Southwire Co. v. Beloit Eastern Corp., Civ. A. No. 42129

Decision Date05 February 1974
Docket NumberCiv. A. No. 42129,42130.
Citation370 F. Supp. 842
PartiesSOUTHWIRE CO. v. BELOIT EASTERN CORP. v. SYNCRO MACHINE CO. The TRAVELERS INDEMNITY CO. v. BELOIT EASTERN CORPORATION v. SYNCRO MACHINE CO.
CourtU.S. District Court — Eastern District of Pennsylvania

Victor L. Drexel, Philadelphia, Pa., for plaintiff.

Lynn L. Detweiler, Philadelphia, Pa., for Beloit.

Joseph J. Murphy, Philadelphia, Pa., for Syncro.

OPINION

EDWARD R. BECKER, District Judge.

I.Preliminary Statement

This suit was brought to recover damages occasioned by the malfunction of a large machine known as a tubular strander, which twists together seven or eight wires of aluminum or steel into wire rope.1The malfunction occurred on January 23, 1964 and was caused by the failure of a cradle casting which supports the large bobbins of wire that feed the machine.PlaintiffSouthwire Company(Southwire), a firm engaged in making electrical wire and cable for distribution in the South, is the owner of the malfunctioning strander which was located at its wire mill in Carrollton, Ga.2DefendantBeloit Eastern Co.(Beloit) manufactured and cast the cradles at its Downingtown, Pa. foundry.Beloit supplied them to third-party defendantSyncro Machine Co.(Syncro) which manufactured and assembled the stranders at its Perth Amboy, N. J. plant.

Southwire is the plaintiff in C.A. 42129.The Travelers Indemnity Co.(Travelers) was, at times relevant here, the products liability insurer of Syncro.By reason of damage claims made by Southwire against Syncro, Travelers entered into an agreement on June 15, 1966.Under this agreement, Travelers advanced $95,000 to Southwire in return for Southwire's covenant not to sue Syncro; Southwire also assigned to Travelers the right to sue any person it considered to be liable.Travelers is the plaintiff in C.A. 42130, which it brought in its own name.3Beloit is the defendant in both actions and it has joined Syncro as third party defendant in both.

The central question in the case is the cause of the failure of the casting.When the casting fractured, the reel and cradle in the No. 6 bay of the strander were thrown through the window of the tube in which they were installed, causing the damage complained of.Plaintiffs contend that the casting failed because it was defective, porous, weak, and improperly cast.Beloit contends that the failure was caused by: (1) the weakening of the casting which occurred when Syncro welded a counterweight to the casting during the course of assembling the machine; and (2) the inordinate and unanticipated stresses to which the casting was subjected because of improper design and maintenance of the machine.In terms of legal theory, the plaintiffs seek recovery under § 402A of the Restatement of Torts,4 and alternatively, on the theory of negligence.5Beloit defends on the grounds that: (1) the casting which it furnished was in accordance with specifications and was not defective; (2) there was a substantial change in the casting between the time it was sold and the time of the accident, because of the effect on the casting of the counterweight weld; (3) there was no negligence in the manufacture of the casting; and (4)plaintiffs have failed to prove proximate cause.In particular, Beloit contends that the causes of the accident were: (1) the welding which materially weakened the casting at its most critical area; (2) the stresses and vibrations to which the casting was subjected by (a) the misalignment and excessive vibration of the machine and (b) frequent tangles in the wire.

As might be expected in a case of this sort, there developed a battle between experts in the field of metallurgical science.Southwire's expert was Dr. Thomas F. Talbot, a Professor of Engineering at the University of Alabama and a consulting engineer and metallurgist.Dr. Talbot visited the Southwire plant on the day of the accident, and subsequently examined and tested metal from the fractured cradle.Dr. Talbot expressed the opinion that the casting was not sound and that the counterweight welding did not substantially affect it or cause the accident.Beloit's expert was Dr. A. W. Grosvenor, a Professor of Engineering at Drexel University and likewise a consulting mechanical engineer and metallurgist.Dr. Grosvenor expressed the view that the casting failed because it was substantially weakened and embrittled from the counterweight welding and because of the high stresses to which the casting was subjected.He expressed his expert opinion that the casting did not fail due to any defect in the cradle as originally cast.Each of the expert witnesses brought a superlative background and imposing qualifications to the witness stand.Each demonstrated encyclopedic knowledge of his field, together with a sharp acumen.We found the testimony of each impressive and they rendered the question before us close indeed.And while we found Dr. Talbot's testimony to be earnest and well-reasoned, it did not overcome the equally earnest and more convincing testimony given by Dr. Grosvenor.

Our detailed findings of fact and conclusions of law now follow.We note that it is the factual and not the legal issues which are crucial in this case.We have made extensive findings of fact in the wake of which the legal issues become relatively simple and straightforward.Suffice it to say at this juncture that, after careful consideration of all the evidence, we have concluded that plaintiffs must be denied relief since they failed to carry their burden of proving their claim by a fair preponderance of the evidence.

II.Findings of Fact
A.The Machine

The strander in question was sold to Southwire by Syncro pursuant to a purchase order dated February 2, 1962, and Syncro's acceptance dated February 5, 1962.This was one of two wire stranders purchased by Southwire in order to take care of its top product range, the production of electrical wire and cable.Southwire and Syncro jointly designed the strander; however Southwire's part in the design consisted merely in prescribing the sizes of the parts in order to be sure the strander would fit in the space that was available.

The strander had the capacity to make seven or eight wire strands of either aluminum or steel and was composed of seven bays, each of which received a bobbin of wire through an opening.The bobbins for the strander in question were 31 inches in diameter.The bobbins were carried by shafts which rested on the cradles.The shafts had bobbin locks which prevented the bobbin from coming off in the event it rotated or turned over.The locks or bars were secured through blocks which were bolted to the side of the cradle.The bearings provided a means of supporting the cradle without a friction grip between the cradle and the spiders which were connected to sections between the tubes or bays and constituted the main support for the tube.The bobbins were held in the same plane by the cradles while the tube rotated at approximately 500-550 r.p.m.'s The rotation of the tube gave a pre-twist to the wire as it came off the machine onto the capstans which were two grooved wheels or drums.The tube and capstan were geared together so that as the tube revolved the capstan moved a pre-determined distance.

The individual strands of wire from each bobbin traveled through guide rollers and wire guides on the individual strands of wire in a uniform configuration so that they would join together in a uniform and controlled manner.The individual wire strands were twisted together as they passed through a closing die.From the closing die, the stranded wire or cable was pulled onto the capstans.From that point, the wire was taken up on a ship-out package or takeup reel.The wire produced as an end product by the strander was used as electrical conductor, messenger wire, and steel supporting cable.

The strander was operated on a 24-hour, 7-day a week basis, except for down-time to change spools and except for one 8-hour shift per week during which the strander was serviced and maintained.It produced stranded wire at a rate of 130 to 500 feet per minute, depending on the product and size of cable being produced.For the first few months of its operation, the strander was realigned several times to compensate for vibration.As soon as vibration was detected, the machine was shut down for realignment and service.Although the gross misalignment problem was thus corrected, the problem of misalignment remained to some degree—at least 7/64ths of an inch.Dr. Talbot so testified, although he concluded that misalignment did not cause the accident in question.

Each cradle was keel-weighted on the bottom so that it would stay in the same plane with a bearing at each end of the cradle and not rotate with the rotation of the barrel and spider.Occasionally a wire would cross over so that it would be pulled off center and tend to either swing the cradle or turn it around.The bobbin shaft had a rod (called a bobbin lock) that prevented the bobbin from coming out in the event it did rotate or turn over.The strander frequently had tangles which could pull the bobbin completely over and rotate the cradle and bobbin; tangles could be and often were caused by improper wrapping of the wire on the spool or reel.6

B.The Casting and The Counter-weights

The cradle casting in question was manufactured by Beloit.Its dimensions were 51¾" in overall length with an overall depth of approximately 10 inches.It can best be described as a flat slab of cast iron, tapered and curved at each end, with a semi-circular depression referred to as a "saddle" in the top side of the middle of the casting.Two mating castings were used in each tube or bay, bolted together at either end and forming a hollow, roughly oval, bottomless cradle which could be likened to a bottomless hammock.Between the sides of the cradle sat the reel or bobbin which contained the wire rope.This bobbin turned on an axle, the...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
29 cases
  • Brown v. U.S. Stove Co.
    • United States
    • New Jersey Supreme Court
    • December 21, 1984
    ...at 149, 484 A.2d at 1231; see Johnson v. Salem Corp., 97 N.J. 78, 94-95, 477 A.2d 1246 (1984); see also Southwire Co. v. Beloit Eastern Corp., 370 F.Supp. 842, 857 n. 21 (E.D.Pa.1974) (for substantial change to negate [Restatement] § 402A liability, it must be intervening superseding cause ......
  • Banks v. Iron Hustler Corp.
    • United States
    • Court of Special Appeals of Maryland
    • September 1, 1983
    ...from the law of negligence, view the matter as whether the alteration constituted a supervening cause. See Southwire Co. v. Beloit Eastern Corp., 370 F.Supp. 842, 856-57 (E.D.Pa.1974). If there is a common thread, it seems to be that, in most cases, the substantiality of the change is a que......
  • Potter v. Chicago Pneumatic Tool Co.
    • United States
    • Connecticut Supreme Court
    • May 27, 1997
    ...modification breaks the chain of causation, akin to an intervening superseding cause in negligence law. Southwire Co. v. Beloit Eastern Corp., 370 F.Supp. 842, 857 n. 21 (E.D.Pa.1974). In other words, a manufacturer "could still be liable because the original defect, although not the sole c......
  • Yun v. Ford Motor Co.
    • United States
    • New Jersey Superior Court — Appellate Division
    • September 26, 1994
    ...cause or the existence of another "sole proximate cause" of the resulting injury. Ibid. (citing Southwire Co. v. Beloit Eastern Corp., 370 F.Supp. 842, 857 n. 21 (E.D.Pa.1974)). Assuming, arguendo, that the spare tire assembly was a substantial factor in causing Chang's injuries, Chang's hi......
  • Get Started for Free

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT