Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co.
Decision Date | 15 October 1991 |
Docket Number | SMOKETREE-LAKE |
Citation | 286 Cal.Rptr. 435,234 Cal.App.3d 1724 |
Court | California Court of Appeals Court of Appeals |
Parties | MURRAY, LTD., et al., Cross-Complainants and Appellants, v. MILLS CONCRETE CONSTRUCTION COMPANY INC., et al., Cross-Defendants and Respondents. D009394. |
Hughes & Campbell, Campbell and Associates, John B. Campbell, San Diego, Horvitz & Levy, David M. Axelrad and Daniel J. Gonzalez, Encino, for cross-complainants and appellants.
Hartley & Associates, Karen J. Hartley, Gibson & Kennerson, Paul R. Kennerson, San Diego, and John K. Grant, Oceanside, for cross-defendants and respondents.
Smoketree-Lake Murray, Ltd., Brehm Construction Company and Forrest W. Brehm (hereafter Developer) appeal a judgment on a cross-claim for indemnification. On appeal, Developer contends the judgment must be reversed because the trial court erred in ruling a fraud finding barred indemnification and failing to find the jury committed misconduct. We reverse.
In 1985, the Smoketree-Lake Murray Owners' Association, Inc. sued Developer and others for damage to their condominium complex. These damages manifested themselves as cracks in walls and slabs, doors which would not close properly, patios which pulled away from buildings and cracks causing leaks in the complex's swimming pool. Developer eventually settled with the Association for over $3,000,000.
Developer cross-complained for indemnification against various subcontractors including Calego Excavating Company (Calego) who performed the grading work, and Mills Concrete Construction Company, Inc. (Mills), which did the concrete work. In defense, Mills and Calego contended Developer's fraud, in making misrepresentations and concealing information from the condominium purchasers, barred Developer from obtaining indemnity. Developer also raised a fraud issue, contending the subcontractors had fraudulently induced Developer to enter into narrower indemnity agreements.
The trial court, ruling a finding of fraud would preclude indemnification, bifurcated the trial.
At trial, there was evidence presented that the damage to the condominiums and pool was caused, in part, by soil movement. The soil may not have been properly compacted by Calego or properly tested by Southern California Testing Laboratory (SOCAL), the soils expert hired by Developer. There was also evidence that the concrete slabs were improperly constructed. Among other things, there was evidence that the concrete used was of inadequate quality, contained too much water and that the slabs were poured too thin.
To support the claim Developer made material misrepresentations to the buyers, the subcontractors presented evidence indicating Developer knew at the time he bought the property there were expansive soils on the property which would make development more expensive, the initial soils report originally recommended specially designed footings and slabs but a subsequent report made after discussions with Developer recommended a less expensive alternative of capping the building pads with 2.5 feet of select (nonexpansive) soil; pockets of expansive soils were found in the upper 2.5 feet of some of the building pads but only one building received a reinforced slab; shortly after the concrete slabs were poured, cracks were observed which prompted a report from the soils experts stating the "structural integrity of the foundation system" was threatened; and despite this knowledge, Developer failed to disclose the existence of the expansive soils, the cracks in the concrete slabs or the soils expert's report to the condominium buyers.
In response, Developer presented evidence showing it relied on the recommendations of its experts. Developer reinforced only one slab because SOCAL only recommended reinforcing one slab. Developer had, at SOCAL's recommendation extended the footings in other slabs. 1 Developer presented evidence that the cracks observed in the concrete slabs soon after they were poured were shrinkage cracks which were monitored over a period of months. Numerous witnesses, including Mills, testified shrinkage cracks normally or regularly occur, are not a matter of concern and do not need to be repaired. The soils expert who had reported the cracks would "have an adverse affect on the structural integrity" testified that was a bad choice of words and he did not believe the cracks actually threatened the structural integrity of the building because they were only shrinkage cracks. A number of experts testified Developer's monitoring of the cracks rather than conducting additional investigation by taking core samples or drilling holes and Developer's eventual conclusion the cracks were due to concrete shrinkage rather than soil subsidence were reasonable and therefore, according to Developer's evidence, Developer did not make any material misrepresentations to the condominium buyers.
As we explain below, we hold a jury's finding Developer made misrepresentations to or concealed information from third parties does not negate the express indemnity agreements entered into between Developer and the subcontractors. 2
The parties entered into more than one idemnification agreement. 3 In the original standard form contract between Developer and the subcontractors, an indemnity clause provided:
In August 1976, Developer individually negotiated agreements with Mills and Calego which contained indemnity clauses and personal guarantees for indemnity.
In the agreement between Mills and Developer, Mills acknowledged "[t]he concrete work performed by Mills on the Property may not have been done in accordance with the plans and specifications provided, the engineer's requirements and the Uniform Building Code." Developer agreed to accept Mills's work and pay as provided by the original agreement and Mills and its two sole shareholders agreed to "indemnify and hold [Developer] harmless from any damage or loss [Developer] may suffer resulting from any failure by Mills to comply with the plans and specifications, engineer's requirements or the Uniform Building Code, including but not limited to all actions, suits, proceedings, demands, assessments, judgments, attorneys' fees, costs and expenses incident thereto."
The agreement between Developer and Calego provided "[t]he grading and excavating work performed by CALEGO on the property was not done in accordance with the plans and specifications" and that Developer would only accept and pay for the work if (1) Calego entered an indemnity agreement, (2) Calego's work was accepted by the city, (3) Developer verified the grading met foundation elevations and agreed banks between buildings and (4) Calego agreed to perform some remedial grading. In the indemnity provision, Calego and its partners agreed to hold Developer "harmless from any damage [Developer] may suffer resulting from any failure by CALEGO to comply with the plans and specifications through the fault of CALEGO including, but not limited to, all actions, suits, proceedings, demands, assessments, judgments, costs and expenses reasonably incident thereto."
The trial court bifurcated the trial ordering the fraud issues be tried before the issues of damages. During the course of the arguments on the issue, the trial court stated:
In its instructions to the jury at the outset of the case, before opening arguments were made or evidence was presented, the trial court instructed the jury on the elements of fraud and then explained:
Thr...
To continue reading
Request your trial-
Downey Venture v. LMI Ins. Co.
...that section 1668 applies to indemnity agreements such as an insurance policy. (See Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal.App.3d 1724, 1741, 286 Cal.Rptr. 435.) Moreover, since section 533 clearly precludes an insurer from indemnifying an insured for ......
-
People v. Wilson
...other jurors he knew the law]), or engages in an experiment that produces new evidence (Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal.App.3d 1724, 1746, 286 Cal.Rptr. 435 [conducting an experiment regarding the pouring of concrete]). "Juror misconduct, such a......
-
Chicago Title Ins. Co. v. Amz Ins. Serv. Inc.
...negligence; to obtain greater indemnity, more specific language must be used." ( Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal.App.3d 1724, 1737, 286 Cal.Rptr. 435; see Gonzales v. R.J. Novick Constr. Co. (1978) 20 Cal.3d 798, 809-810, 144 Cal.Rptr. 408, 575 ......
-
Heppler v. J.M. Peters Co.
...supra, 53 Cal.App.4th at p. 505, 61 Cal.Rptr.2d 668.) As this court has pointed out in Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal.App.3d 1724, 1737, 286 Cal.Rptr. 435, the specificity of the language used is a key factor in construction of an indemnity agr......
-
Submission to jury and deliberations
...inject his or her own expertise into the jury’s deliberations. Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal. App. 3d 1724, 1746, 286 Cal. Rptr. 435. The court may permit the jurors to separate during deliberations. Code Civ. Proc. §611; Pen. Code §1128; McDo......
-
Table of cases
...(2006) 138 Cal. App. 4th 883, 41 Cal. Rptr. 3d 857, §10:180 Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal. App. 3d 1724, 286 Cal. Rptr. 435, §§22:170, 22:180 Smrekar v. Bay & River Nav. Co. (1945) 69 Cal. App. 2d 654, 160 P.2d 85, §4:70 Snelgrove v. Dept. of ......