Stanley v. Louisiana Pure Ice & Supply Co.
Decision Date | 08 December 1925 |
Docket Number | No. 18947.,18947. |
Parties | STANLEY v. LOUISIANA PURE ICE & SUPPLY CO. et al. |
Court | Missouri Court of Appeals |
Appeal from Circuit Court, Pike County; Edgar B. Woolfolk, Judge.
"Not to be officially published."
Action by Clarence Stanley against the Louisiana Pure Ice & Supply Company and another. Judgment for plaintiff, and defendants appeal. Affirmed.
May & May, of Louisiana, Mo., Hostetter & Haley, of Bowling Green, and Ras Pearson and A. J. Murphy, Jr., both of Louisiana, Mo., for appellants.
C. E. Rendlen, of Hannibal, W. F. Goodman and F. D. Wilkins, both of Louisiana, Mo., and Tom B. McGinnis, of Bowling Green, for respondent.
Plaintiff recovered judgment for $500 for personal injuries alleged to have been sustained by him by bricks from a wall which collapsed falling on him while he was digging a trench parallel with, adjacent to, and under, `said brick wall. Each of the defendants in due course appeals.
It appears that the Louisiana Pure Ice & Supply Company, one of the defendants herein (and hereinafter referred to as the Ice Company), was the owner of a certain brick building in Louisiana, Mo., wherein it operated a cold storage and ice manufacturing plant. It determined to build an addition to said brick building immediately adjoining it, and a trench was dug immediately adjoining the west wall of their said building for the foundation of the new addition. This trench was to be dug three feet deeper or lower than said west wall, and from underneath said wall to the bottom of the trench to an extent of six inches in width.
One Charles E. Goodman was employed by the defendant ice company to do the excavating or trench work on a basis of 65 cents per cubic yard. The plaintiff was employed directly by said Goodman as one of the laborers to do the actual digging. After Goodman had been working some time upon the excavation work, one Thomas J. Humphries, the other defendant in the case, became general contractor for the building of the new addition. Under the general contract entered into by said Humphries and the ice company, one Ralph Stuart was to be the supervising architect or inspector of the erection of the addition.
There is no dispute but that the west wall of the old building nearest to which the excavation or trench was being dug was not shouldered or shored up in any manner to prevent it from falling, nor was the excavation dug in sections and such sections filled in with stone or cement so as to give support to the wall while the next section of the trench was being dug. There seems to be no contention but that it was negligence to dig beneath the foundation for its entire length in the manner in which the digging of the trench was admittedly done, and it is conceded that the wall did fall and injure plaintiff while he was in the trench excavating underneath the foundation wall of the ice company's building.
It will be noted that Goodman, the direct employer of plaintiff, who was doing the general excavating work for the new addition, is not made one of the defendants herein, but that the action is directed solely against the owner of the building and the general contractor.
But one assignment of error is suggested here; namely, that the court erred in refusing each of the instructions in the nature of a demurrer to the evidence offered by the defendants.
In support of this contention it is urged that under the record the court should have declared as a matter of law that Goodman was an independent contractor for the doing of all of the excavating work, and that therefore neither the defendant ice company owner of the building and contractee for the excavation work, nor the defendant Humphries, general contractor (excepting for excavation work), are liable for an injury to plaintiff employé, suffered through the negligence of his employer, the independent contractor.
In considering this question, we have gone Over the record with painstaking care, and have come to the conclusion that the trial court could not have ruled as a matter of law that Goodman Was an independent contractor, but that the testimony adduced, bearing on this question, made it a question for the jury. The court therefore properly ruled said demurrers.
We set out so much of the testimony as we think sufficient to Support our ruling.
Charles E. Goodman, a witness for plaintiff, testified:
That one Eugene B. Rogers was manager of the defendant ice company; that Rogers came to him, and stated that the ice company intended to build an addition to their building, which new building would need some excavating; that he wanted the witness to do the excavating, and wanted' to know how much it was worth; that the witness did some figuring on the proposition, and concluded that "the excavation would be worth 65 cents per cubic yard"; that Rogers asked him how many yards of excavating there would be; that he, the witness, replied he did not know "how deep, how wide, or how long" the trenches would be; that Rogers replied that their architect had gone over the ground, and had figured the excavation at approximately 200 yards. The witness then told Rogers he would do the excavating for 65 cents per cubic yard, and Rogers stated "he would take care of what was under the building."
According to this witness, they completed digging the trench alongside the west wall foundation, excepting for the digging a the earth from underneath the foundation, on March 3d. The witness stated:
That before he began digging under the wall he said to Humphries, the general contractor, that he "didn't think it looked good" to him; that Humphries said it was all right; that the building would hold; that Humphries thereupon got a spud, "but it was dull, and he told me to take it to the blacksmith shop, and have it sharpened, and I did, and when I got back we began spudding under there, and Mr. Humphries did the first spudding, and then I took the spud and spudded after he showed me how he wanted it.
We quote the following from the cross-examination of this witness:
To continue reading
Request your trial-
Mallory v. Louisiana Pure Ice & Supply Co.
...Mo.App. 69; Whittaker v. Railroad, 252 Mo. 452. (2) In a companion case on same accident, both appellants were held liable. Stanley v. Louisiana Ice Co., 279 S.W. 157. (3) Goodman was not an independent contractor. (a) The Company and Humphries retained general control of the premises, they......
-
Mallory v. Ice & Supply Co.
...v. Railroad, 252 Mo. 452. (2) In a companion case on same accident, both appellants were held liable. Stanley v. Louisiana Ice Co., 279 S.W. 157. (3) Goodman was not an independent contractor. (a) The Ice Company and Humphries retained general control of the premises, they had power to and ......
-
Martin v. First Nat. of Independence Co.
...Jackson v. Butler, 249 Mo. 342, 155 S.W. 1071, 1078; Crenshaw v. Ullman, 113 Mo. 633, 20 S.W. 1077, 1078; Stanley v. Louisiana Pure Ice & Supply Co., Mo.App., 279 S.W. 157, 160. Ordinarily the owner of premises is not required to inspect the work of an independent contractor to determine wh......
-
Harvey v. Blue Oak Handle Co.
... ... Louisiana, Mo., for appellant ... Hostetter & Haley, of Bowling ... ...