Smith v. Freeport Kaolin Co.
| Court | U.S. District Court — Middle District of Georgia |
| Writing for the Court | George C. Grant, Macon, Ga., for defendants |
| Citation | Smith v. Freeport Kaolin Co., 687 F.Supp. 1550 (M.D. Ga. 1988) |
| Decision Date | 27 May 1988 |
| Docket Number | Civ. A. No. 84-241-1-MAC (WDO). |
| Parties | Mrs. Helen Stinson SMITH, As Trustee Under the Will of George F. Stinson by Order of Wilkinson County Superior Court of September 18, 1978, Plaintiff, v. FREEPORT KAOLIN COMPANY, et al., Defendants. |
Manley F. Brown, Macon, Ga., William H. Stanhope, Atlanta, Ga., Charles R. Adams, III, Ft. Valley, Ga., for plaintiff.
George C. Grant, Macon, Ga., for defendants.
This matter is before the court on the parties' cross motions for partial summary judgment. The focus of this dispute is a mining lease originally executed in September of 1945 between landowner Mr. I.B. Stinson, predecessor in interest of plaintiff Helen Stinson Smith, and Owen and Shepherd, an entity composed of two individuals, Mr. S.R. Owen and Mr. C.M. Shepherd. Defendant Freeport Kaolin Company, and subsequently defendant Engelhard Corporation, eventually acquired the mining rights described in the lease, and both corporations have conducted mining operations on the property described therein. This instant disagreement centers on a provision in the lease establishing the amount of royalties due the lessor, now Mrs. Smith. The parties agree that, at least initially, the interpretation of the lease is a question of law properly ruled upon by this court. To further such interpretation, the parties have submitted well-prepared pleadings. Having read and considered those materials, this court now makes the following findings of fact and conclusions of law.
1. In a lease recorded in Book 77, Page 133, in the Office of the Clerk of the Superior Court of Wilkinson County, Georgia, I.B. Stinson conveyed certain mining rights to Owen and Shepherd.1 The disputed provision of this lease states as follows:
The party of the second part Owen and Shepherd agrees to pay to the party of the first part I.B. Stinson, his heirs and assigns, the sum of .15 cents for each and every ton of said bauxite, clay or other ore moved from said lands said ton to weight (sic) 2240 pounds, said weight shall be ascertained from the records of the railroad companies shipping said material. ...
Judgment, Docket No. 82; see also Exhibits A and B to Exhibit 1 attached to Brief in Support of Defendant Freeport Kaolin Company's Motion for Partial Summary Judgment, Docket No. 84.2
2. Owen and Shepherd executed a number of leases containing language identical to the provision in the Stinson lease. See Exhibit E attached to Plaintiff Smith's Reply Brief in Support of Motion for Partial Summary Judgment, Docket No. 90.
3. Owen and Shepherd executed a sublease on or about September 29, 1945, conveying the kaolin mining rights on the Stinson property to P.W. Martin Gordon Clays. See Exhibit C to Exhibit 1 attached to Defendant Freeport Kaolin Company's Motion for Partial Summary Judgment. This contract, which had a term of twenty-five years with an option provision for an additional five years, provided that the subtenant pay "the sum of twenty cents (20c) for each ton of 2240 pounds of refined clay and bauxite (railroad weight) removed from said land by subtenant." No mining occurred pursuant to the sublease, and it expired by its own terms no later than September of 1975.
4. George F. Stinson and Anita M. Stinson inured to the interests of the original landowner and lessor, Mr. I.B. Stinson. Plaintiff Helen Stinson Smith has succeeded George and Anita Stinson and is the holder of record title to the property at issue in this case.
5. Defendant Freeport Kaolin Company succeeded to the mining rights originally belonging to Owen and Shepherd and conducted mining operations on the Stinson property beginning in 1977 and continuing until 1985. In 1985, defendants Freeport and Engelhard entered into an agreement by which Freeport assigned to Engelhard its interest in the Stinson property. Defendant Engelhard conducted mining operations in the property until 1986.3
6. From the inception of mining in 1977 until and through January of 1982, Freeport made monthly royalty payments to George F. Stinson and his successors, Mrs. Anita M. Stinson and Mrs. Helen Stinson Smith.4 Included with the monthly payments transmitted to the various payees were explanatory letters indicating that the payments were based upon the total number of "long tons (2240 pounds per ton) of refined clay removed." Exhibits G1-G53 to Exhibit 1 attached to Motion of Defendant Freeport Kaolin Company for Partial Summary Judgment, Docket No. 83. These checks have been cashed, and they amount to $45,244.92.
Following the installation of new equipment which accurately measured the amount of dry crude kaolin pumped by pipelines from the Stinson property, Freeport in a letter to plaintiff offered to pay royalties on the basis of crude or unrefined kaolin transported through the pipeline, and, in fact, Freeport tendered subsequent payments to plaintiff based thereupon. Id. at G-63 and at Exhibit H. This offer to pay royalties based upon crude tonnage alerted plaintiff to the fact that she and her predecessors had been receiving royalty payments based upon refined tonnage, and it caused plaintiff to question the propriety of such payments. The dispute which ensued resulted in this lawsuit, and the royalty payments by both Freeport and Engelhard since December of 1982 have not been cashed but have been paid into the court. Id. at Exhibit 1, p. 13 7. Id. at Exhibit 1, p. 12, and at Exhibit 2, p. 3. "The railroad weight of refined kaolin which is shipped to the customer can be converted to wet crude tons of clay by mathematical calculation...." Exhibit C, p. 5, attached to Plaintiff Smith's Reply Brief in Support of Motion for Partial Summary Judgment, Docket No. 90.
1. "The construction of the provisions of this lease, as with other contracts, is generally one for the court to determine as a matter of law." Peachtree on Peachtree Investors v. Reed Drugs, 251 Ga. 692, 694, 308 S.E.2d 825, 828 (1983), citing O.C.G.A. § 13-2-1.5 As such, the interpretation of this written contract regarding the mining of certain materials from the Stinson property is "properly subject to disposition by summary judgment." Sims' Crane Service, Inc. v. Reliance Insurance Company, 514 F.Supp. 1033, 1036 (S.D.Ga.1981), aff'd 667 F.2d 30 (11th Cir.1982).
2. "Under Georgia law whether a contract is ambiguous is to be determined by the court." Kaiser Aluminum & Chemical v. Ingersoll-Rand Co., 519 F.Supp. 60, 71 (S.D.Ga.1981), citing Stone Mountain Scenic Railroad, Inc. v. Stone Mountain Memorial Association, 230 Ga. 800, 199 S.E.2d 216 (1973); see Georgia R.R. Bank & Trust v. Fed. Deposit Ins., 758 F.2d 1548, 1551 (11th Cir.1985)("the existence vel non of an ambiguity is a question of law for the court"). "Ambiguity in a contract may be defined as duplicity, indistinctness, an uncertainty of meaning or expression." Salvatori Corp. v. Rubin, 159 Ga. App. 369, 372, 283 S.E.2d 326, 328 (1981) (citations omitted).
3. However, no construction is "required or even permissible when the language employed by the parties in the contract is plain, unambiguous, and capable of only one reasonable interpretation." Merrill Lynch, Pierce, Fenner & Smith v. Stidham, 506 F.Supp. 1182, 1186 (M.D.Ga. 1981) (citations omitted), modified for other reasons, 658 F.2d 1098 (5th Cir. Unit B. 1981).6 Consequently, "where the contract language is definite and unambiguous, the Court will not resort to surrounding circumstances to interpret the agreement." Kaiser Alumimum & Chemical, 519 F.Supp. at 71 (citations omitted).
4. If the court determines that an ambiguity exists, "it becomes the duty of the court to attempt to resolve the ambiguity by applying the rules of construction set forth in O.C.G.A. § 13-2-2." Capital Ford Truck v. U.S. Fire Ins. Co., 180 Ga. App. 413, 418, 349 S.E.2d 201, 206 (1986).
5. "The cardinal rule of construction is to ascertain the intention of the parties." O.C.G.A. § 13-2-3, quoted in Georgia R.R. Bank & Trust, 758 F.2d at 1551.
The courts are to afford greater regard to the clear intent of the parties than to any particular words which they may have used in expressing their intent. However unskillfully prepared a particular instrument or agreement may be, the courts are to discover and give effect to the intent of the parties if possible. Similarly, words in a contract are to be construed in the sense in which they are mutually employed by contracting parties, irrespective of the proper and logical meaning those words might otherwise carry.
Georgia R.R. Bank & Trust, 758 F.2d at 1551 (citations omitted). This "cardinal rule of construction" becomes applicable, however, only upon a determination that the contract is ambiguous. Id. at 1552. "Where parties have reduced to writing what appears to be a complete and certain agreement, it will, in the absence of fraud, accident or mistake, be conclusively presumed that the writing contains the entire contract...." Andrews v. Skinner, 158 Ga.App. 229, 231, 279 S.E.2d 523, 526 (1981). But see, In Re Smith, 436 F.Supp. 469, 475 (N.D.Ga.1977) ().
6. If an ambiguity remains after application of the appropriate rules of construction, a jury question is presented. Travelers Ins. Co. v. Blakey, 255 Ga. 699, 342 S.E.2d 308 (1986).
7. A contract may be unenforceable due to the uncertainty, vagueness or indefiniteness of its terms. An agreement with such a defect may be cured by the parties' subsequent conduct. The general rule in Georgia is as follows:
A contract...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
- Mira v. Monroe County School Bd.
-
Assoc. Mechanical Contract. v. Martin K. Eby Const.
...has the duty of resolving the ambiguity by applying the rules of construction set forth in O.C.G.A. § 13-2-2. See Smith v. Freeport Kaolin Co., 687 F.Supp. 1550 (M.D.Ga.1988). A writing which to relinquish rights is subject to the same rules of construction as govern ordinary contracts. Tho......
-
Butts v. Southern Clays, Inc.
...of "Ten Cents ... per ton of twenty-two hundred and forty (2240) pounds refined clay, railroad weights." In Smith v. Freeport Kaolin Co., 687 F.Supp. 1550, 1553 (M.D.Ga.1988), the court recognized that 1.5 tons of dry crude kaolin is required to produce one ton of refined However, plaintiff......