SPS Industries, Inc. v. Atlantic Steel Co.
Decision Date | 26 February 1988 |
Docket Number | No. 75143,75143 |
Citation | 366 S.E.2d 410,186 Ga.App. 94 |
Parties | , 6 UCC Rep.Serv.2d 122 SPS INDUSTRIES, INC. v. ATLANTIC STEEL COMPANY. |
Court | Georgia Court of Appeals |
James T. Perry, Atlanta, for appellant.
Walter G. Elliott II, Atlanta, for appellee.
On February 6, 1979, defendant Atlantic Steel Company sent to plaintiff SPS Industries, Inc., a "quotation request" seeking information regarding price, terms and delivery for six (three pairs) cast tooth mill pinions. The pinions were to be manufactured in accordance with defendant's specifications for use in a Blooming mill which defendant operated. Replying to defendant's request, plaintiff submitted a price quotation of $4,795 for each pinion; delivery was proposed to be made in "20-24 weeks." Thereafter, on March 5, 1979, defendant issued to plaintiff a "purchase order" which called for the delivery of six cast tooth mill pinions (at the price quoted by plaintiff) as follows: one pair to be delivered by July 25, 1979; a second pair to be delivered by November 1, 1979; a third pair to be delivered by January 5, 1980. In response to defendant's purchase order, plaintiff sent defendant an "order acknowledgement" which confirmed the delivery dates.
Plaintiff encountered numerous problems manufacturing the pinions and it did not meet the delivery dates. On August 6, 1979, defendant's purchasing agent sent the following letter to plaintiff: Charles J. Wentz, plaintiff's president, deposed that ordinarily such a letter was referred to the appropriate personnel for a response. He did not know, however, whether plaintiff in fact responded to the letter.
Nearly 18 months after the delivery date specified in the contract, on January 14, 1981, plaintiff shipped the first pair of pinions to defendant. By that time, unbeknownst to plaintiff, defendant abandoned the operation of its Blooming mill (it was replaced by a "continuous caster") and it had no use for the pinions.
Several weeks after the delivery of the first pair of pinions, defendant notified plaintiff that it was cancelling the "remaining part" of the order. The cancellation took the form of a "change order" which was sent by defendant to plaintiff on February 16, 1981.
On February 18, 1981, plaintiff mailed a letter to defendant confirming a telephone conversation which took place on the previous day. Therein, plaintiff informed defendant that the charges for the cancellation of the four remaining pinions would be $13,840. In this regard, plaintiff advised defendant that of the four remaining pinions, two had been drawn to specifications and two were "in the as cast condition." Plaintiff concluded: "Per your telephone instructions all work on this order has been stopped until you advise [plaintiff] if we are to continue to finish these four (4) pinions or are to ship in present condition to your plant." Thereafter, on March 17, 1981, plaintiff sent defendant an invoice which acknowledged defendant's February 16, 1981, change order and set forth cancellation charges of $13,840.
On April 24, 1981, plaintiff received a letter from defendant stating, in pertinent part:
In view of defendant's refusal to make payment, plaintiff brought this action in the State Court of Fulton County seeking to recover $23,940 (the price of the delivered pinions plus the cancellation charges). Defendant answered the complaint, alleging, inter alia, that plaintiff was not entitled to a recovery because it breached the parties' contract. Additionally, defendant counterclaimed, alleging it incurred damages as a result of plaintiff's purported breach. Following discovery, defendant moved for summary judgment. Its motion was accompanied by a statement of undisputed material facts (in accordance with Rule 6.5 of the Uniform State Court Rules). Paragraphs 6 and 7 of the statement read: In Paragraph 11 of the statement, defendant asserted: "On February 6, 1981 [defendant] notified [plaintiff] that it had no use for the pinions and that it did not want them."
Opposing defendant's summary judgment motion, plaintiff submitted the affidavit of Charles J. Wentz, its president. In the affidavit, Wentz deposed that the letter which plaintiff received from defendant on April 24, 1981, was "the first statement of any kind, by [defendant] that it was rejecting delivery of the first two mill pinions ... [and] the first indication that [defendant] would not pay the CANCELLATION charges as detailed in [plaintiff's] prior invoice." Plaintiff did not file a formal response to defendant's statement of undisputed material facts.
Following a hearing upon defendant's summary judgment motion, the trial court entered summary judgment in favor of defendant with regard to the main claim. In pertinent part, the trial court's order read as follows:
Plaintiff appeals, asserting the existence of genuine issues of material fact and the inappropriateness of summary judgment. Held:
1. Defendant contends it is entitled to summary judgment because plaintiff repudiated the contract as a matter of law. In this regard, defendant argues that it demanded adequate assurance of due performance and that plaintiff failed to respond to the demand, thereby repudiating the contract. We disagree. Viewing the evidence favorably to plaintiff, as we are bound to do, Blount v. Seckinger Realty Co., 167 Ga.App. 778, 779, 307 S.E.2d 683, we find genuine issues of material fact with respect to the repudiation issue. Specifically, factual questions exist concerning (a) whether defendant had reasonable grounds for insecurity, (b) whether defendant demanded adequate assurance of due performance, (c) whether plaintiff failed to respond to the demand and (d) whether defendant proceeded as if a repudiation never took place.
(a) OCGA § 11-2-609(1) provides: The Code section makes it clear that in order for a party to demand adequate assurance, he must first have "reasonable grounds for insecurity." As observed in Cole v. Melvin, 441 F.Supp. 193, 203 (D.S.D.1977),
"Whether in a specific case a buyer has reasonable grounds for insecurity is a question of fact." AMF, Inc. v. McDonald's Corp., 536 F.2d 1167, 1170 (7th Cir.1976). Do the facts show that defendant had reasonable grounds for insecurity when it sent its letter of August 6, 1979? We think not. "Between merchants the reasonableness of grounds for insecurity and the adequacy of any assurance offered shall be determined according to commercial standards." OCGA § 11-2-609(2). Reviewing the record, we can find no evidence showing the reasonableness of grounds for insecurity on August 6, 1979, by any objective standard. Cole v. Melvin, 441 F.Supp. 193, 203, supra. Compare AMF, Inc. v. McDonald's Corp., 536 F.2d 1167, 1170, supra.
(b) OCGA §...
To continue reading
Request your trial-
Validsa, Inc. v. Pdvsa Services Inc.
...the scope of Section 2-609. Id. at 1046-47. Likewise, the facts here are different from those in SPS Industries, Inc. v. Atlantic Steel Co., 186 Ga. App. 94, 366 S.E.2d 410, 414 (1988), where genuine issues of material fact remained concerning whether the buyer's letter was a demand for ade......
-
Colonial Pacific Leasing Corp. v. J.W.C.J.R. Corp.
...5 Anderson § 2A-509:3, at 664.3 Whether a party has rejected goods is a question of fact. See, e.g., SPS Indus., Inc. v. Atlantic Steel Co., 186 Ga.App. 94, 366 S.E.2d 410, 414 (1988) ("Whether a buyer rejected goods within a 'reasonable time after their delivery' and seasonably notified th......
-
Counter v. Thione Int'l Inc.
...adequate assurance of due performance,” for a reasonable jury could have concluded it did not. See SPS Indus., Inc. v. Atl. Steel Co., 186 Ga.App. 94, 366 S.E.2d 410, 411, 413-14 (1988) (declining to rule that a letter demanding immediate information on a defective product constituted as a ......
-
Atwood-Kellogg, Inc. v. Nickeson Farms
...court noted that "`[t]his section requires the demand for assurances be in writing.'" Id. (quoting SPS Indus., Inc. v. Atlantic Steel Co., 186 Ga.App. 94, 366 S.E.2d 410, 413-14 (1988)). The court added "absent attenuating circumstances, this written demand is required before the demanding ......