Sellersburg Stone Co. v. Federal Mine Safety and Health Review Com'n

Citation736 F.2d 1147
Decision Date11 June 1984
Docket NumberNo. 83-1630,83-1630
Parties1984-1985 O.S.H.D. ( 26,934 SELLERSBURG STONE COMPANY, Petitioner, v. FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION, Secretary of Labor, and Mine Safety and Health Administration, (MSHA), Respondents.
CourtU.S. Court of Appeals — Seventh Circuit

Edwin S. Sedwick, Sedwick & Sedwick, Sellersburg, Ind., for petitioner.

Anna L. Wolgast, U.S. Dept. of Labor, Arlington, Va., for respondents.

Before CUDAHY and FLAUM, Circuit Judges, and BARTELS, Senior District Judge. **

FLAUM, Circuit Judge.

In this case we review an order issued by the Federal Mine Safety and Health Review Commission ("Commission"), which affirmed the decision of an administrative law judge ("ALJ") finding violations of the Federal Mine Safety and Health Amendments Act of 1977 and assessing penalties for these violations. For the reasons set forth below, we affirm and enforce the order.

Sellersburg Stone Company ("Sellersburg") operates an open-pit limestone quarry and a crushed limestone operation in Clark County, Indiana. The mining technique used by Sellersburg involves a two-step procedure. In the first step, "primary blasting," boulders are blasted from the side of the quarry. Those boulders that are too large to pass through the stone-crusher then are moved by a front-end loader to the floor of the quarry, where they are closely clustered, in preparation for "secondary blasting." In this second step, workers drill a hole into each boulder and place a stick of dynamite in each hole. The workers add a primer cord to each stick of dynamite and pack each hole with fine stones. The dynamite in approximately twenty boulders is then detonated at one time. If, after the detonation, a dynamite charge does not explode, the standard safe practice in the industry is to inspect all remaining boulders for undetonated dynamite by turning the boulders over. 1 Sellersburg, however, did not follow this practice. It relied instead upon the workers' visual inspection of only the top sides of the boulders.

On December 13, 1979, two Sellersburg workers were engaged in secondary blasting. David Hooper drilled the boulders that had been collected in a cluster, while Carl Sparrow loaded the drill holes with sticks of dynamite and added the primer cord to the dynamite. After Hooper and Sparrow detonated the dynamite of about twenty boulders, Hooper began inspecting and drilling the remaining boulders. He inspected the top of one boulder, but he did not have the equipment to turn it over in order to inspect its bottom. Hooper then began drilling the boulder, but when the drill was about halfway through the boulder the boulder exploded, causing him permanent disabling injuries. 2

After Hooper was taken to the hospital, Sellersburg did not preserve the accident site. Instead, it removed or disturbed all evidence of the accident and then resumed normal mining activity. In addition, Sellersburg did not inform the Mine Safety and Health Administration of the Department of Labor ("MSHA") about the accident until January 2, 1980, when it mailed a written report of the accident to the MSHA's subdistrict office located in Vincennes, Indiana.

On January 3, 1980, MSHA inspectors examined the petitioner's quarry and issued three citations to Sellersburg for violating three MSHA regulations: 30 C.F.R. Secs. 50.10, 50.12, 56.6-106. 3 An assessment officer of the MSHA proposed, on July 2, 1980, that the petitioner be assessed penalties of $78 for the violation of section 50.10, $78 for the violation of section 50.12, and $1000 for the violation of section 56.6-106. On July 25, 1980, Sellersburg notified the Secretary of Labor that it would contest the citations and the proposed penalties. Several weeks later, on August 8, 1980, the Secretary petitioned the Commission for an assessment of the proposed civil penalties, in accordance with 29 C.F.R. Sec. 2700.27.

A hearing on the petition for assessment took place before an ALJ on December 10, 1981. The ALJ issued his decision on July 26, 1982, affirming the violations and imposing penalties of $1000 for the violation of section 50.10, $1000 for the violation of section 50.12, and $7500 for the violation of section 56.6-106. Sellersburg then petitioned the Commission for discretionary review of the ALJ's decision, and review was granted on September 1, 1982. In a decision dated March 11, 1983, the Commission affirmed the ALJ's findings of violations and his assessment of penalties. On April 6, 1983, Sellersburg filed a petition for review with this court, arguing both that the ALJ made insufficient factual findings to support his determination that Sellersburg violated section 56.6-106, and that the amount of penalties assessed is contrary to law and constitutes an abuse of discretion.

Factual Findings Relating to 30 C.F.R. Sec. 56.6-106

Section 56.6-106 of the MSHA regulations requires that, at mining operations, "faces and muck piles" must be examined for undetonated explosives. 4 Sellersburg argues that, since the ALJ did not find specifically that the boulder that exploded and injured Hooper was part of a muck pile, the ALJ's finding of a violation of section 56.6-106 must be vacated or modified. The Commission considered this argument in its review of the ALJ's decision, and it concluded that the ALJ implicitly had found the boulder to be part of a muck pile. Furthermore, the Commission concluded that the ALJ's findings sufficiently supported his determination that Sellersburg violated section 56.6-106.

Under the Commission's regulations, decisions of ALJs must "include findings of fact, conclusions of law, and the reasons or bases for them, on all material issues of fact, law or discretion presented by the record." 29 C.F.R. Sec. 2700.65 (1983). Such findings and conclusions are also mandated by section 557(c) of the Administrative Procedure Act. See 5 U.S.C. Sec. 557(c)(3)(A)(1982). 5 In interpreting section 557(c), the Supreme Court has held that, where an agency makes no specific findings upon a contention, the agency complies with the Administrative Procedure Act if it considers the contention and discusses it. Minneapolis & St. Louis Railway Co. v. United States, 361 U.S. 173, 193, 80 S.Ct. 229, 241, 4 L.Ed.2d 223 (1959). Federal courts also have held that they are not disposed to overturn an agency's decision on the basis of section 577(c) "if the agency's path, although not ideally clear, may reasonably be discerned." Benmar Transport & Leasing Corp. v. ICC, 623 F.2d 740, 746 (2d Cir.1980). See also Wasson v. SEC, 558 F.2d 879, 884 (8th Cir.1977); Chieppo Bus Co. v. United States, 383 F.Supp. 1192, 1198 (D.Conn.1974).

In the present case, the ALJ found that Sellersburg "did not properly examine the muck pile after secondary blasting, because after such blasting it drilled boulders without turning them over to examine each boulder for a dynamite drill hole on the bottom of the boulder." ALJ Decision dated July 26, 1982, at 3. It is apparent from the ALJ's brief discussion that he considered and decided that the boulder that injured Hooper was part of a muck pile. We thus are able to discern the path taken by the ALJ, and we hold that this path sufficiently supports his determination of a violation of section 56.6-106.

Penalties

According to Sellersburg, the penalties in this case were assessed erroneously because the ALJ and the Commission failed to make the findings required for "determination of penalty amount" as outlined in 30 C.F.R. Sec. 100.3(a). Sellersburg cites Allied Products Co. v. FMSHRC, 666 F.2d 890 (5th Cir.1982), for the proposition that both the ALJ and the Commission must follow the procedure set forth in section 100.3(a), and it argues that in the absence of appropriate findings, the penalties must be deemed excessive, arbitrary and capricious, and an abuse of discretion.

In its decision affirming the penalties assessed by the ALJ, the Commission expressed its position that the Allied decision "misperceived the penalty assessment authority of the Commission and its judges under the Act." Commission Decision dated March 11, 1983, at 4. The Commission stated that, in contested cases, the amount of the penalties to be assessed by the Commission and its judges is a de novo determination based on the six statutory criteria specified in 30 U.S.C. Sec. 820(i). Applying section 820(i), the Commission concluded that the ALJ erred in failing to make specific findings regarding four of the six criteria. However, the Commission determined from the record that information relating to these four criteria had been uncontested. Choosing not to remand the case for specific findings, the Commission entered the uncontested information as the required findings. It then ruled that in light of all the findings, the assessed penalties were not excessive.

We begin with a review of the process of penalty assessment under the Federal Mine Health and Safety Act ("Act"). The Act empowers the Secretary of Labor, acting through the MSHA, to issue citations against mine operators that have violated the standards of the Act and also to propose civil penalties for these violations. See 30 U.S.C. Secs. 814(a), 815(a) (1982). In proposing penalties, the Secretary must consider the six criteria listed in 30 U.S.C. Sec. 815(b)(1)(B) (1982). 6 Applying these criteria, the Secretary assigns penalty points and then converts the points into proposed penalty amounts, pursuant to MSHA regulations. See 30 C.F.R. Sec. 100.3 (1980). 7

If a mine operator timely notifies the Secretary of its intent to contest the Secretary's citations or proposed penalties, the Secretary must advise the Commission of such notification, and the Commission must afford an opportunity for a hearing before an ALJ. See 30 U.S.C. Secs. 815(d), 823(d) (1982). The ALJ, after determining that a violation has occurred, may affirm,...

To continue reading

Request your trial
9 cases
  • Thunder Basin Coal Co. v. Martin
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • 20 Julio 1992
    ...C.F.R. § 2700.29(b) (ALJ and Commission not bound by penalty recommended by Secretary); Sellersburg Stone Co. v. Federal Mine Safety & Health Review Comm'n, 736 F.2d 1147, 1151-52 & n. 11 (7th Cir.1984) In any event, Thunder Basin may have the merits of its claims decided without risking su......
  • RAG Cumberland Resources LP v. Fed. Mine Safety & Health Review Comm'n
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 7 Diciembre 2001
    ...1076, 1085 n.6 (10th Cir. 1998) (holding remand unnecessary where the "essential facts were not in dispute"); Sellersburg Stone Co. v. FMSHRC, 736 F.2d 1147, 1153 (7th Cir. 1984) (holding remand not required "[g]iven the Commission's conclusion that uncontroverted evidence did not warrant f......
  • K & I Transfer & Storage, Inc. v. N.L.R.B.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • 18 Noviembre 1986
    ...R.R. v. United States, 361 U.S. 173, 193-94, 80 S.Ct. 229, 241-42, 4 L.Ed.2d 223 (1961); Sellersburg Stone Co. v. Federal Mine Safety and Health Review Commission, 736 F.2d 1147, 1150 (7th Cir.1984); Trailways, Inc. v. I.C.C., 676 F.2d 1019, 1022 (5th Cir.1981)). We are also unwilling to ho......
  • Amoco Production Co. v. F.E.R.C.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • 17 Mayo 1985
    ...Interstate Gas Co. v. FPC, 324 U.S. 581, 595, 65 S.Ct. 829, 836, 89 L.Ed. 1206 (1945); Sellersburg Stone Co. v. Federal Mine Safety & Health Review Comm'n, 736 F.2d 1147, 1150 (7th Cir.1984); Benmar Transport & Leasing Corp. v. ICC, 623 F.2d 740, 746 (2d Cir.1980). A company has to have a r......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT