State ex rel. Dept. of Natural Resources v. Walworth County Bd. of Adjustment
| Decision Date | 15 July 1992 |
| Docket Number | No. 92-0170,92-0170 |
| Citation | State ex rel. Dept. of Natural Resources v. Walworth County Bd. of Adjustment, 489 N.W.2d 631, 170 Wis.2d 406 (Wis. App. 1992) |
| Parties | STATE of Wisconsin ex rel. DEPARTMENT OF NATURAL RESOURCES, and Town of Richmond, Petitioners-Respondents, v. WALWORTH COUNTY BOARD OF ADJUSTMENT, Respondent-Respondent, Linda M. Friedman, Intervenor-Appellant. |
| Court | Wisconsin Court of Appeals |
On behalf of the intervenor-appellant, the cause was submitted on the briefs of David C. Williams of Allen, Harrison, Williams, McDonell & Swatek of Lake Geneva.
On behalf of the petitioners-respondents, State of Wis., the cause was submitted on the brief of James E. Doyle, Atty. Gen., and Lorraine C. Stoltzfus, Asst. Atty. Gen.
On behalf of the petitioners-respondents, Town of Richmond, the cause was submitted on the brief of David J. Nommensen of Seymour, Kremer, Nommensen & Morrissy of Elkhorn.
On behalf of the respondent-respondent, Walworth County Board of Adjustment, the cause was submitted on the brief of Dianne M. Soffa, Asst. Corp.Counsel.
Before BROWN, ANDERSON and SNYDER, JJ.
This is another case in which a landowner and the DNR do battle over the state's shoreland zoning policies.Here, the landowner contends that the DNR has no standing under our statutes to appeal local board of adjustment decisions, and that even if the DNR does have standing, it did not correctly follow the statute in initiating its appeal.Because the DNR is a "trustee" of the navigational waters of this state, it is a "person aggrieved" and has standing to appeal; further, the DNR correctly followed the statute in initiating its appeal.We affirm as to the DNR.The town of Richmond, however, did not follow the statutes; so we reverse as to it.
The landowner is Linda Friedman.She owns the Snug Harbor campground on Turtle Lake.Development and use of the land in this area is regulated by the Walworth County Shoreland Zoning Ordinance.In 1967, the circuit court declared the campground a legal, nonconforming use under the ordinance.In 1990, Friedman decided to make major changes to the campground, including removal of existing cottages and the building of new ones.The zoning administrator for the county determined that while Friedman needed to obtain the usual sewer, erosion control, and building permits, she did not need a zoning permit for development of the campground because the 1967 judgment was still in effect, and the county could not restrict the area without a further court order amending the previous judgment.
The DNR and the town of Richmond appealed the zoning administrator's decision to the Walworth County Board of Adjustment, arguing that Friedman's plans for the campground constituted an extension, enlargement or substitution of a nonconforming use.The board upheld the zoning administrator.The DNR and the town then sought certiorari review in the circuit court.The court reversed the board and ordered the board to require Friedman to file an application for a Certificate of Compliance if she wanted to continue with her plans for the campground.Friedman appeals.1
We initially address the standing issue.Section 59.99(4), Stats., provides that appeals of zoning decisions may be taken "by any person aggrieved or by any officer, department, board or bureau of the municipality affected by any decision of the ... administrative officer."Friedman argues that the DNR lacks standing because it is not a "person aggrieved" or a municipal officer, department, board or bureau.
Friedman further contends that sec. 59.971, Stats., permits the DNR to require a county to adopt a shoreland zoning ordinance but it provides for the county board of adjustment to handle variances and appeals regarding the shorelands.She also argues that according to Just v. Marinette County, 56 Wis.2d 7, 18, 201 N.W.2d 761, 769(1972), when the state required counties to pass shoreland zoning ordinances, the state thereby delegated authority over the navigable waters of the state to the counties.Friedman concludes that the statutory framework was designed such that the boards of adjustment are the final arbiters of shoreland zoning policy, not the DNR.
We conclude that the DNR does have standing to appeal zoning decisions regarding shorelands.The DNR is a "person aggrieved" by a county decision affecting shorelands because it is a trustee of the navigable waters of the state.Our supreme court has recognized that the state has standing to appeal decisions which violate the public trust.State v. Deetz, 66 Wis.2d 1, 13, 224 N.W.2d 407, 413(1974).Moreover, according to Just, the DNR has a duty to appeal decisions which do not comply with shoreland zoning requirements.Just, 56 Wis.2d at 18, 201 N.W.2d at 768.Additionally, both our supreme court and this court have implicitly granted standing to the DNR to appeal county zoning decisions.SeeState v. Trudeau, 139 Wis.2d 91, 94-95, 408 N.W.2d 337, 339(1987), cert. denied, 484 U.S. 1007, 108 S.Ct. 701, 98 L.Ed.2d 652(1988);State v. Ozaukee Bd. of Adjustment, 152 Wis.2d 552, 564, 449 N.W.2d 47, 52(Ct.App.1989).
This policy is borne out by our state administrative rules.SeeWis.Adm.Code sec. NR 115.06(4).Administrative rules have the force and effect of law.Law Enforcement Standards Bd. v. Lyndon Station, 101 Wis.2d 472, 488, 305 N.W.2d 89, 97(1981).The state's administrative code gives the DNR the responsibility of monitoring the administration and enforcement of shoreland zoning ordinances and the authority to appeal actions of county zoning officials or county boards of adjustment.Wis.Adm. Code sec.NR 115.06(4).We hold that the DNR has standing.
Regarding the issue of whether the DNR and the town's initial appeals to the board of adjustment were timely, Friedman contends that actual verbal notice of the zoning administrator's decision occurred in November 1990 and that this notice, rather than the written notice in December 1990, controls whether the DNR's and the town's appeals were timely filed in January 1991.She points to State ex rel. Brookside Poultry Farms v. Jefferson County Bd. of Adjustment, 131 Wis.2d 101, 117-18, 388 N.W.2d 593, 599(1986), where our supreme court concluded that because aggrieved residents received no written notice of the issuance of a building permit, the beginning of the building's construction constituted notice and started the clock running on the right to appeal.Here, Friedman argues that the DNR and the town received notice of the zoning administrator's decision in November because they were told that an erosion control permit and a plumbing permit had been issued by the county.She contends, therefore, that the clock must start running on the right to appeal from the date of that notice.
Friedman reads Brookside wrongly.The court in that case was faced with a situation where a county failed to promulgate rules for zoning appeals as required by sec. 59.99(4), Stats.The supreme court was concerned that without such rules, access to judicial review would be hampered.Indeed, the court noted that the aggrieved residents had not received written notice of the zoning administrator's issuance of a building permit.Brookside, 131 Wis.2d at 114, 388 N.W.2d at 598.Noting that sec. 59.99(4) mandates a "reasonable" time to appeal, the supreme court was troubled by the fact that absent notice of the decision, there was no way to determine a "reasonable time" to appeal.Brookside, 131 Wis.2d at 113, 388 N.W.2d at 597-98.Rather than allow this absurd result, the court looked to the time when the residents first found out about the building permit, fashioned a constructive notice remedy to start the appeal time running from that date, and thereby resolved the case.
Here, we do not have the same facts.In this case, the time for appealing the zoning administrator's decision is clearly specified in sec. 10.5, Walworth County Shoreline Zoning Ordinance.That ordinance states: "[A]ppeals shall be filed ... within (30) days after the date of written notice of the decision or order of the zoning administrator."Id.(emphasis added).A written decision was issued by the zoning administrator in this case.The appeal was filed based upon that written notice.
We read Brookside to say that the appeal time begins on one of two dates.If there is a provision in the ordinance for notice, then the clock begins to run at the time the notice is given.If no such provision exists, then the clock begins to run when the aggrieved parties find out about the decision.This rule is designed to expand access to judicial review rather than to limit it.
Even if the law were as Friedman suggests--that notice is either by actual verbal notice or by written decision, whichever comes first--we would not accept the facts relied upon by Friedman to argue that actual verbal notice of the zoning administrator's decision was given in November 1990.First, the permits relied upon for constructive notice were not issued by the zoning administrator.They were an erosion control permit and a plumbing permit, and thus were not part of the decision of the zoning administrator sufficient to start the clock running for constructive notice purposes.Second, the facts cited by Friedman are taken from affidavits in the motion to dismiss, not from the record of the proceedings as is required for certiorari review.
We conclude that the appeal time started running only when the zoning administrator issued a written decision on December 27, 1990.When the DNR's and the town's appeals were filed with the board of adjustment on January 25, 1991, they were timely.
Friedman's final argument concerns the proper statutory procedure for certiorari appeals to the circuit court.She cites sec. 801.02(5), Stats., as a prelude to her argument, which we repeat here:
An action seeking a remedy available by certiorari ... may be commenced under sub. (1), by service of an appropriate...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Nowell v. City of Wausau
...process specified in sec. 801.02(1) for the commencement of all civil actions.” State ex rel. Dep't of Natural Resources v. Walworth Cnty. Bd. of Adjustment, 170 Wis.2d 406, 415, 489 N.W.2d 631 (Ct.App.1992) (citing Tobler v. Door Cnty., 158 Wis.2d 19, 23, 461 N.W.2d 775 (1990)). Thus, cont......
-
Koenig v. Pierce Cnty. Dep't of Human Servs.
...§ 801.02(5) within thirty days of the panel's decision is also supported by our decision in State ex rel. DNR v. Walworth County Board of Adjustment, 170 Wis.2d 406, 489 N.W.2d 631 (Ct.App.1992). There, we described § 801.02(5) as setting forth two procedures for initiating a certiorari act......
-
State ex rel. Kurtzweil v. Sawyer Cnty. Zoning Bd. of Appeals
...¶24 The Board argues that we incorrectly stated that there were only two procedures in State ex rel. DNR v. Walworth County Board of Adjustment , 170 Wis. 2d 406, 489 N.W.2d 631 (Ct. App. 1992). In that case, we stated that the appellant "correctly observes that there are two different proc......
-
Burnett v. Hill
...and complaint is not made within 60 days after filing. Id. at 533-34, 481 N.W.2d 629; see also DNR v. Walworth County Bd. of Adjustment, 170 Wis.2d 406, 417-18, 489 N.W.2d 631 (Ct.App.1992). Further, we held that compliance with the statute, and not "substantial compliance," is the proper t......