State for Use and Ben. of Pegan v. American Sur. Co. of New York
Decision Date | 22 September 1931 |
Citation | 137 Or. 394,2 P.2d 1116 |
Parties | STATE, for Use of PEGAN et al., v. AMERICAN SURETY CO. OF NEW YORK et al. |
Court | Oregon Supreme Court |
Department 2.
Appeal from Circuit Court, Multnomah County; Louis P. Hewitt, Judge.
On defendant appellants' petition for rehearing.
Petition denied.
For original opinion, see 300 P. 511.
Plowden Stott and Collier, Collier & Bernard, all of Portland, William Smith, of Baker, and P.J. Gallagher, of Portland, for appellants.
George F. Alexander and Bartlett Cole, both of Portland, for respondents.
The defendants have petitioned this court for a rehearing. For a full statement of the issues of fact and law, see our original opinion decided June 23, 1931, and reported in 300 P. 511.
By their petition the defendants assert that this court erred in holding that the plaintiffs' complaint stated facts sufficient to constitute a cause of action, for the alleged reason that it failed to aver or prove a consideration for the modification of the contract sued upon and that the plaintiffs abandoned their contract.
On the other hand, the plaintiffs contend that the contract was not abandoned by them, but that they entered upon the performance thereof and proceeded therewith until all the work to be performed thereunder was completed, except a few odds and ends which could not be completed at that time because the defendant construction company had not completed the grading. As to the particular work that remained unfinished, we note the following testimony of plaintiff Pegan:
Witness further testified that Sweeney agreed to complete the unfinished subcontract and charge the plaintiffs "what it cost to do the work," and give them credit therefor.
As stated in our original opinion, the trial court found that there had been no abandonment by the plaintiffs of their contract with the defendant construction company. The plaintiffs alleged, and the court found, in substance, that after the execution of the contract between the plaintiffs and defendant Sweeney Construction Company, the plaintiffs entered upon the performance thereof and proceeded therewith in accordance with all its terms and duly performed all the conditions thereof until on or about November 17, 1926, when all the work to be performed under the contract was completed except putting in two or three pipe culverts and a few odds and ends which could not be done or completed until several weeks or months thereafter, whereupon it was mutually agreed between the plaintiffs and defendant Sweeney Construction Company that the construction company would, and it thereafter did, complete it and charge them for the expense and give them credit for the work to be done and performed by...
To continue reading
Request your trial-
Martin v. First Nat. Bank of Hattiesbubg
... ... Gibson, 72 Miss ... 58, 17 So. 13; American Fire Ins. Co. v. First Nat'l ... Bank, 73 Miss ... Land Co., 132 So. 904; Smith v. State Industrial ... Accident Com., 23 P.2d 904, 25 ... ...
-
Idaho Gold Dredging Corporation v. Boise Payette Lumber Company
... ... the State of Idaho from so much of the judgment so made and ... (See Scholtz ... v. American Surety Co. , 35 Idaho 207, 206 P. 187.)" ... ...
-
Unitec Corporation v. Beatty Safway Scaffold Co. of Oregon, 19788.
...for each party foregoes rights against the other. State v. American Surety Co., 137 Or. 394, 300 P. 511, rehearing denied, 2 P.2d 1116 (1931); Restatement, Contracts ¶ 406, comment a (1932). The United States Supreme Court succinctly disposed of a contention similar to that raised by Unitec......
-
Hines v. Ward Baking Co.
...this are Romaine v. Beacon Lithographic Co., 13 Misc. 122, 34 N.Y.S. 124; State v. American Surety Co., 137 Or. 394, 300 P. 511, 2 P.2d 1116; Julian v. Gold, 214 Cal. 74, 3 P.2d 1009, 1010; Nordfors v. Knight et ux., 90 Utah 114, 60 P.2d 1115; Price v. Price, 24 Cal.App.2d 462, 75 P.2d 655;......