703.86, which included the retained percentage of $2,800, remained due from defendant under the contract.

On August 8, 1936, Peterson entered into another and a much larger contract with defendant, No. 12r-6411 (which contract is not here in suit) relating to construction by plaintiff of certain washover chutes, drainage, inlets, and outlets for the All-American Canal System. Peterson also defaulted on this contract and plaintiff, as surety, paid out about $74,000 for labor and material claims thereunder, and also completed this contract. Upon such completion a balance of $26,807.85 remained due under this contract. Payment of the balance due under the contract in suit, No. 12r-6316, was apparently held up to await completion of the other contract, No. 12r-6411.

The payment and performance bonds given under the contract in suit, and on which plaintiff was surety, were required by and given under the provisions of the contract in suit and pursuant to the provisions and requirements of the act of August 24, 1935, 49 Stat. 793. At the time Peterson defaulted on its payment bond, which was prior to its default in performance, plaintiff was compelled to pay and did pay at that time $9,675.88 on due and unpaid claims of laborers and materialmen against Peterson, and subsequently paid an additional amount of $3,786.95 for such claims. The total of the claims so paid was $13,462.83. After the default of Peterson on its payment bond, certain progress payments thereafter becoming due from the Government to Peterson under the contract in suit for contract work performed by Peterson to date of default in performance on July 28, 1937, were delivered by the defendant to plaintiff, and the total of the progress payments so received by plaintiff was $7,685.00. In addition plaintiff received $4.46 from Peterson. The total of these amounts was used by plaintiff in making payments for Peterson's payroll and for materials to July 28, 1937, when the Government terminated Peterson's right to proceed, and thereafter plaintiff used the balance for the same purposes in completing the work. As above stated, plaintiff completed the unfinished work on August 17, 1937, and in doing so earned and in February 1939 received the unpaid balance of $903.86 and, also, $937.38 of the $2,800, retained percentage remaining in the hands of the Government upon completion and acceptance of the contract work. The balance of $1,862.62 of the $2,800, retained percentage, was applied by defendant through the Comptroller General on February 9, 1939, as an offset in satisfaction of that amount due the Government by Peterson for accrued taxes, penalties and interest representing capital stock tax for the fiscal year ending June 30, 1937, and Social Security tax for the calendar year 1937 and the first quarter of 1938.

After payment by plaintiff of labor and materialmen claims against Peterson and after completion of the contract Peterson made a general assignment on May 10, 1938, for the benefit of creditors, and the properties and assets of Peterson Company thereupon passed into the hands of the trustees.

Upon the making of this general assignment there arose a statutory preference or priority under R.S. § 3466, 31 U.S. C.A. § 191, in favor of the Government in respect of the debt due it by Peterson for the taxes above mentioned. In addition to the statutory priority the Government, by giving notice and demand on October 20, 1937, and April 26, 1938, had acquired a lien under the act of March 4, 1913, 37 Stat. 1016, as to a part of this tax debt, and by further notice and demand acquired such lien as to the balance of the debt on May 17 and June...

To continue reading

Request your trial
17 cases
  • Crain v. United States
    • United States
    • U.S. Claims Court
    • July 11, 1949
    ...were arbitrary or capricious, not only with respect to the year 1937 but also with respect to the offsets. Seaboard Surety Company v. United States, 67 F. Supp. 969, 107 Ct.Cl. 34, 44. They have not sustained this burden. The cases relied upon by plaintiffs in support of their contention th......
  • In re Cummins Const. Corporation, 9876.
    • United States
    • U.S. District Court — District of Maryland
    • December 3, 1948
    ...place a lien." On the same day that the Court of Claims' decided the Munsey case it rendered its decision in Seaboard Surety Co. v. United States, 67 F.Supp. 969, 107 Ct. Cl. 34. There, the decision was against the surety who had paid materialmen after default but before a general assignmen......
  • IN RE JONKER CORPORATION, In Bankruptcy No. M-13856.
    • United States
    • U.S. District Court — District of Maryland
    • November 25, 1974
    ...v. Agricultural Stabilization and Conservation State Committee for Arizona, 299 F.2d 516 (9th Cir. 1962); Seaboard Surety Co. v. United States, 67 F.Supp. 969, 107 Ct.Cl. 34 (1946), cert. denied, 330 U.S. 826, 67 S.Ct. 863, 91 L.Ed. 1275 (1947). These cases clearly establish the view "The g......
  • Lawrence and Tuttle
    • United States
    • Comptroller General of the United States
    • April 11, 1963
    ... LAWRENCE AND TUTTLE No. B-150854Comptroller General of the United StatesApril 11, 1963 ... Your ... letter of ... all merchandise imported into the United States shall be held ... to be the property of the person to whom the same ... Munsey ... trust company, 332 U.S. 234; and seaboard surety Co.V. United ... States, 67 F.Supp. 969. Thus any refund in ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT