State Group Indus. v. Murphy & Assoc. Indu.

Decision Date28 December 2007
Docket NumberNo. 82A04-0703-CV-158.,82A04-0703-CV-158.
Citation878 N.E.2d 475
PartiesTHE STATE GROUP INDUSTRIAL (USA) LIMITED, Appellants-Plaintiffs, v. MURPHY & ASSOCIATES INDUSTRIAL SERVICES, INC., Appellees-Defendants.
CourtIndiana Appellate Court

Reed S. Schmitt, Frick Powell Whinrey Cravens & Schmitt, LLP, Evansville, IN, Attorney for Appellant.

Marilyn R. Ratliff, Evansville, IN, Attorney for Appellee.

OPINION

ROBB, Judge.

Case Summary and Issues

The State Group Industrial (USA) Limited ("State Group") appeals from the trial court's judgment awarding State Group actual damages but denying State Group's request for relief under Indiana Code section 34-24-3-1. State Group raises the sole issue of whether the trial court improperly denied it relief under this statute based on a contract provision. Concluding the Contract does not proscribe the relief sought by State Group, we remand with instructions that the trial court determine whether and to what extent damages under this statute are warranted.

Facts and Procedural History

State Group is a Delaware corporation authorized to transact business in Indiana, with its principal place of business in Evansville. Murphy & Associates ("M & A") is an Indiana corporation with a principal place of business in Evansville. In 2000, the Army Corps of Engineers (the "Corps") sought bids for a project based on the Sabine-Neches Waterway in Beaumont, Texas (the "Project"). The Project involved a control system, which would identify the salinity content of the water in the Sabine-Neches and relay the data to a control panel, which would in turn process the data and determine whether the tainter gates on the waterway's dam should be opened or closed to regulate salt water infiltration.

State Group was a prime contractor on the Project. In June 2000 M & A requested information from State Group relating to the Project and prepared an estimate for supplying materials for the control system. Jeff Erk and Steve Murphy prepared M & A's estimate, which came to $394,773. On August 9, 2000, Erk prepared a bill of materials, which listed all the materials that M & A would provide. Included in this list were Falmouth Scientific salinity probes, necessary components of the control system. On March 21, 2001, Murphy met with State Group employees to finalize the terms and conditions of the contract between M & A and State Group (the "Contract"). At this meeting, M & A confirmed that the salinity probes were part of the Contract, that M & A would provide engineering for the start-up process, and that M & A had prior experience with Corps projects.

The Contract's payment schedule was as follows:

                1.1 Due Upon Contract Award ............... $ 20,000.00
                1.2 Due Upon Approval of Submittal Drawings
                & Documentation ........................... $  5,000.00
                1.3 Due Upon Receipt of Equipment at
                M & A ..................................... $336,895.00
                1.4 Due After Customer Acceptance/Witness
                Testing at M & A .......................... $ 20,002.00
                1.5 Due Upon Equipment Delivery/Shipment
                to Customer ............................... $  3,250.00
                1.6 Due Upon Completion of Installation &amp
                Testing ................................... $ 15,345.00
                1.7 Due Upon Receipt of Final Deliverables  $    945.00
                TOTAL ..................................... $401,437.00
                

Appellant's Appendix. at 35.

On October 15, 2001, M & A submitted Invoice No. 965, which was prepared by Murphy, for payment number 1.3. Invoice No. 965 indicated that the terms of the Contract required that State Group was required to make payment number 1.2 "Upon Submittal of Drawings and Documentation," instead of upon approval of these documents. Id. at 144 (emphasis added). Invoice No. 965 also indicated that payment number 1.3 was "Due Upon Submittal Approval/M & A Ordering Equipment," instead of upon receipt of the equipment. Id. (emphasis added). M & A had not discussed a change in payment terms with State Group. Also, at the time M & A delivered this invoice, it had not ordered or acquired any of the materials for the control system.

After receiving this invoice, State Group contacted M & A and requested proof of ownership of the materials, as the Corps required such proof before it would release payment. In response, M & A supplied State Group with documentation representing that it had paid in full for the materials, and that no other party had any claim on the materials. These representations were false. The trial court found that Murphy knew or should have known these representations were false and that he "made misleading written statements with the apparent intent to receive payment from the Corps." Id. at 149.

On January 30, 2002, Murphy sent a letter to State Group indicating that payment on Invoice No. 965 was 107 days past due, at which time Murphy "knew or should have known that such representation was false and that according to the contract terms Invoice No. 965 was not due and payable until 60 days after the materials had been received at [M & A]." Id. Over the next few months, State Group made payments to M & A, making the final payment on May 6, 2002. M & A did not make its first payment to its supplier until three days after it received this final payment.

On August 19, 2002, M & A shipped materials to Beaumont. This shipment did not include the salinity probes and necessary cabling. On October 28, 2002, State Group forwarded a letter to M & A informing it of the missing equipment. On November 11, 2002, State Group sent another such letter. On December 18, 2002, State Group's General Manager, Steve Theodoru, met with Murphy to discuss the missing materials. Theodoru stated that he would be willing to discuss with the Corps the possibility of M & A receiving payment from the Corps on a "compassionate basis." Id. at 154. Following discussions, the Corps indicated that it was not inclined to provide such relief.

On January 18, 2003, State Group notified M & A that State Group needed to review the software programming developed by M & A. On February 12, 2003, State Group provided M & A with a forty-eight-hour deficiency notice requesting supply of the salinity probes and cabling. M & A failed to supply the materials, and State Group was forced to hire a replacement subcontractor, KAPOS Machine Control. Additionally, M & A refused to provide the necessary software and start-up procedures, stating that it would begin these procedures after money it claimed State Group owed in relation to alleged finance charges and labor cost increases was placed in escrow. At this point, M & A also took the position that the salinity probes were not part of the Contract. State Group purchased the missing materials from KAPOS, and incurred additional on-site expenses resulting from M & A's breach.

On April 2, 2003, M & A filed a complaint against State Group alleging breach of contract. On May 8, 2003, M & A filed its amended complaint. On May 8, 2003, State Group filed its response, affirmative defenses, and counterclaim alleging that M & A breached the Contract. On July 26, 2005, State Group filed its amended counterclaim, apparently adding a claim of fraud and seeking damages under Indiana Code section 34-24-3-1 (the "Crime Victims Statute").1 The trial court held a bench trial over five days in January 2006, and issued its judgment, along with findings of fact and conclusions of law, on July 28, 2006.

The trial court concluded that M & A breached the Contract by failing to supply the salinity probes and cabling. The trial court also concluded that M & A knowingly made numerous false or misleading statements or representations. The trial court awarded State Group actual damages in the amount of $141,943.22. However, the trial court refused to award State Group attorney's fees, pre-judgment interest, or any other damages outside of the direct expenses caused by M & A's breach. The basis for the trial court denying State Group these damages was its conclusion that "[t]he Contract entered into between the parties does not provide for reimbursement of legal fees in the event that [M & A] is found to be in breach. The Contract also limits [M & A's] liability to actual damages and excludes loss of profits, special, consequential or exemplary damages." Id. at 163. State Group now appeals, arguing that the trial court should have awarded it additional damages despite this Contract provision.

Discussion and Decision2

In this case, the trial court entered findings of fact and conclusions of law along with its judgment. In such situations, we generally apply a two-tiered standard of review, first determining whether the evidence supports the findings, and then determining whether the findings support the judgment. See Yanoff v. Muncy, 688 N.E.2d 1259, 1262 (Ind.1997). However, no challenge has been raised as to the propriety of any factual finding, and the only issue raised on this appeal — whether the Contract proscribes relief under the Crime Victims Statute — is a question of law that we will review de novo. See State Farm Mut. Auto. Ins. Co. v. Cox, 873 N.E.2d 124, 127 (Ind.Ct.App. 2007) (noting that where there are no disputed facts, and the sole issue involves the interpretation of a contract, this court will review the matter de novo).

Under the Crime Victims Statute, "[i]f a person suffers a pecuniary loss as a result of a violation of IC 35-43 ... the person may bring a civil action against the person who caused the loss for" treble damages, the costs of the action, and reasonable attorney's fees. The trial court concluded that M & A violated Indiana Code section 35-43-5-3, deception, by knowingly and intentionally making false or misleading statements with the intent to obtain payment from State Group.3 Neither a criminal conviction nor proof beyond a reasonable doubt is required to trigger the Crime Victims Statute. Gilliana v. Paniaguas, 708 N.E.2d 895, 899 (Ind.Ct. App.1999), trans. denied. Therefore, the trial court's conclusion, which was supported...

To continue reading

Request your trial
15 cases
  • Perrine v. E.I. Du Pont De Nemours And Co.
    • United States
    • West Virginia Supreme Court
    • 26 Marzo 2010
    ...597, 533 N.E.2d 941, 127 Ill.Dec. 859 (1989) (pre-injury release in training agreement); State Group Indus. (USA) Ltd. v. Murphy & Assocs. Indus. Servs., Inc., 878 N.E.2d 475 (Ind.Ct.App.2007) (pre-injury contract provision exempting a party from Adloo v. H.T. Brown Real Estate, Inc., 344 M......
  • Bank of Am., N.A. v. Cartwright
    • United States
    • U.S. District Court — Northern District of Indiana
    • 1 Settembre 2021
    ...2013). This claim cannot be predicated on a contract breach, only an independent tort. State Group Industrial (USA) Ltd. v. Murphy & Assocs. Indus. Servs., Inc. , 878 N.E.2d 475, 480 (Ind. Ct. App. 2007).Statutory deception occurs when a person either "knowingly or intentionally makes a fal......
  • Dixon v. Nat'l Hot Rod Ass'n
    • United States
    • U.S. District Court — Southern District of Indiana
    • 30 Marzo 2020
    ...and economic duress is a violation of public policy. In support, Plaintiffs cite State Group Industry (USA) Ltd. v. Murphy & Associates Industry Services, Inc. , 878 N.E.2d 475 (Ind. Ct. App. 2007), which held that a limitation of remedies clause "lack[ed] the requisite specificity to prote......
  • Bank of Am. v. Cartwright
    • United States
    • U.S. District Court — Northern District of Indiana
    • 1 Settembre 2021
    ... ... true, to state a plausible claim, not a speculative one ... , Sloan Valve Co. v. Zurn Indus., ... Inc. , 712 F.Supp.2d 743, 750 (N.D ... State Group ... Industrial (USA) Ltd. v. Murphy & ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT