Sime Const. Co., Inc. v. Washington Public Power Supply System

CourtWashington Court of Appeals
Writing for the CourtGREEN
CitationSime Const. Co., Inc. v. Washington Public Power Supply System, 621 P.2d 1299, 28 Wn.App. 10 (Wash. App. 1980)
Decision Date18 December 1980
Docket NumberNo. 3357-III-1
PartiesSIME CONSTRUCTION CO., INC., a Washington Corporation, Appellant, v. WASHINGTON PUBLIC POWER SUPPLY SYSTEM; Ragnar Benson, Inc.; Burns & Roe, Inc.; The Marley Company; and Commercial Union Insurance Company, Respondents.

Dale R. Ulin, Taylor & Ulin, Seattle, for appellant.

Frederic C. Tausend, Schweppe, Doolittle, Krug, Tausend, Beezer & Beierle, Seattle, for Marley & Comm. Ins.

G. E. Doupe, Richland, for Wash. Public Power.

Rembert Ryals, Critchlow & Williams, Richland, for Burns & Roe, Inc. GREEN, Chief Judge.

This action was brought by Sime Construction Co., Inc., (Sime), a second-tier subcontractor, against the Washington Public Power Supply System (WPPSS), the owner; Marley Co. (Marley), the prime contractor; Commercial Union Insurance Co. (Commercial), the bonding company; and Ragnar Benson, Inc., the subcontractor with whom Sime contracted. Sime sought damages for delay in the submission of changes in architectural drawings and for defective concrete supplied to it. Cross claims were filed between the parties and Burns & Roe, the architect, was added as a cross-defendant. Sime recovered damages for the defective concrete, but appeals from the denial of its drawings claim. WPPSS cross-appeals from a judgment in favor of Marley; Marley and Commercial cross-appeal the dismissal of their cross claim against Burns & Roe and from portions of the judgment entered against them. We affirm.

Two basic issues are presented: (1) Did Sime's failure to submit a notice of claim in accordance with the terms of the prime contract bar recovery of its drawings claim? (2) Was Sime entitled to recover attorney fees and prejudgment interest on the concrete claim?

The unchallenged findings of fact 1 establish that WPPSS entered into a construction contract with Marley to build six nuclear reactor cooling towers at Hanford Project No. 2 at a cost of $7,226,600. Marley awarded a subcontract for earth work, foundations and erection of the super structure to Ragnar Benson, Inc. Ragnar in turn entered into a sub-subcontract with Sime for the excavation and construction of the concrete foundations of the towers for the sum of $350,000. During negotiations, Ragnar approved a proposed construction schedule. It provided that the foundations were to be built sequentially in a clock-wise manner, and the hot water inlets and cold water outlets were to be built in the early stages of construction. This schedule was approved and essentially followed by Sime in the performance of the Ragnar-Sime contract.

In June 1978, when Sime commenced work, certain critical drawings relating to the cold water outlets were not available. Burns & Roe had withheld the drawings because it was initiating a change in a construction joint to improve the design of the outlet structure. Sime, Ragnar and Marley all knew the drawings were delayed. Due to the late delivery of the revised drawings, Sime was unable to begin the outlets until August. Even though the eventual design changes were minor, the sequence of work was seriously disrupted.

After it had completed its work, Sime submitted a claim for damages arising from the late delivery of the revised drawings. The claim was rejected on the ground that Sime had failed to submit a timely notice of claim as required by the prime contract. This action was then filed by Sime. After a 6-week trial to the court, Sime was awarded damages, attorney's fees, and prejudgment interest on the concrete claim but was denied recovery on the drawing claim.

First, was the drawings claim barred by Simm's failure to give a 15-day notice in accordance with the terms of the prime contract between WPPSS and Marley? It is clear that article 2, section C of the Ragnar-Sime sub-subcontract entitles Sime to damages for delay. 2 Marley and Commercial assert the trial court was correct when it held that Sime's failure to give the 15-day notice bars recovery on the drawings claim. On the other hand, Sime contends the court erred because (1) the notice procedures of the prime contract are not incorporated by reference into the sub-subcontract for purposes of the drawings claim; (2) application of the notice procedures contained in the "Change Order" clause of the prime contract created a procedural ambiguity which should have been construed against the drafters, Marley, Ragnar and WPPSS; and (3) the court's interpretation made an agreement which the parties had not made for themselves. We disagree with Sime's contentions.

The sub-subcontract incorporates by reference, without qualification, the terms of the prime contract. McDaniel v. Ashton-Mardian Co., 357 F.2d 511 (9th Cir. 1966); Turner v. Wexler, 14 Wash.App. 143, 538 P.2d 877 (1975). Article 1, section A of the Ragnar/Sime sub-subcontract provides:

A. Subcontract documents include all the below listed items, all of which are incorporated herein and made part hereof by reference thereto.

1. The Contract between the Owner and the Contractor dated and the conditions thereof (general, supplementary and other conditions).

While the date of the prime contract was omitted, WPPSS and Marley are referred to immediately preceding the incorporation clause. 3

Section 3.0 of the WPPSS-Marley prime contract sets forth the procedures for changes in the work. The term "Change Order Work" is broadly defined in section 3.1 as "work not included in the original contract." Section 3.5 provides:

If at any time the Contractor receives any drawings, specification, instruction or request from the Owner or from the Engineer of the Owner with respect to which the Owner does not request a proposal for the doing of the Work and the payment of compensation, but which in the Contractor's opinion entails the performance of Change Order Work for which compensation has not been included in the compensation for the original contract work in the contract price(,) the Contractor shall within fifteen days after such receipt notify the Owner that he considers the item to require the payment of compensation for work in addition to that provided for in the original contract and he shall submit a proposal according to the method outlined above for the doing of the work and the payment of compensation for it ... Failure of the Contractor to give the notice required within fifteen days shall constitute a release and waiver of any claim against the Owner and unless so claimed, no additional compensation shall be considered or paid.

Sime admittedly failed to comply with the notice procedures.

However, Sime argues the notice procedures of the prime contract are not incorporated by reference into the sub-subcontract for purposes of the drawings claim. It relies upon the rule that where one contract is incorporated by reference into another for a special purpose, the incorporation is limited to that purpose. Guerini Stone Co. v. P. J. Carlin Construction Co., 240 U.S. 264, 36 S.Ct. 300, 60 L.Ed. 636 (1915); John W. Johnson, Inc. v. Basic Construction Co., 429 F.2d 764 (D.C. Cir. 1970); United States ex rel. B's Co. v. Cleveland Electric Co., 373 F.2d 585 (4th Cir. 1967). It contends the purpose for the incorporation is to define the scope of the work of subcontractors and to make it clear that the subcontractor must perform its work pursuant to "applicable" specifications. Therefore, Sime asserts the administrative and procedural provisions of the prime contract are not applicable. The cases upon which Sime relies are not controlling. There, the incorporation was for a special purpose. Here, the incorporation clause is general and unlimited. In that situation, both the contract specifications and procedural provisions of the prime contract are incorporated by reference. McDaniel v. Ashton-Mardian Co., supra.

Sime further argues that the "Change Order" clause of the prime contract created a procedural ambiguity which should have been resolved against the drafters, Marley, WPPSS and Ragnar. We disagree. "Change Order Work" is broadly defined as "work not included in the original contract work." Sime submitted a work schedule to Ragnar which was accepted and became a specification of the sub-subcontract. That schedule was disrupted by the late delivery of the revised drawings. As a result, Sime was forced to perform work out of sequence and not included in the contract. The court found Sime, Ragnar and Marley all knew the drawings were delayed because Burns & Roe were initiating an improvement of the design for the outlet structure. The...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
26 cases
  • Mike M. Johnson, Inc. v. County of Spokane
    • United States
    • Washington Supreme Court
    • October 23, 2003
    ... ... The COUNTY OF SPOKANE, a Washington State Municipal Corporation, Petitioner, ... US ... , amicus curiae on behalf of State School Const ...         MADSEN, J ... widen the road and revise the storm drain system. MMJ began construction on the Apple Valley ... Absher Constr. Co. v. Kent Sch. Dist. No. 415, 77 Wash.App. 137, ... owner could not be liable for extra costs); Sime Constr. Co. v. Wash. Pub. Power Supply Sys., 28 ... public works projects in a competitive bidding process ... ...
  • Story v. Shelter Bay Co.
    • United States
    • Washington Court of Appeals
    • September 6, 1988
    ... ... of all Members of Shelter Bay Community, Inc., ... similarly situated, Plaintiffs, ... ER BAY COMPANY, a Washington corporation, Respondent ... Osberg Construction ... proceedings which, although official and public, are not judicial in substance, as a nonjudicial ... "situations in which authorities have the power to discipline as well as strike from the record ... Sime Constr. Co. v. Washington Pub. Power Supply ... ...
  • Wash. State Major League Baseball Stadium Pub. Facilities Dist. v. Huber, Hunt & Nichols–Kiewit Constr. Co.
    • United States
    • Washington Supreme Court
    • January 31, 2013
    ... 176 Wash.2d 502 296 P.3d 821 WASHINGTON STATE MAJOR LEAGUE BASEBALL STADIUM PUBLIC ... joint venture; Hunt Construction Group, Inc., a foreign corporation; and Kiewit Construction ... contract documents is more akin to that in Sime Construction Co. v. Washington Public Power y System, 28 Wash.App. 10, 621 P.2d 1299 (1980). There, a ... ...
  • State v. Ramirez
    • United States
    • Washington Court of Appeals
    • August 5, 1991
    ... ... 301 ... 814 P.2d 227 ... STATE of Washington, Respondent, ... Sabino M. RAMIREZ, Andre G ... ), review denied, 105 Wash.2d 1014 (1986); Sime Constr. Co. v. WPPSS, [814 P.2d 230] 28 ... 1 Moore v. Mayfair Tavern, Inc., 75 Wash.2d 401, 409, 451 P.2d 669 (1969) (jury ... ...
  • Get Started for Free
4 books & journal articles
  • Table of Cases
    • United States
    • Washington State Bar Association Washington Construction Law Deskbook (WSBA) Table of Cases
    • Invalid date
    ...Inc. v. Dep't of Labor & Indus., 159 Wn.2d 868, 154 P.3d 891 (2007): 7.4(2) Sime Constr. Co. v. Wash. Pub. Power Supply Sys., 28 Wn.App. 10, 621 P.2d 1299 (1980), review denied, 95 Wn.2d 1012 (1981): 4.5(2), 15.4(12), 19.3(1) S.L. Rowland Constr. Co. v. Beall Pipe & Tank Corp., 14 Wn.App. 2......
  • §4.5 Defenses and Contractual Considerations
    • United States
    • Washington State Bar Association Washington Construction Law Deskbook (WSBA) Chapter 4
    • Invalid date
    ...See Gibson v. Seattle Crescent Container Servs., 28 Wn.App. 508, 624 P.2d 1168 (1981); Sime Constr. Co. v. Wash. Pub. Power Supply Sys.,28 Wn. App. 10, 621 P.2d 1299 (1980). The parties to the contract may bind themselves and their successors to certain limitations, but claims by third part......
  • §19.3 Key Subcontract Provisions
    • United States
    • Washington State Bar Association Washington Construction Law Deskbook (WSBA) Chapter 19
    • Invalid date
    ...the subcontract clauses that flow down or are incorporated by reference. Sime Construction Co. v. Washington Public Power Supply System, 28 Wn.App. 10, 621 P.2d 1299 (1980), review denied, 95 Wn.2d 1012 (1981), illustrates some of the problems presented by a conduit clause. In Sime, a prime......
  • §15.4 Contractor's Damages Components
    • United States
    • Washington State Bar Association Washington Construction Law Deskbook (WSBA) Chapter 15
    • Invalid date
    ...to compute the amount with exactness, without reliance on opinion or discretion." Sime Constr. Co. v. Wash. Pub. Power Supply Sys., 28 Wn. App. 10, 18, 621 P.2d 1299 Additionally, interest is recoverable only if there is no speculation as to its recoverability or amount. Vermette v. Anderse......