Sierra Pacific Power Co. v. F.E.R.C.

Decision Date08 July 1986
Docket NumberNo. 84-7627,84-7627
Citation793 F.2d 1086
PartiesSIERRA PACIFIC POWER COMPANY, Petitioner, v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent, and Utah Power and Light Company, Intervenor.
CourtU.S. Court of Appeals — Ninth Circuit

Reuben Goldberg, Joshua L. Menter, Goldberg, Fieldman & Letham, P.C., Washington, D.C., for petitioner.

A. Karen Hill, Michael E. Small, F.E.R.C., Washington, D.C., for respondent.

C. Hayden Ames, Chickering & Gregory, San Francisco, Cal., for Utah Power & Light Co.

On Petition to Review from Final Orders of the Federal Energy Regulatory Commission.

Before POOLE, NELSON and BRUNETTI, Circuit Judges.

BRUNETTI, Circuit Judge:

Sierra Pacific Power Company ("Sierra") petitions for review of the Federal Energy Regulatory Commission's ("FERC") orders permitting the costs of Utah Power and Light Company's ("UP & L") lower voltage transmission system to be rolled-in with the costs of its higher voltage system. Sierra argues that FERC's findings are not supported by substantial evidence and that FERC erroneously failed to follow its own precedent. We affirm.

FACTS AND PROCEEDINGS BELOW

In January 1982, pursuant to section 205(d) of the Federal Power Act, 16 U.S.C. Sec. 824d(d) (1982), UP & L filed with FERC revised rate schedules that increased electricity rates to its interstate resale customers. In March 1982, FERC accepted the revised rate schedules for filing, ordered a hearing concerning the reasonableness of the revised rates pursuant to 16 U.S.C. Sec. 824d(e) (1982), and permitted several parties, including Sierra, one of UP & L's interstate resale customers, to intervene as objectors.

In June 1983, FERC accepted a settlement in the rate revision controversy with one exception. The unresolved issue concerned Sierra's (a higher voltage customer) disagreement with UP & L's use of the rolled-in allocation method. Sierra asserted, inter alia, that it should not have to pay for any of the forty-six and sixty-nine kilovolt transmission facilities because it receives no benefit from them.

The Administrative Law Judge's decision, issued in September 1983, held that res judicata barred relitigation of the issue because FERC had found rolled-in allocation appropriate in an earlier UP & L case. Nevertheless, the ALJ reached the merits of the case and concluded alternatively that rolled-in allocation was appropriate in the current proceeding. In May 1984, FERC rejected the ALJ's res judicata analysis but affirmed and adopted his decision to accept rolled-in allocation. In June 1984, pursuant to 16 U.S.C. Sec. 825l (a) (1982), Sierra applied to FERC for rehearing. FERC denied the application in July 1984, and Sierra timely petitioned for review of FERC's opinion and order denying rehearing pursuant to 16 U.S.C. Sec. 825l (b) (1982).

DISCUSSION
1. Rolled-in Transmission Costs

FERC's finding that rolling-in transmission costs is permissible is a question of fact. See Nevada Power Company v. Federal Power Comm'n, 589 F.2d 1002, 1007 (9th Cir.1979) (roll-in of transmission costs reviewed by court under the substantial evidence standard); cf. Anaheim v. Federal Energy Regulatory Comm'n, 669 F.2d 799, 810 (D.C.Cir.1981) (allocation of hardware costs to distribution or transmission function is a question of fact). The Federal Power Act provides that "[t]he finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive." 16 U.S.C. Sec. 825l (b). Accord, Nevada Power Company, 589 F.2d at 1006. Substantial evidence "means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion". Consolidated Edison Company v. National Labor Relations Board, 305 U.S. 197, 229, 59 S.Ct. 206, 216, 83 L.Ed. 126 (1938). Deference to FERC's decisions is suitable because of "the breadth and complexity of the Commission's responsibilities" under the Federal Power Act, Permian Basin Area Rate Cases, 390 U.S. 747, 790, 88 S.Ct. 1344, 1372, 20 L.Ed.2d 312 (1968) (quoted in Nevada Power Company, 589 F.2d at 1005), and because this rate case raises "numerous intricate and detailed contentions within the special competence of the Commission." Nevada Power Company, 589 F.2d at 1006. Moreover, it is the Commission's function to reach conclusions on conflicting engineering and economic issues so long as its judgment is reasonable and based on evidence. City of Cleveland, Ohio v. Federal Power Commission, 525 F.2d 845, 849 n. 36 (D.C.Cir.1976).

When a utility uses the rolled-in allocation method for transmission costs, all customers share proportionately in the ownership, operation, and maintenance costs of all transmission facilities. If costs are not rolled-in, each customer class pays only for the transmission system that serves it. FERC favors rolled-in cost allocation when a system is integrated. Fort Pierce Utilities Authority v. Federal Energy Regulatory Commission, 730 F.2d 778, 782 n. 11 (D.C.Cir.1984) (citing Otter Tail Power Company, 12 FERC p 61,169, at 61,420 (1980)). Intervenor UP & L supplies the best definition of integration in this record:

Lower voltage transmission facilities are "integrated," ... when, in addition to being connected with higher voltage facilities, the lower voltage facilities are themselves interconnected and designed to operate in parallel. This is also referred to as "looping," that is, the lower voltage transmission facilities form parallel paths for electric energy with the higher voltage transmission facilities. The existence of two or more parallel transmission paths from sources of power to receiving points establishes integration. This is true even where one of the parallel paths is normally operated "opened," that is, with the connection broken by opening a switch.

Intervenor's Br. at 10. "[W]hen ... a higher voltage line goes out of service, power is automatically rerouted throughout the parallel 46 kilovolt system because of this "looping" or integration in accordance with the laws of physics." Id. at 11. The record confirms this definition.

In a previous UP & L rate case to which Sierra was a party, FERC held that UP & L's transmission costs should be rolled-in because UP & L's transmission system is integrated. Utah Power & Light Company, 11 FERC p 63,017, pp. 65,078-79 (1980), aff'd, 14 FERC p 61,162, p. 61,296, reh'g denied, 15 FERC p 61,076, pp. 61,183-84 (1981). Because Sierra proposed a change from FERC's earlier conclusion that UP & L's transmission system costs should be rolled-in, Sierra was required to show by a preponderance of the evidence, see Steadman v. Securities & Exchange Commission, 450 U.S. 91, 101-02, 101 S.Ct. 999, 1007, 67 L.Ed.2d 69 (1981) (construing 5 U.S.C. Sec. 556(d)), either that (1) the transmission system is not integrated, or (2) even though the system is integrated, the particular transmission lines at issue do not provide system-wide benefit. By such a showing, Sierra could overcome the presumption in favor of rolled-in allocation of transmission costs. See New York State Electric & Gas Corp., 25 FERC p 63,031, p. 65,070 (1983).

FERC, in affirming and adopting the ALJ's initial decision on the merits, noted that precedent strongly favors rolled-in allocation of transmission costs for integrated systems. The Commission found that Sierra had not met its burden of proving exceptional circumstances which would warrant departure from this policy. Specifically, FERC found (1) record evidence sufficiently demonstrated that UP & L's transmission system was integrated, and (2) Sierra did not show that the higher voltage transmission facilities received no benefit from the lower voltage facilities. Careful review of the record confirms the soundness of FERC's orders. See, e.g., Central Lincoln Peoples' Utility District v. Johnson, 735 F.2d 1101, 1129 (9th Cir.1984) (rolled-in allocation...

To continue reading

Request your trial
6 cases
  • Alabama Power Co. v. F.E.R.C.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • September 21, 1993
    ...facilities, the lower voltage facilities are themselves interconnected and designed to operate in parallel.' " Sierra Pacific Power Co. v. FERC, 793 F.2d 1086, 1088 (9th Cir.1986) (quoting Intervenor's Brief at 10). Thus, the Commission's argument on this narrow point does not carry the day......
  • Allegheny Power v. Federal Energy Regulatory Com'n
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • February 7, 2006
    ...v. FERC, 165 F.3d 922, 927-28 (D.C.Cir.1999); Maine Public Service Co. v. FERC, 964 F.2d 5, 8 (D.C.Cir.1992); Sierra Pacific Power Co. v. FERC, 793 F.2d 1086, 1088 (9th Cir. 1986); Otter Tail Power Co., 12 FERC ¶ 61,169, at 61,420 (1980). To some extent, of course, the cost of information m......
  • United States v. Turchi
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • September 17, 1986
  • California Dept. of Water Resources v. F.E.R.C.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • June 7, 2007
    ...share proportionately in the ownership, operation, and maintenance costs of all transmission facilities." Sierra Pac. Power Co. v. FERC, 793 F.2d 1086, 1088 (9th Cir. 1986). Rolled-in pricing of transmission facilities is the method traditionally used in the industry. See Pac. Gas & Elec. C......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT