Sellner v. Beechwood Const. Co., Inc.

Decision Date09 January 1979
Citation407 A.2d 1026,176 Conn. 432
CourtConnecticut Supreme Court
PartiesH. Ascher SELLNER et al. v. BEECHWOOD CONSTRUCTION COMPANY, INC., et al.

James R. Fogarty, Stamford, with whom was James J. Huron, Stamford, for appellants (defendants).

Joseph M. Brophy, Westport, for appellees (plaintiffs).

Before COTTER, C. J., and LOISELLE, BOGDANSKI, LONGO and PETERS, JJ.

PETERS, Associate Justice.

This case arises out of two contracts for the construction and sale of a new one-family residence in the town of Brookfield. In 1973, a construction contract was negotiated between the plaintiffs, H. Ascher Sellner and his wife Sandra A. Sellner, and the defendant Beechwood Construction Company, Inc. This contract was signed on behalf of Beechwood by its president, the defendant Simon Aragi. Aragi himself, on his own behalf, subsequently conveyed the land and the building to the Sellners in 1974. When the plaintiffs took possession they encountered problems with the basement, the plumbing, and the septic system. After unsuccessful attempts to have the defendants remedy these alleged defects, the plaintiffs sued both defendants in a four-count complaint alleging: (1) breach of contract; (2) breach of the statutory warranty contained in § 52-563a of the General Statutes; (3) breach of the express warranty in the construction contract; and (4) negligence. After a trial to a jury, the plaintiffs were awarded $15,000 on a general verdict. Judgment was rendered for the plaintiffs in this amount after denial of the defendants' motion to set aside the verdict. Both defendants have appealed.

The defendants' appeal challenges: (1) the legality of a prejudgment remedy afforded to the plaintiffs; (2) the propriety of amendment of the plaintiffs' complaint late in the trial in order to establish a basis for piercing the corporate veil to make Aragi personally liable on the Beechwood construction contract; and (3) the amount of the verdict awarded to the plaintiffs. These various claims must be addressed separately.

I

The plaintiffs' action was begun through an application for a prejudgment remedy in the form of an attachment on real estate, under 1973 Public Acts, No. 73-431, § 5. 1 Under that statute, enacted in response to the constitutional instructions of Fuentes v. Shevin, 407 U.S. 67, 92 S.Ct. 1983, 32 L.Ed.2d 556 (1972), and Sniadach v. Family Finance Corporation, 395 U.S. 337, 89 S.Ct. 1820, 23 L.Ed.2d 349 (1969), prejudgment remedies were no longer to be automatically issued by attorneys as commissioners of the Superior Court. Instead, such remedies were to be granted only by a court and, except under the exceptional circumstances specified by the statute, only after a hearing conducted in accordance with the requirements of due process. See General Statutes §§ 52-278c, 52-278d. In this case, the plaintiffs asked for and received an ex parte attachment under § 52-278e, 2 alleging probable cause that there was a reasonable likelihood that the defendants were about to dispose of their property fraudulently with the intent to hinder, delay or defraud their creditors. The plaintiffs' supporting affidavit averred that threats of personal violence by the individual defendant had led to the belief that the defendant would do everything in his power to obstruct collection of damages, including the transfer of any possible property for attachment for satisfaction of such debt.

In accordance with the procedures specified by § 52-278e, the defendants moved promptly to dissolve the prejudgment remedy, but this motion was denied after a hearing. The defendants subsequently moved to reduce the amount of the attachment, but this motion also was denied after a hearing which the defendants' counsel did not attend. No direct appeal was taken from the denial of either motion. We have held that "prejudgment remedy proceedings pursuant to the provisions of Public Act 73-431 (now §§ 52-278a et seq.) are not involved with the adjudication of the merits of the action brought by the plaintiff or with the progress or result of that adjudication. They are only concerned with whether and to what extent the plaintiff is entitled to have property of the defendant held in the custody of the law pending adjudication of the merits of that action. . . . The decision of the court in the separate and distinct proceeding prescribed by Public Act 73-431 concludes the rights of the parties as to the available prejudgment remedy so that further proceedings in the determination of the merits of the action alleged in the plaintiff's complaint cannot affect them. We conclude that the order is a final judgment from which an appeal may be taken." E. J. Hansen Elevator, Inc. v. Stoll, 167 Conn. 623, 629-30, 356 A.2d 893, 896 (1975).

The defendants admit that they have failed to take a timely appeal, or to file a timely notice of appeal, of the disputed prejudgment remedy order. They urge, however, that the issue of its validity is one of constitutional dimension, that procedural due process is at stake. This court has on occasion decided untimely appeals on their merits when a constitutional issue would otherwise remain unresolved, or in order "to facilitate business and advance justice." Silverman v. St. Joseph's Hospital, 168 Conn. 160, 171, 363 A.2d 22, 27 (1975); State v. Chesney, 166 Conn. 630, 639, 353 A.2d 783, cert. denied, 419 U.S. 1004, 95 S.Ct. 324, 42 L.Ed.2d 280 (1974). See rules of practice, July 1, 1978, § 3164. We do not believe, however, that this case presents the compelling circumstances that must be shown to warrant our decision of an issue untimely raised and collateral to the judgment on appeal.

The defendants do not attack § 52-278e as inherently procedurally incompatible with the requirements of constitutional due process. They concede that they were afforded the prompt postseizure hearings that the statute prescribes. They claim only that the plaintiffs' affidavit was defective because it failed to allege sufficient facts to show the presence of any of the exceptional circumstances mandated by § 52-278e and because it contained no evidentiary statement of the damages allegedly sustained. In essence their quarrel is neither with the statute nor with the procedures that were followed but rather with the allegedly erroneous conclusions reached at the various hearings on these matters below. Whatever the substantive merits of these contentions; see Ledgebrook Condominium Assn., Inc. v. Lusk Corporation, 172 Conn. 577, 376 A.2d 60 (1977); they do not warrant a bypass of the normal avenue of a direct and timely appeal. The judgment below cannot now be collaterally impeached on this basis.

II

The defendants do not on this appeal contest the substantive judgment below insofar as it imposed liability upon the corporate defendant Beechwood. They do challenge the sufficiency of the evidence to support the verdict against the individual defendant Aragi. In this connection, they argue that the trial court acted improperly in permitting the plaintiffs, late in the trial, to amend their complaint in order to allege that Beechwood was a "mere instrumentality" for its president, Aragi, and to hold Aragi personally liable on the breach of contract and breach of warranty counts on which he had previously not been personally charged. Aragi had from the outset been a named defendant on the fourth count of negligence. The defendants allege error in the allowance of this amendment on the ground that it was untimely and that no excuse was offered for the delay.

This court has held repeatedly that the decision whether to allow an amendment to the pleadings lies within the sound discretion of the court, and that such a ruling may be reversed only upon a clear showing of abuse of discretion. Phaneuf v. Commissioner of Motor Vehicles, 166 Conn. 449, 454, 352 A.2d 291 (1974); Robinson v. Faulkner, 163...

To continue reading

Request your trial
15 cases
  • DeJesus v. R.P.M. Enters., Inc.
    • United States
    • Connecticut Court of Appeals
    • May 18, 2021
    ...allowed to decide the piercing the corporate veil claim, he would lose his right to a jury trial. See Sellner v. Beechwood Construction Co ., 176 Conn. 432, 433, 437, 407 A.2d 1026 (1979) (jury returned verdict piercing corporate veil of defendant construction company); see also American Pr......
  • Shaumyan v. O'NEILL
    • United States
    • U.S. District Court — District of Connecticut
    • June 27, 1989
    ...party proves probable cause to sustain the validity of his claim. Id. at 397-98, 423 A.2d at 83. Accord Sellner v. Beechwood Constr. Co., 176 Conn. 432, 434, 407 A.2d 1026, 1028 (1979) (section 52-278e "enacted in response to the constitutional instructions of Fuentes ... and Sniadach....")......
  • Ford Motor Credit Co. v. B.W. Beardsley, Inc.
    • United States
    • Connecticut Supreme Court
    • June 21, 1988
    ...by the statute, only after a hearing conducted in accordance with the requirements of due process." Sellner v. Beechwood Construction Co., 176 Conn. 432, 434, 407 A.2d 1026 (1979). In order to comply with due process, notice and an opportunity to be heard must be afforded litigants " 'at a ......
  • Naples v. Keystone Building and Development Corporation, (SC 18397) (Conn. 3/30/2010)
    • United States
    • Connecticut Supreme Court
    • March 30, 2010
    ...Presuming that the plaintiffs meant instead to cite the published opinion on the merits of that appeal; Sellner v. Beechwood Construction Co., 176 Conn. 432, 407 A.2d 1026 (1979); we note that, in that case, although the trial court had rendered judgment in that case in accordance with the ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT