Siemens Westinghouse Power Corp. v. Dick Corp.

Decision Date14 January 2004
Docket NumberNo. 03 CIV.364 VM.,03 CIV.364 VM.
Citation299 F.Supp.2d 242
PartiesSIEMENS WESTINGHOUSE POWER CORPORATION, Plaintiff, v. DICK CORPORATION, Defendant/Counterclaim Plaintiff, Continental Casualty Company and National Fire Insurance Company of Hartford, Defendants. Dick Corporation, on Behalf of the Consortium of Dick Corporation and Siemens Westinghouse Power Corporation, and Individually, Third-Party Plaintiff, v. AES Londonderry, L.L.C., Sycamore Ridge, L.L.C., Stone & Webster, Inc., Limbach Company and Sachs Electric Company, Third-Party Defendants.
CourtU.S. District Court — Southern District of New York

Gregory N. Chertoff, Peckar & Abramson, P.C., New York, NY, for Plaintiff.

John T. Bergin, Richard M. Preston, Seyfarth Shaw, Washington, DC, John C Sabetta, Seyfarth Shaw, New York, NY, for Defendants.

DECISION AND ORDER

MARRERO, District Judge.

Defendant and third-party plaintiff Dick Corporation ("Dick") moves this Court for leave to file a second amended answer and counterclaim for the purpose of, among other things, adding updated counterclaims of negligent misrepresentation and fraudulent concealment. Plaintiff Siemens Westinghouse Power Corporation ("SWPC") opposes the motion on the ground that the proposed amended filing would be futile with respect to those counterclaims. The Court agrees that those claims would not survive a motion to dismiss because they fail to sufficiently allege justifiable reliance upon the alleged misrepresentations and omissions. The motion is therefore denied with respect to those proposed amendments, and, in all other respects, granted.

The Court also addresses motions to dismiss Dick's third-party complaint. Because the third-party complaint is not proper under Federal Rule of Civil Procedure 14, it is dismissed. Dick seeks to amend its third-party complaint, as well. However, the proposed new filing does not remedy the Rule 14 defect and therefore the motion to amend is denied.

I. BACKGROUND

SWPC and Dick formed a Consortium for the purpose of constructing a power plant in Londonderry, New Hampshire on behalf of global power company AES Corporation ("AES"). Two AES subsidiaries, AES Londonderry, LLC, and Sycamore Ridge Co., LLC (collectively, the "Owners"), are signatories to the relevant contracts parties to this action. Because of delays in the project, SWPC has paid extensive liquidated damages to the Owners. SWPC filed a complaint seeking reimbursement of those payments from Dick, and from Dick's sureties. SWPC moved the Court for partial summary judgment, and the Court granted, in part, SWPC's motion. See Siemens Westinghouse Power Corp. v. Dick Corp., 293 F.Supp.2d 336, 2003 WL 22383284 (S.D.N.Y. Oct.14, 2003). The Court determined that, under the Consortium Agreement, Dick was responsible for paying liquidated damages to the Owners in the first instance and that the parties were to later determine, by applying certain formulas in the Consortium Agreement, SWPC's share of those damages. See id. at 340. Accordingly, the Court determined that, for now, Dick owed SWPC about $15 million. Id. at 343-44.

In opposing that summary judgment motion, Dick asserted that the Consortium Agreement was the product of negligent misrepresentation. The Court found that defense, as stated in the first amended answer and counterclaim, to lack the particularity required under Federal Rule of Civil Procedure 9(b). See id. at 343. While the summary judgment motion was in briefing, Dick filed a motion for leave to file a second amended answer and counterclaim. The proposed new filing contained, among other changes, more specific allegations of negligent misrepresentation and a related counterclaim for fraudulent concealment. Specifically, Dick alleges that SWPC, via misrepresentations and omissions, disguised the fact that a certain combustion turbine SWPC supplied to the project was still experimental and therefore not ready for commercial operation. Dick maintains that these counterclaims serve as valid defenses to SWPC's contract remedies at issue in the summary judgment motion.

The Court did not address the updated allegations because it had yet to determine whether Dick was entitled to leave to amend, and because SWPC's motion related to Dick's first amended answer and counterclaim. The Court stayed entry of its judgment for the purpose of determining whether Dick was entitled to leave to amend, and if so, whether those counterclaims would suffice as defenses to defeat SWPC's motion for partial summary judgment. See id. This Decision and Order addresses the issue of whether Dick is entitled to leave to amend.

Dick's second amended counterclaims for negligent misrepresentation and fraudulent concealment describe the following facts, which the Court will assume are true for purposes of this motion. At the inception of the power plant project in December 1999, Stone & Webster, Inc. ("Stone & Webster") agreed with the Owners to supply engineering, procurement, and construction services (the "EPC contract") to the project. SWPC agreed to provide around $164 million in equipment, including two combustion turbines. When Stone & Webster went bankrupt shortly thereafter, the remaining parties scrambled to find a new EPC contractor.

The Owners hoped to get SWPC to agree to be the EPC contractor, but SWPC refused. The Owners and SWPC then approached Dick in May 2000 with the prospect of joining the project. Dick "diligently attempted to investigate the Project ..., but the time period afforded to Dick to investigate the prior design and construction efforts on the Project, as well as its overall viability, was extremely short." Proposed Second Amended Counterclaim ¶ 25. The other project participants, including SWPC, knew that time was short and that Dick would rely on their representations in deciding whether to join the project. By September 2000, Dick and SWPC agreed to complete the project as a Consortium. The Consortium Agreement incorporated SWPC's previous commitment to supply the equipment.

Dick now asserts it never would joined the project if it had known the truth about its viability. Dick alleges that SWPC, among others, made several material misrepresentations and omissions in the period between May and September 2000, when Dick was deciding whether to participate.

The Consortium Agreement provided that SWPC would have a total of seventy-five (75) days — called "pool days" — to perform "corrective work" on certain equipment it supplied, before being responsible for any delay attributable to defects in the equipment. Dick therefore anticipated that SWPC would require around that many days in corrective work. It turns out that SWPC spent over two hundred (200) days doing corrective work, causing a massive delay in the project overall. Dick attributes the unanticipated delay to the fact that SWPC's combustion turbine was still experimental and, therefore, not commercially viable. Dick states that SWPC knew or should have known this fact, but never alerted Dick before Dick signed the Consortium Agreement.

Dick directs the Court's attention to a March 2000 bond offering prospectus for a company formed to build and operate a power plant in Pennsylvania, and for which SWPC supplied two of the exact model of combustion turbine at issue here. Under the heading "Summary of Risk Factors," that prospectus states: "The success of our project and future operations may be impaired because ... the combustion turbine to be used in our facility has no significant operating experience, and we may incur problems relating to start-up, commissioning and performance." Second Affidavit of Keith A. Moatz, dated Dec. 4, 2004, Ex. 14, at 19. The prospectus also states that the turbines in question were to become only the third and fourth ones of that make and model in operation. Id. at 20. SWPC's failure to inform Dick of the true nature of its combustion turbines is the essence Dick's counterclaims for negligent misrepresentation and fraudulent concealment.

SWPC opposes the motion for leave to amend only with respect to the proposed changes regarding negligent misrepresentation and fraudulent concealment, and only upon the ground that the changes would be futile. The issue here is therefore narrow: whether Dick's proposed second amended answer and counterclaim states claims for relief for either negligent misrepresentation or fraudulent concealment.

II. DISCUSSION
A. LEAVE TO AMEND

Although leave to amend "shall be freely given," Fed.R.Civ.P. 15(a), and the Court must generally have good reason to deny the motion, "[o]ne good reason to deny leave to amend is when such leave would be futile." Acito v. IMCERA Group, Inc., 47 F.3d 47, 55 (2d Cir.1995). "Determinations of futility are made under the same standards that govern Rule 12(b)(6) motions to dismiss." Nettis v. Levitt, 241 F.3d 186, 194 n. 4 (2d Cir.2001).

In reviewing a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6), the Court must accept as true the factual allegations of the non-moving party (here, counter-claimant and defendant Dick) and must draw all reasonable inferences in favor of that party. Bernheim v. Litt, 79 F.3d 318, 321 (2d Cir.1996). The Court may not grant the motion "unless it appears beyond doubt" that the counterclaimant "can prove no set of facts" which would entitle it to relief. Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957). Allegations of "fraud or mistake" will be dismissed unless they are stated "with particularity." Fed. R.Civ.P. 9(b). The particularity requirement of Rule 9(b) also applies to claims of negligent misrepresentation. Marcus v. Frome, 275 F.Supp.2d 496, 503 (S.D.N.Y. 2003).

SWPC puts forth several reasons why the proposed counterclaims would be futile, including that Dick has failed to meet the particularity requirements of Federal Rule of Civil Procedure 9(b), and failed to allege causes of action sufficiently distinct from its breach of contract...

To continue reading

Request your trial
12 cases
  • Im Partners v. Debit Direct Ltd.
    • United States
    • U.S. District Court — District of Connecticut
    • September 29, 2005
    ...357, 380 (S.D.N.Y.2005); Fagan v. AmerisourceBergen Corp., 356 F.Supp.2d 198, 218 (E.D.N.Y.2004); Siemens Westinghouse Power Corp. v. Dick Corp., 299 F.Supp.2d 242, 246 (S.D.N.Y.2004). District courts in Connecticut have also cited cases from the Southern District of New York for the propos......
  • Federal Insurance Company v. Tyco International
    • United States
    • U.S. District Court — Southern District of New York
    • March 21, 2006
    ...defendant." Steed Fin. LDC v. Laser Advisers, Inc., 258 F.Supp.2d 272, 281 (S.D.N.Y.2003); see also Siemens Westinghouse Power Corp. v. Dick Corp., 299 F.Supp.2d 242, 248 (S.D.N.Y.2004) ("`The crucial characteristic of a Rule 14 claim is that defendant is attempting to transfer to the third......
  • Zohar CDO 2003-1, Ltd. v. Patriarch Partners, LLC
    • United States
    • U.S. District Court — Southern District of New York
    • December 29, 2017
    ...original action or allege that the Third Party Defendants are secondarily liable to Defendants. See Siemens Westinghouse Power Corp. v. Dick Corp., 299 F.Supp.2d 242, 248 (S.D.N.Y. 2004) ("The crucial characteristic of a Rule 14 claim is that defendant is attempting to transfer to the third......
  • Jp Morgan Chase Bank v. Winnick
    • United States
    • U.S. District Court — Southern District of New York
    • June 23, 2004
    ...of copyrights to all of Warhol's known artwork was an impossibility." 119 F.3d 91, 99. See also Siemens Westinghouse Power Corp. v. Dick Corp., 299 F.Supp.2d 242, 247-48 (S.D.N.Y.2004) (reliance not justified in claim for misrepresentation over delays in installation of turbine where liquid......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT