Sproul Const. Co. v. St. Paul Fire & Marine Ins. Co.

Decision Date18 May 1964
Docket NumberNo. 7323,7323
Citation392 P.2d 339,1964 NMSC 102,74 N.M. 189
PartiesSPROUL CONSTRUCTION COMPANY, Sproul Brothers, Inc., Sproul-Brozo Construction Corp., Plaintiffs-Appellees, v. ST. PAUL FIRE & MARINE INSURANCE COMPANY, Defendant-Appellant.
CourtNew Mexico Supreme Court

Keleher & McLeod, Russell Moore, Albuquerque, for appellant.

Rodey, Dickason, Sloan, Akin & Robb, Robert D. Taichert, John P. Eastham, Albuquerque, for appellees.

ON SECOND MOTION FOR REHEARING

PER CURIAM:

Leave of the court has been granted for the filing of a second motion for rehearing by defendant-appellant. Sec. 21-2-1(18)(7), N.M.S.A.1953. Upon consideration of the same, the former opinion, reported at 73 N.M. 421, 389 P.2d 194, is withdrawn and the following substituted therefor:

OPINION

MOISE, Justice.

This action was commenced as a suit to foreclose materialmen's liens. The plaintiffs, Air Service, Inc., and Air Conditioning Equipment Company, furnished labor and materials to the defendant, Associated Roofing and Supply Company, Inc., hereinafter referred to as 'Associated,' in connection with the performance by Associated of a sub-contract between it and defendants, Sproul Construction Company, Sproul Brothers, Inc., and Sproul-Brozo Construction Corp., hereinafter referred to as 'Sproul.' Upon failure of Associated to pay plaintiffs as agreed, liens were duly filed and this suit commenced to foreclose the same. Additional suppliers, who had also filed liens, intervened. Sproul, the contractor, filed a third-party action against St. Paul Fire & Marine Insurance Company, hereinafter referred to as 'St. Paul' or 'insurer,' alleging the execution by St. Paul of a 'performance and payment bond' guaranteeing the performance by Associated of its sub-contract with Sproul. St Paul, by answer, pleaded a number of defenses, only two of which are material to this appeal.

St. Paul, in its brief, states its 'principal defense' to be 'that after notice to Sproul that Associated was insolvent and that liens had been filed' in connection with the construction, Sproul continued to make progress payments to Associated, prejudicing the rights of St. Paul and thus voiding the bond.

All issues of fact having been settled by agreement between the parties, judgments were duly entered. It was understood that the issues raised by the defenses of St. Paul to the third-party complaint of Sproul were not to be prejudiced thereby. The issues of law raised by the answer of St. Paul were in turn decided by the trial court in favor of Sproul, and this appeal followed.

The contract between the parties contained the following language:

'D * * * Subcontractor shall submit to Contractor at his office as noted above, or by mail to the Contractor at P. O. Box 3158, Sta. D., Albuquerque, N. M., on or before the 25th day of each month an estimate of the amount of work put in place by Sub Contractor during that month. Contractor upon satisfying itself that Sub Contractor's estimate is reasonably accurate, shall pay to Sub Contractor a sum representing 90% thereof.'

and the following additional sections:

'2. The work done under the contract resulting from this Proposal (hereinafter called the Contract) shall be turned over by Sub-Contractor to Contractor in good condition, free and clear from all claims, encumbrances, patent royalties and liens growing out of the performance of that contract. In the event of the failure of Sub-Contractor during the progress of such work, or at any time thereafter, to pay for all materials and/or labor used in the prosecution of said work. Contractor may, at its option and without notice to Sub-Contractor prior thereto, pay any or all such claims for materials and/or labor and charge the amount so paid to Sub-Contractor. In case suit to establish lien is brought by any person, firm or corporation employed by or furnishing material or services to Sub-Contractor in connection with the Contract, Sub-Contractor shall at his own cost and expense (including Attorney's fees) defend such suit and pay such lien established in court and in any other way make Contractor whole for any costs or losses sustained as a result of such lien claims. Sub-Contractor shall, as often as requested in writing by the owner or by Contractor, make out and give to said Owner or Contractor a sworn statement of persons furnishing labor or materials to the Sub-Contractor, giving their names and how much, if any, is due or will be due to each.'

'5. Monies received by Sub-Contractor for the performance of the Contract shall be used primarily for labor and material entering into this work and said monies shall not be diverted. to satisfy obligations of the Sub-Contractor on other contracts.'

The condition of the bond executed by Associated Roofing and Supply Company, Inc., as principal, and St. Paul Fire and Marine Insurance Company, as surety, to Sproul Construction Company, as obligee, reads as follows:

'NOW, THEREFORE, the condition of the foregoing obligation is such that if the Principal shall indemnify the Obligee for all loss that the Obligee may sustain by reason of the Principal's failure to comply with any of the terms of said contract, then this obligation shall be void; otherwise it shall remain in force.'

Although St. Paul pleaded numerous defenses, we need notice only those that are argued here on appeal, all others being considered abandoned. Hendrix v. Dominguez, 58 N.M. 216, 269 P.2d 1099.

Did the trial court err in sustaining Sproul's motion for summary judgment? By so ruling, the legal defenses presented were held ineffective. These defenses asserted that the bond was voided by virtue of Sproul's acts in continuing to make payments to Associated after mechanics' liens had been filed, knowing Associated was insolvent, and also because of Sproul's failure to retain 10% of the contract price.

St. Paul places principal reliance on the early cases of Lyons v. Kitchell, 18 N.M. 82, 134 P. 213, Ann.Cas.1915C, 671, and Morgan v. Salmon, 18 N.M. 72, 135 P. 553, L.R.A.1915B, 407.

Lyons v. Kitchell, supra, is distinguishable. Payment without retaining 20% was held to be a deviation from the contract and to operate to discharge the surety. The surety there was an accommodation or non-compensated surety, whereas here, St. Paul was paid for the obligation it undertook. That this makes a difference is recognized by the court in its decision. See also, Southwestern Portland Cement Co. v. Williams, 32 N.M. 68, 251 P. 380, 49 A.L.R. 525; note in 94 A.L.R. 876.

Morgan v. Salmon, supra, was a case of a paid surety and, even so, a failure to retain a percentage of the value of labor and materials furnished as provided in the contract was held to be a substantial deviation and operate to discharge the surety. However, the bond there being sued upon was conditioned as follows:

'[A]ll moneys, which but for such default would be due, or would thereafter become due, to the principal, shall be held by the obligee and by him applied for the indemnification of the surety. * * *'

and also:

'Fourth. That the obligee shall retain not less than fifteen (15%) per centum of the value of all work performed and materials furnished in the performance of said contract, until the complete performance by the said principal of all the terms, covenants, and conditions thereof, on said principal's part to be performed, and that the obligee shall faithfully perform all the terms, covenants and conditions of said contract on the part of said obligee to be performed.'

The surety bound itself only on condition...

To continue reading

Request your trial
6 cases
  • Sangre de Cristo Development Corp., Inc. v. City of Santa Fe
    • United States
    • Supreme Court of New Mexico
    • 22 Noviembre 1972
    ...N.M. 30, 474 P.2d 712 (Ct.App.1970)), and then to present argument and authority in support thereof (Sproule Const. Co. v. St. Paul Fire & Marine Ins. Co., 74 N.M. 189, 392 P.2d 339 (1964); Gibbs v. Whelan, 56 N.M. 38, 239 P.2d 727 (1952); Spain Management Co. v. Packs' Auto Sales, 54 N.M. ......
  • Honolulu Roofing Co. v. Felix
    • United States
    • Supreme Court of Hawai'i
    • 28 Marzo 1967
    ...then the burden again rested on the owners of showing that such sums were so borrowed.32 See Sproul Construction Co. v. St. Paul Fire & Marine Insurance Co., 74 N.M. 189, 392 P.2d 339, 341, and Steck v. Home Indemnity Co., 74 N.M. 419, 394 P.2d 267, 268, which distinguish Morgan v. Salmon, ......
  • Denton v. Fireman's Fund Indemnity Company, 7939.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (10th Circuit)
    • 28 Octubre 1965
    ...will operate to release his obligations at least to the extent of the prejudice. See Sproul Construction Company et al. v. St. Paul Fire and Marine Insurance Company, 74 N.M. 189, 392 P.2d 339. While New Mexico has not specifically applied this rule to indemnity contracts, it is generally a......
  • Steck v. Home Indemn. Co.
    • United States
    • Supreme Court of New Mexico
    • 20 Julio 1964
    ...properly ascertained and fixed by the trial court. A very recent opinion of this Court in the case of Sproul Const. Co. v. St. Paul Fire & Marine Ins. Co., 74 N.M. 189, 392 P.2d 339, considers and rules upon the precise question here involved. That opinion fully and clearly enunciated the r......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT