O'shield v. Lakeside Bank

Decision Date27 November 2002
Docket NumberNo. 1-01-2065.,1-01-2065.
Citation269 Ill.Dec. 924,335 Ill. App.3d 834,781 N.E.2d 1114
PartiesLeroy O'SHIELD and Beverly O'Shield, Plaintiffs-Appellants, v. LAKESIDE BANK, a Corporation, as Trustee Under Trust Agreement dated September 5, 1996, and Known as Trust No. 10-1789; 5350 South Shore, L.L.C., a Limited Liability Corporation; Horwitz and Company, Inc., an Illinois Corporation; and Tem Horwitz, Defendants-Appellees.
CourtUnited States Appellate Court of Illinois

Leon M. Despres and Jorge Sanchez, both of Despres, Schwartz & Geoghegan, of Chicago, for appellants.

Lawrence M. Karlin, of Katz, Randall, Weinberg & Richmond, of Chicago, for appellees.

Justice GORDON delivered the opinion of the court:

Plaintiffs LeRoy O'Shield and Beverly O'Shield (plaintiffs) appeal from the trial court's order denying their motion for reconsideration of a prior order granting summary judgment to defendants Lakeside Bank, 5350 South Shore, L.L.C., Horwitz & Co., and Tem Horwitz (defendants) in relation to a real estate purchase contract. Plaintiffs ask that we order specific performance of the contract or, alternatively, that we reverse the trial court's grant of summary judgment and remand this cause. Because we find that plaintiffs' exclusive remedy was return of their earnest money, we affirm.

BACKGROUND

In November 1996, plaintiffs entered into a contract for the purchase a townhouse being built by defendants1 in the development known as 5350 South Shore Drive Townhomes. The contract signed by plaintiffs and defendants contained the following provisions:

"3. Date of Completion. * * * If the Townhouse has not been substantially completed within one hundred eighty (180) days after the Estimated Completion Date * * *, then Purchaser may, as its sole remedy, terminate this Agreement upon five (5) days prior written notice to Seller and the Earnest Money, and all interest which may have been earned thereon, and all other sums paid by Purchaser to Seller shall be refunded to Purchaser, whereupon this Agreement shall be null and void without further liability to Seller.
* * *

14. Defaults and Termination. * * * If Seller fails to perform any of Seller's obligations under this Agreement and such failure continues for ten (10) days after Purchaser delivers to Seller written notice of such failure, Purchaser's only remedy shall be to terminate this Agreement by written notice delivered to Seller. Upon such termination resulting from Seller's failure to perform any of its obligations under this Agreement, all payments made by Purchaser to Seller under this Agreement shall be returned to Purchaser and thereupon this Agreement shall be null and void, and of no further force and effect, and neither party shall have any further rights or obligations thereunder."

During construction of the townhouse, plaintiffs made two earnest money payments to defendants, for a total of $48,050. However, once it was built, defendants, in breach of contract, refused to complete the sale of the townhouse to plaintiffs.

Plaintiffs thereupon filed a one-count complaint against defendants for specific performance of the sales contract. Defendants moved to dismiss. Before any determination was made on this motion, plaintiffs were granted leave to file an amended complaint, adding a second count for money damages for interest on the earnest money and a third count for intentional infliction of emotional distress. Defendants again moved to dismiss, stating that the exclusive remedies provisions found in paragraphs 3 and 14 of the contract barred specific performance. Plaintiffs obtained leave to further amend their amended complaint, whereupon they included, among other contentions, allegations of racial bias and specific allegations of individual liability with respect to Tem Horwitz as president of Horwitz & Co. in a separate count. Defendants' motion to dismiss was denied.

After discovery was conducted, defendants moved for partial summary judgment, asserting that the contract's provisions mandated summary judgment with respect to plaintiffs' claim for specific performance, that the count for individual liability against Tem Horwitz should be dismissed with prejudice, and that summary judgment should be granted on the issue of racial bias. The trial court granted defendants' motion in part and denied it in part. First, the court granted summary judgment to defendants on the question of racial bias, finding that plaintiffs failed to adequately demonstrate their claim. Second, the court denied summary judgment in relation to Tem Horwitz's individual liability, finding that plaintiffs had alleged sufficient facts in this regard. Finally, as to specific performance, the court granted defendants' motion for summary judgment, finding that there were no genuine issues of material fact. The court held that the contract's terms, as exemplified in paragraphs 3 and 14, were clear and unambiguous that plaintiffs' "only remedy in case of nonperformance by the [d]efendants is to void the contract and have all payments returned." (Emphasis in original.) Therefore, concluded the court, because plaintiffs "failed to show that there are genuine issues of material fact in dispute as to whether the [contract] bars specific performance from being sought as a remedy," summary judgment for defendants on this count was proper.

Plaintiffs then filed an emergency motion to vacate the trial court's order as to its findings regarding specific performance only. Alternatively, plaintiffs asked the court to enter Supreme Court Rule 304(a) (155 Ill.2d R. 304(a)) language allowing for appeal. This motion was adopted by the court, with the parties' agreement, as a motion for reconsideration. The court denied plaintiffs' motion and certified the issue of specific performance for interlocutory appeal.

ANALYSIS

Before addressing the substantive issue presented in this cause, we first clarify the applicable standard of review. As noted above, plaintiffs appeal from the trial court's denial of their motion to reconsider its prior order granting summary judgment to defendants. Plaintiffs claim in their memorandum in support of their motion to reconsider that the court erred in its application of the law when it granted defendants' motion for partial summary judgment on the issue of specific performance. Defendants assert that we should review the court's denial of plaintiffs' motion for reconsideration under an abuse of discretion standard. We disagree, as it is unquestionable that the standard of review applicable to this cause is de novo. A motion to reconsider based on the submission of new matters, such as additional facts or new arguments or legal theories not presented during the pendency of the original motion for summary judgment, is reviewed under an abuse of discretion standard. See, e.g., Delgatto v. Brandon Associates, Ltd., 131 Ill.2d 183, 195, 137 Ill.Dec. 36, 545 N.E.2d 689 (1989) (submitting a new matter on a motion to reconsider after summary judgment motion has already been granted "lies in the discretion of the trial court"). Such a motion asks the trial court to allow the losing party a "second bite of the apple," i.e., requiring the court to determine whether it should admit these new matters into evidence and, in turn, reconsider its prior decision based upon them. That determination is subject to the trial court's discretion. See Delgatto, 131 Ill.2d at 195; 137 Ill.Dec. 36, 545 N.E.2d 689; see also Korogluyan v. Chicago Title & Trust Co., 213 Ill.App.3d 622, 627, 157 Ill.Dec. 690, 572 N.E.2d 1154 (1991) (general rule is that motion to reconsider based on new matters not presented during prior motion is for the trial court's discretion). However, whether or not the new matters are admitted through the motion to reconsider, the standard used to review the trial court's application of existing law, namely, its application of law to the facts presented, always remains de novo. See Sacramento Crushing Corp. v. Correct/All Sewer Inc., 318 Ill.App.3d 571, 577, 252 Ill.Dec. 291, 742 N.E.2d 829 (2000), quoting Korogluyan, 213 Ill.App.3d at 627,157 Ill.Dec. 690,572 N.E.2d 1154 ("`a motion to reconsider an order granting summary judgment raises the question of whether the judge erred in his previous application of existing law. Whether the court has erred in the application of existing law is not reviewed under an abuse-of-discretion standard.' [Citation.] As with any question regarding the application of existing law, we review the denial of such a motion de novo"). A party cannot convert the de novo standard applicable to the original motion into an abuse of discretion standard simply by asking the court to reconsider its previous ruling. See Sacramento Crushing Corp.,318 Ill.App.3d at 577,252 Ill.Dec. 291,742 N.E.2d 829; Korogluyan, 213 Ill.App.3d at 627,157 Ill. Dec. 690,572 N.E.2d 1154. In the instant case, plaintiffs' motion to reconsider does not rest on the presentation of new matters nor on a determination of whether any new facts or arguments should be reconsidered with respect to the original motion for summary judgment. Rather, plaintiffs assert error on the part of the trial court with respect to its application of substantive law when it first granted defendants' motion for summary judgment and, in effect, asks the court to rethink what it already thought. Accordingly, this issue, which brings into question the propriety of the trial court's application of substantive law to the facts presented before it, merits de novo review. See Sacramento Crushing Corp.,318 Ill.App.3d at 577,252 Ill. Dec. 291,742 N.E.2d 829; Korogluyan, 213 Ill.App.3d at 627,157 Ill.Dec. 690,572 N.E.2d 1154.

We now turn to the substantive issue in this case; namely, whether the trial court erred in dismissing plaintiffs' count for specific performance based on those provisions of the contract which purport to limit their remedy to a...

To continue reading

Request your trial
50 cases
  • Lobo Iv, LLC v. V Land Chi. Canal, LLC
    • United States
    • United States Appellate Court of Illinois
    • March 21, 2019
    ...We agree. ¶ 80 The parties' rights under a contract are limited by the terms expressed therein. O'Shield v. Lakeside Bank , 335 Ill. App. 3d 834, 839, 269 Ill.Dec. 924, 781 N.E.2d 1114 (2002). Parties may contract for an exclusive remedy under the contract, and "[o]nce made and agreed upon,......
  • CNB Bank & Trust, N.A. v. Rosentreter
    • United States
    • United States Appellate Court of Illinois
    • September 3, 2015
    ...underlying issues are legal rather than factual, “we will proceed de novo. ” Id. ¶ 24. See also O'Shield v. Lakeside Bank, 335 Ill.App.3d 834, 838, 269 Ill.Dec. 924, 781 N.E.2d 1114 (2002) (noting that a “party cannot convert the de novo standard applicable to the original motion into an ab......
  • Daniels v. Corrigan
    • United States
    • United States Appellate Court of Illinois
    • March 31, 2008
    ...of the original motion for summary judgment, is reviewed under an abuse-of-discretion standard. O'Shield v. Lakeside Bank, 335 Ill.App.3d 834, 838, 269 Ill.Dec. 924, 781 N.E.2d 1114 (2002). See Delgatto v. Brandon Associates, Ltd., 131 Ill.2d 183, 195, 137 Ill.Dec. 36, 545 N.E.2d 689 (1989)......
  • Windy City Limousine Co. v. Milazzo
    • United States
    • United States Appellate Court of Illinois
    • December 20, 2018
    ...of existing law, that party, in essence, "ask[s] the court to rethink what it already thought." O'Shield v. Lakeside Bank , 335 Ill. App. 3d 834, 838, 269 Ill.Dec. 924, 781 N.E.2d 1114 (2002). As such, our review is of the court's original ruling. Papadakis , 2018 IL App (1st) 170388, ¶ 13,......
  • Request a trial to view additional results