St. Joe Minerals Corp. v. E.P.A.

Decision Date29 January 1975
Docket NumberNo. 72-1543,72-1543
Citation508 F.2d 743
Parties, 5 Envtl. L. Rep. 20,188 ST. JOE MINERALS CORPORATION, Petitioner, v. ENVIRONMENTAL PROTECTION AGENCY, Respondent.
CourtU.S. Court of Appeals — Third Circuit

David McNeil Olds, John McN. Cramer, Reed, Smith, Shaw & McClay, Pittsburgh, Pa., for petitioner.

Wallace H. Johnson, Asst. Atty Gen., Edmund B. Clark, Martin Green, John E. Varnum, Attys., Dept. of Justice, Washington, D.C., for respondent.

On petition for review of the order of the Administrator of the Environmental Protection Agency.

Before ALDISERT, ADAMS and HUNTER, Circuit Judges.

OPINION OF THE COURT

ADAMS, Circuit Judge.

The pivotal issue in this appeal is whether the Administrator of the Environmental Protection Agency is vested with the authority to disapprove a state implementation plan, or one of its provisions, drafted pursuant to the Clean Air Act Amendments of 1970, when the Administrator has found such plan to be 'technologically infeasible.'

I.

Under the Clean Air Act Amendments of 1970, the Administrator of the Environmental Protection Agency is directed to promulgate national primary 1 and secondary 2 ambient air quality standards for each air pollutant designated by the Administrator as having an adverse effect upon the public health or welfare. 3

The states are each required to develop an air pollution control scheme by which the national ambient air quality standards may be achieved within each state. The implementation plan of each state must then be submitted for the approval of the Administrator. 4

Upon approval by the Administrator, the implementation plan developed by each state may be enforced by the Administrator, as well as the state. Under federal law, fines and sentences of imprisonment may be imposed on those who refuse to comply with the plan. 5 In addition, violators are subject to enforcement suits by private individuals. 6

St. Joe Minerals Corporation operates a zinc-smelting plant at Monaca, Pennsylvania. These facilities emit sulfur oxides, which are the subject of ambient air quality standards established by the Administrator.

During December, 1971, the Common-wealth of Pennsylvania held four days of hearing focused on controlling sulfur oxide pollutants. The Commonwealth then submitted its implementation plan to the Administrator in January, 1972. The regulations published by the Administrator to assist the states in formulating their implementation plans included 'Examples of Emission-Limitations Attainable with Reasonably Available Technology.' 7 One of the examples was a standard for zinc smelters, such as that operated by St. Joe. The Pennsylvania implementation plan, however, which contained only one standard governing all existing sources of sulfur oxide emissions within the state, concededly was substantially more stringent, when applied to a smelter, than the Administrator's example. 8 Without conducting further hearings the Administrator in May, 1972, approved Pennsylvania's plan in part and disapproved it in part. 9

St. Joe filed with this Court a petition challenging the Administrator's approval of that portion of the Pennsylvania implementation plan relating to sulfur oxide emissions. 10 St. Joe alleged that the Administrator had not fulfilled certain procedural requirements, and asked that the case be remanded to the EPA. On January 22, 1973, this Court granted the motion for a remand without specifying the type of procedure to be followed by the EPA on the remand. The EPA moved for clarification of the order or for a rehearing. On the motion for clarification, after consideration of the record of the state proceedings, this Court stated that it was not convinced that St. Joe had been afforded 'a truly meaningful hearing' regarding the technological and economic feasibility of the Pennsylvania implementation plan. Moreover, the Court indicated that events since the state proceedings may have rendered the plan outdated. The EPA, therefore, was ordered either to grant St. Joe a limited hearing on the technological and economic feasibility of the plan or to suspend enforcement of the plan against St. Joe while the company pursued 'with due diligence' state administrative and judicial remedies for its infeasibility claims. 11

Pursuant to this Court's ruling, the EPA elected to conduct an administrative hearing on the feasibility of the plan. After considering written and oral presentations by St. Joe, the Commonwealth and the EPA staff, the Administrator, in a decision announced March 18, 1974, concluded that the Pennsylvania provisions relating to sulfur oxide emissions 'as applied to St. Joe Minerals Corporation's smelter . . . (are) technologically infeasible.' He therefore did not reach the question of economic feasibility. The Administrator, however, interpreted the Clean Air Act Amendments 'as precluding any disapproval of the plan on that basis.' He proposed instead to notify the Commonwealth of his finding of technological infeasibility and to request a revision. Furthermore, he proposed to stay federal enforcement of the plan pending state administrative and judicial review of the plan.

St, Joe petitioned this Court to review the Administrator's refusal to disapprove the plan, alleging that the Administrator's refusal was based on an erroneous construction of the law. 12

II.

St. Joe contends that where the state has not provided an adequate hearing on the issues of the technological and economic feasibility of an emission limitation in a state implementation plan and the limitation has not been demonstrated to be essential to the achievement of a primary or secondary ambient air quality standard, the Administrator must disapprove the limitation when he has found it to be technologically or economically infeasible. The Administrator, on the other hand, argues that if the criteria set forth in section 110(a)(2) 13 are satisfied, sections 110(a)(2) and 116 14 require him to approve a provision of an implementation plan even though he has found the provision to be technologically or economically infeasible and more restrictive than is necessary to attain national ambient air quality standards. According to the Administrator, to obtain a revision of the implementation plan so as to conform to that which is technologically and economically possible, St. Joe must resort to state administrative and judicial review. Furthermore, confining St. Joe to state review, the agency suggests, is not inappropriate since the Administrator has stayed federal enforcement of the provision in question.

III.

Although judicial review of the actions of administrative agencies is limited in scope, the Administrator's approval of the sulfur oxide provision of the Pennsylvania implementation plan cannot escape review by the Court of Appeals if the agency's decision is founded upon an incorrect conclusion of law. 15 Therefore, we must determine whether, under the circumstances here, sections 110 and 116 compel the Administrator to approve the provision of the Pennsylvania plan that he has found technologically infeasible.

There appears to be no opinion which squarely addresses the precise issue raised on this appeal. However, an interpretation of the Clean Air Act Amendments empowering the Administrator to disapprove the Pennsylvania plan if he finds it technologically unworkable is implicit in our decision in Duquesne Light. If the Administrator has no authority to disapprove such plan or provision, there would have been no cause to remand the case to the EPA so as to conduct a hearing on precisely this subject. Indeed, the agency argued in Duquesne Light, in urging a denial of the remand, that the statute had not intended the Administrator to consider economic and technological factors. Yet we ordered the remand.

The Court's earlier decision in Getty Oil Co. v. Ruckelshaus 16 is premised upon a similar reading of the duty of the Administrator under sections 110 and 116. In Getty Oil, Getty operated an oil refinery in Delaware and supplied fluid petroleum coke, a by-product, to Delmarva Power and Light Co., which operated a nearby power station. Delmarva, in turn, supplied electricity and steam to the refinery. As part of its implementation plan, Delaware imposed a limit on the sulfur content of fuels burned in the area in which the Delmarva station was located. This portion of the implementation plan was approved by the EPA, and neither Getty nor Delmarva sought judicial review. However, Getty subsequently asked the state to grant the power station a variance so as to delay the effective date of the sulfur restriction. The relevant state administrative agencies denied the variance, but when Getty sought review in the Delaware courts, it obtained an order restraining the state from enforcing the sulfur limitation.

While the state was so restrained, however, the EPA ordered Delmarva to comply with the implementation plan EPA had already approved. Getty asked this Court to review the compliance order. That ofder, Getty alleged, deprived Getty of due process because national primary air quality standards had already been met in the area without compliance, and because compliance, prior to the development of alternative technology, would therefore impose an unreasonable economic burden on Getty and Delmarva. Significantly, this Court held that Getty at that time was barred from obtaining judicial consideration of its claims of technological and economic infeasibility since Getty could have obtained such review at the time EPA approved the implementation plan. Section 307(b), 17 the Court reasoned, bars subsequent scrutiny of any claim that could have been reviewed by a court of appeals at the time of the Administrator's approval of the plan.

An essential underpinning of this Court's decision in Getty Oil was the conclusion that the Court could have considered technological and economic objections to the...

To continue reading

Request your trial
8 cases
  • PEOPLE OF STATE OF CAL., ETC. v. Dept. of Navy
    • United States
    • U.S. District Court — Northern District of California
    • April 12, 1977
    ...EPA standards promulgated under Section 109. Indiana & Michigan Electric Co. v. EPA, 509 F.2d 839 (7th Cir. 1975); St. Joe Minerals Corp. v. EPA, 508 F.2d 743 (3d Cir. 1975), vacated on other grounds, 425 U.S. 987, 96 S.Ct. 2196, 48 L.Ed.2d 812 Despite the states' broad power to implement s......
  • Marshall v. Consumers Power Co.
    • United States
    • Court of Appeal of Michigan — District of US
    • October 27, 1975
    ...plan. Indiana & Michigan Electric Co. v. Environmental Protection Agency, 509 F.2d 839 (CA7, 1975); St. Joe Minerals Corp. v. Environmental Protection Agency, 508 F.2d 743 (CA3, 1975). Both the WQIA and the Clean Air Act deal with interstate pollution. The fact that the Federal government h......
  • Bethlehem Steel Corp. v. U.S. E.P.A., 79-2502
    • United States
    • U.S. Court of Appeals — Third Circuit
    • June 8, 1981
    ...whether the EPA has correctly interpreted the statutory provision upon which it has based its decision. See St. Joe Minerals Corp. v. EPA, 508 F.2d 743, 746 (3d Cir. 1975), vacated as moot, 425 U.S. 987, 96 S.Ct. 2196, 48 L.Ed.2d 812 (1976). We must determine that the agency had statutory a......
  • Duquesne Light Co. v. E.P.A.
    • United States
    • U.S. Court of Appeals — Third Circuit
    • August 21, 1975
    ...1857f-1 et seq.6 42 U.S.C. § 1857c-5(a)(2). For a description of the process of EPA review, see St. Joe Minerals Corp. v. Environmental Protection Agency, 508 F.2d 743, 749 (3d Cir. 1975), Petition for cert. filed, 44 U.S.L.W. 3001 (July 8, 1975).7 St. Joe Minerals, 508 F.2d 743; Duquesne L......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT