Smith v. McCain Boiler & Engineering Co.

Decision Date25 September 1969
Docket Number6 Div. 452
Citation284 Ala. 618,227 So.2d 131
PartiesKearney SMITH v. McCAIN BOILER AND ENGINEERING CO., Inc., et al.
CourtAlabama Supreme Court

Cato & Hicks, Birmingham, for appellant.

Locke & Locke, Birmingham, for appellees.

LIVINGSTON, Chief Justice.

This suit was filed by Kearney Smith, the appellant, in the Circuit Court of the Tenth Judicial Circuit of Alabama, in Equity, against McCain Boiler and Engineering Company, Inc., a Corporation, Wayne McCain and J. H. McCain, seeking a mechanic's lien on the property described in the bill of complaint.

The respondents' (appellees) demurrer to the bill of complaint was overruled. The appellees answered and filed a cross bill. By their answer, the appellees substantially denied the allegations of the bill of complaint. They also filed a cross bill seeking to specifically perform the contract entered into by Kearney Smith, or, in the alternative, damages in the amount of $9,000.00.

The trial was had in the court below before Honorable Robert Giles on testimony taken ore tenus before the trial court. The trial court entered, in pertinent part, the following decree:

'FINAL DECREE

'THIS CAUSE heretofore duly came on to be heard, argued and submitted upon pleadings and proof as noted for final decree, and upon consideration of the same the Court is of the opinion that the following decree ought to be and is hereby rendered thereon.

'The Court has found resolution of this controversy to be difficult. The testimony is highty detailed, complex, ambiguous and gravely conflicting. The ends of justice would seem to require, in order to avoid running the risk of doing a substantial injustice to either party, that they be left in the situation in which they had placed themselves prior to the filing of the bill, which is to say that affirmative relief both under the bill as amended, and under the cross-bill as amended should be denied, with the exception of a small and severable item of $330.00 for gas air conditioning installed for the respondents by complainant as an extra, which is entirely severable from performance of the main contract.

'It is therefore accordingly ORDERED, ADJUDGED AND DECREED by the Court as follows:

'1. That complainant Kearney Smith have and recover of the respondent, McCain Boiler and Engineering Company, Inc., a corporation, the sum of $330.00 for which let execution issue.

'2. Except as provided in the next preceding paragraph, the complainant Kearney Smith is not entitled to relief, and same hereby is denied.

'3. That respondents and cross-complainants, J. H. McCain, Wayne McCain; Mrs. J. H. McCain, and McCain Boiler and Engineering Company, Inc., a corporation, are not entitled to any relief as against the complainant and cross-respondent Kearney Smith, and that such relief be and it hereby is denied.

'4. That the costs of this cause be and the same hereby are taxed one-half (1/2) against complainant and one-half (1/2) against resondents, for which let executions issue.

'DONE AND ORDERED this the 17th day of February, 1967.

'Robert C. Giles

Circuit Judge in Equity Sitting.'

The cause was argued before this Court and submitted on motions and merits. The motion referred to was made by appellees and had for its purpose the dismissal of the appeal on grounds stated therein. We have reached the conclusion that the decree of the lower court must be affirmed and for this reason pretermit a consideration of said motions.

We make no effort to set out the evidence contained in this transcript of over 500 pages. Suffice it to say, in the language of Judge Giles 'The testimony is highly detailed, complex, ambiguous and gravely conflicting.'

The main question before us is whether or not the evidence supports the finding of the trial court. At the outset, therefore, we must point out that the trial court, sitting without a jury in this case, heard the evidence ore tenus, and it is axiomatic in such cases that a presumption of correctness must be indulged unless to do so would result in a gross miscarriage of justice. Consequently, unless the trial court's decision is shown to be palpably wrong and unjust and contrary to the great weight of the evidence, its decision should be affirmed. Lovelace v. McMillian, 265 Ala. 290, 90 So.2d 822; Butts v. Lancaster, 279 Ala. 589, 188 So.2d 548; Talbot v. Braswell, 266 Ala. 578, 98 So.2d 7; Deese v. Odom, 283 Ala. 420, 218 So.2d 134.

It is also axiomatic that assignments of error not argued in brief are waived. There are 13 assignments of error but only the first 8 assignments are argued in brief, therefore, assignments of error 9, 10, 11, 12 and 13 are waived and will not be considered. The first 8 assignments of error are:

'1. For that the final decree is contrary to the law in the case.

'2. For that the final decree is contrary to the evidence in the case.

'3. For that the final decree is contrary to the law and the evidence in the case.

'4. For that the final decree is not supported by the evidence in the case.

'5. For that the Court erred to reverse in denying the Complainant the relief prayed for in the bill of Complaint as amended.

'6. For that the Court erred to reverse in not entering a Decree fixing a lien upon the property described in the Bill of Complaint.

'7. For that the...

To continue reading

Request your trial
4 cases
  • City Stores Co. v. Williams
    • United States
    • Alabama Supreme Court
    • June 10, 1971
    ...established, nor where the trial court has taken an erroneous view of the law as applied to such facts. Smith v. McCain Boiler & Enginerring Co., 284 Ala. 618, 227 So.2d 131. Because of the reasons set forth above, we hold that the defendants' evidence supported their pleas in abatement, an......
  • Ford v. Washington
    • United States
    • Alabama Supreme Court
    • March 9, 1972
    ...for our review. National Life and Accident Insurance Co. v. Allen, 285 Ala. 551, 234 So.2d 567 (1970); Smith v. McCain Boiler and Engineering Co., 284 Ala. 618, 227 So.2d 131 (1969). In assignment of error No. 8, it is contended that the trial judge erred in holding that all doubts and disp......
  • Valley Heating, Cooling & Elec. Co. v. Alabama Gas Corp., 6 Div. 754
    • United States
    • Alabama Supreme Court
    • June 18, 1970
    ...to the admitted facts in the case.' These assignments of error are the same as assignments 1, 2 and 3 in Smith v. McCain Boiler and Engineering Co., Inc., 284 Ala. 618, 227 So.2d 131, except that assignment 2 there used the term 'contrary to the evidence in the case' and here it was 'contra......
  • Ewing v. Certain Lands
    • United States
    • Alabama Supreme Court
    • November 21, 1974
    ...Advancement of Colored People v. State of Alabama, 274 Ala. 544, 150 So.2d 677, and cases there cited.' Smith v. McCain Boiler & Engineering Co., 284 Ala. 618, 227 So.2d 131 (1969). '(2) An assignment of error is an instrument of appellate pleading, Board of Education of Colbert County v. M......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT