Smith & Wesson, In re, 84-1992

Citation757 F.2d 431
Decision Date09 January 1985
Docket NumberNo. 84-1992,84-1992
Parties, 32 Cont.Cas.Fed. (CCH) 73,291 In re SMITH & WESSON, etc., Petitioner. . Heard
CourtU.S. Court of Appeals — First Circuit

Charles E. Raley, Israel & Raley, Washington, D.C., Martin O'Donnel, Steven J. Henry, Cesari & McKenna, Boston, Mass., for petitioner.

C. Brian McDonald, Asst. U.S. Atty., and William F. Weld, U.S. Atty., Boston, Mass., for respondent.

Before COFFIN, BOWNES and TORRUELLA, Circuit Judges.

TORRUELLA, Circuit Judge.

In essence, this case presents two principal issues to be decided on appeal: (1) Whether the district courts have jurisdiction of pre-contract claims against an agency of the United States after the enactment of the Federal Court Improvements Act of 1982 (FCIA), 1 and (2) in the event such jurisdiction exists, whether mandamus is an appropriate remedy to review the refusal of a district court to assume jurisdiction over such a controversy.

The facts, which for purposes of this appeal we will assume to be true, are as follows:

On November 9, 1983 the Army issued a Request for Test Samples (RFTS), seeking the submission of weapon samples and supporting materials in a "test package" on or before January 31, 1984. The request stated that samples would be tested and evaluated to determine their conformance to certain personal defense weapon "characteristics" described more fully in attachments issued with the request itself. This evaluation was motivated by the anticipated authorization for the letting of contracts to supply approximately 300,000 handguns to the Army over a 5-year period. 2 The request stated that a failure to meet the requirements of the stated "characteristics" would result in exclusion from participation in any follow-on procurement.

Plaintiff submitted its test package within the time limit. It included thirty sample pistols and two firing pin adapters.

The Army conducted a conference for interested parties at which the procedures for preliminary testing were set forth. On May 8, 1984 additional documentation was issued by the Army to Smith & Wesson. Petitioner alleges that the documentation at this date indicated that its weapons were still under consideration.

On September 18, 1984, the Army issued a letter indicating that the tests were nearing completion but that Smith & Wesson would be excluded from further participation in the testing on the ground that the handguns had failed the tests for firing pin energy and service life.

The petitioner, contending that the Army's action in excluding it from further consideration for procurement contracts to be issued was in violation of procedures, duties and obligations with which the Army was required to comply, proceeded to file a civil suit in the United States District Court for the District of Massachusetts contesting the Army's conduct. 3 Thereafter, the district court transferred the action to the United States Claims Court on the grounds that the jurisdiction of the district court had been divested by virtue of 28 U.S.C. Sec. 1491(a)(3), and this appeal ensued. The merits of the dispute which Smith & Wesson seeks to litigate before the district court are not before us, but rather, as previously indicated, the appellate controversy is limited to determining the scope of the district court's jurisdiction and whether mandamus lies to enforce the same.

I. The nature of the controversy

In an effort to completely avoid the issue of jurisdiction under Sec. 1491(a)(3), Smith & Wesson rejects the characterization of its suit as a "pre-award contract claim." Petitioner instead alleges that its challenge is one based on the Army's arbitrary action in barring petitioner from competition for future procurement of pistols. It is obvious that Smith & Wesson seeks to so label this controversy, because it is well-settled that there is standing to seek judicial review of agency action in the district courts under Section 10 of the Administrative Procedure Act [5 U.S.C. Sec. 706(2)(A) ], when arbitrary or capricious agency conduct is claimed. See Chrysler Corp. v. Brown, 441 U.S. 281, 99 S.Ct. 1705, 60 L.Ed.2d 208 (1978).

However, not only do various points in Smith & Wesson's petition belie the characterization it so vehemently denies (see Pages 2, 4 of its Petition), but the plain language of Sec. 1491(a)(3) ("any contract claim brought before the contract is awarded") would appear to be clearly descriptive of the controversy presented to the court below in the suit filed by Smith & Wesson, i.e. a dispute concerning the actions or inactions of an agency occurring prior to the award of a contract, and the questions raised thereby regarding the rights of the parties to such dispute.

We thus regard the action below as a pre-award contract claim within the meaning of Sec. 1491(a)(3).

II. The jurisdiction of the district courts under the FCIA

Although the express language of Sec. 1491(a)(3) would appear to divest the district courts of jurisdiction of pre-award contract claims, the courts are divided on this issue. See Opal Manufacturing Co. v. U.M.C. Industries, Inc., 553 F.Supp. 131 (D.D.C.1982) (no jurisdiction in district courts); accord, B.K. Investments v. United States, 715 F.2d 713, 715 n. 4 (dictum) (2nd Cir.1983). Cf., Coco Bros., Inc. v. Pierce, 741 F.2d 675 (3rd Cir.1984) (there is jurisdiction), United States v. John C. Grimberg, 702 F.2d 1362, 1369-72 (Fed.Cir.1983) (there is jurisdiction).

Relying solely on the literal language of section 1491(a)(3), the District Court for the District of Columbia held, in Opal Manufacturing Co., supra, that "the FCIA must be read to vest jurisdiction in the Claims Court for pre-award contract claims, to the exclusion of this Court." (Emphasis added). This position, based upon the interpretation of the word "exclusive" as applying to any and all other courts was, however, rejected by the Third Circuit Court of Appeals. In Coco Bros., Inc., supra, the Third Circuit found that construction plausible but erroneous by reason of the legislative history of the statute in question.

The legislative history explaining the grant of equitable powers to the Claims Court was reviewed in John C. Grimberg, supra. As summarized in Coco Bros., Inc., supra, at 678, it explained:

In an early version of the proposed legislation, the Claims Court was to be given equitable power in all cases brought before it. See S. 21, 97th Cong., 1st Sess. Sec. 132(a)(2) (1981); H.R. 2405, 97th Cong., 1st Sess. Sec. 126(d) (1981). However, because of strenuous objections by the Justice Department, that provision was changed to limit the grant to pre-award contract cases. The Federal Circuit Court, although not presented with the issue of pre-award jurisdiction, commented that it could find no indication that Congress intended to take away the district court's power to act in those cases.

Observations by the House Judiciary Committee regarding the grant of equitable power to the Claims Court include a statement to the effect that: "This enlarged authority is exclusive of the Board of Contract Appeals and not to the exclusion of the district court." (Emphasis supplied). H.R.Rep. No. 312, 97th Cong., 1st Sess. 43 (1981). That exclusion of the district courts was not contemplated is further emphasized in that report where it states:

It is not the intent of the Committee to change existing case law as to the ability of the parties to proceed in the district court pursuant to the provisions of the Administrative Procedure Act in instances of illegal agency action.... Nor is it the intent of the Committee to obligate lawyers, litigants, and possibly witnesses to travel to Washington, D.C., whenever equitable relief is sought in a contact (sic) action prior to award. Although Claims Court judges will travel, they cannot be expected to do so at (sic) extremely short notice. Therefore, for the time being, the Committee is satisfed (sic) by clothing the Claim Court with enlarged equitable powers not to the exclusion of the district courts. The dual questions of whether these powers should be even broader and of whether they should be exclusive of the district courts will have to wait for a later date.

Id. (Emphasis added).

The Senate Report supports the House report in its assertion that under Section 1491(a)(3) there is no change in the jurisdiction of the district courts:

By conferring jurisdiction upon the Claims Court to award injunctive relief in the pre-award stage of the procurement process, the Committee does not alter the current state of the substantive law in this area. Specifically, the Scanwell doctrine as enunciated by the D.C. Circuit Court of Appeals in 1970 is left in tact (sic). See Scanwell Laboratories, Inc. v. Shaffer, 424 F.2d 859 (D.C.Cir.1970)....

Since the court is granted jurisdiction in this area boards of contract appeals would not possesses comparable authority pursuant to the last sentence of section 8(d) of the Contract Disputes Act.

S.Rep. No. 275, 97th Cong., 1st Sess. 23, reprinted in 1982 U.S.Code Cong. and Admin.News 11, 33.

We are well aware that in going behind the apparently plain language of Sec. 1491(a)(3) we seem to be violating a cardinal principal of legislative interpretation. See T.V.A. v. Hill, 437 U.S. 153, 184 n. 29, 98 S.Ct. 2279, 2296 n. 29, 57 L.Ed.2d 117 (1978). Yet this rule is not without exceptions. In our recent opinion in Cia. Petrolera Caribe, Inc. v. Arco Caribbean, Inc., et al., 754 F.2d 404 at 415 (1st Cir., 1985), we made reference to such an exception If the statutory language is unambiguous, in the absence of "a...

To continue reading

Request your trial
15 cases
  • Norton v. Beasley
    • United States
    • U.S. District Court — Eastern District of Kentucky
    • September 30, 2021
    ...standing requirement, and they are entitled to judicial review of the Keeper's decision. See generally In re Smith & Wesson , 757 F.2d 431, 433 (1st Cir. 1985) ("It is well-settled that there is standing to seek judicial review of agency action in the district courts under [the APA] when ar......
  • Isaac v. Harvard University, 84-1934
    • United States
    • U.S. Court of Appeals — First Circuit
    • May 8, 1985
    ...L.Ed.2d 17 (1983); United States v. Turkette, 452 U.S. 576, 580, 101 S.Ct. 2524, 2527, 69 L.Ed.2d 246 (1981). See In re Smith & Wesson, 757 F.2d 431, 434-35 (1st Cir.1985); Cia. Petrolera Caribe, Inc. v. Arco Caribbean, Inc., 754 F.2d 404, 415 (1st Cir.1985). We have concluded that we need ......
  • Gilman v. Helms
    • United States
    • U.S. District Court — District of New Hampshire
    • April 18, 1985
    ...Coal Company v. Federal Mine Safety and Health Review Commission, 743 F.2d 589, 595 (7th Cir.1984); see generally In re Smith and Wesson, 757 F.2d 431, 433-434 (1st Cir.1985) (rejecting plain meaning of statute only where both House and Senate legislative history clearly expressed opposite ...
  • National Federation of Federal Employees v. Cheney
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • August 25, 1989
    ...contracting out would have standing to sue.29 See Choctaw Mfg. v. United States, 761 F.2d 609 (11th Cir.1985); In re Smith & Wesson, 757 F.2d 431 (1st Cir.1985); CACI, Inc.-Federal v. United States, 719 F.2d 1567, 1573-75 (Fed.Cir.1983); B.K. Instrument, Inc. v. United States, 715 F.2d 713 ......
  • Request a trial to view additional results
1 books & journal articles

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT