Studer v. Rasmussen, 2853
Citation | 344 P.2d 990,80 Wyo. 465 |
Decision Date | 20 October 1959 |
Docket Number | No. 2853,2853 |
Parties | R. J. STUDER, d/b/a Studer Construction Company, and Studer Construction Company, a foreign corporation, Appellants (Defendants below), v. Willard N. RASMUSSEN and Clifford E. Rasmussen, d/b/a Rasmussen Brothers, a Co-partnership, Appellees (Plaintiffs below). |
Court | United States State Supreme Court of Wyoming |
Henry A. Burgess and Bruce P. Badley, Sheridan, for appellants.
Holstedt & Schwartz, Sheridan, oral argument by Robert E. Holstedt and Harry F. Schwartz, Sheridan, for appellees.
Before BLUME, C. J., PARKER, J., and PEARSON, D. J.
This is an action brought by Willard N. Rasmussen and Clifford E. Rasmussen against R. J. Studer, doing business as Studer Construction Company, to recover an amount due on a subcontract and for damages for delay in connection therewith. Subsequently the Studer Construction Company was added as a defendant.
The defendants had a contract with the United States Government for constructing water and sewer systems, paved roads and electrical distributing system at the Glasgow Air Force Base near Glasgow, Valley County, Montana. Part of this work relating to the construction of roads was subcontracted by the defendants to the plaintiffs in this case. Under that contract the subcontractors agreed to furnish all labor, materials, equipment and supplies, and to perform all work as described below. It was agreed that the work, labor and materials to be done, performed or furnished by the subcontractors were as follows:
The contractor agreed to pay the subcontractors for performance of the subcontract as follows:
"Unit Price Estimated Amount ---------- ---------------- "Item No. 7. 3,760 C.Y. $ 1.40 $ 5,264.00 "Item No. 8. 30,300 C.Y. 1.00 30,300.00 "Item No. 10. 1,670 Ton 2.00 3,340.00"
It might be mentioned that many months after the times hereinafter stated Item No. 10 was eliminated from the work to be performed on behalf of the Government of the United States but the government agreed to pay and did pay the defendants for 387 tons of mineral aggregate under Item 10 already produced at that time and the defendants herein used 194 tons and 91 tons of this aggregate and agreed to pay the plaintiffs for that at the rate of $3 per ton.
The contract provided that the subcontractors should be bound by the general conditions of the contract between the government and the contractor.
This action was brought on May 15, 1957, in the District Court of Sheridan County. In the first cause of action the plaintiffs claimed judgment for $2,818.04 and interest. This included the sum of $1,000 still due under items 7 and 8, the amount paid by the government for the 387 tons of mineral aggregate, the amount due for the mineral aggregate used by the defendants themselves and also the sum of $389.04 for a bond furnished by the plaintiffs in accordance with the agreement between the parties.
In the second cause of action plaintiffs claimed damages for delaying the plaintiffs in the performance of their contract for a period from July 15, 1955, to September 15, 1955, and also further damages by reason of the fact that they had to perform the contract in cold weather and were delayed in the work by reason thereof.
The court rendered judgment for the plaintiffs on the first cause of action as claimed by the plaintiffs and on the second cause of action found the following facts:
equipment allocated, moved to and used upon said job was $200,000.00.
Judgment for the plaintiffs accordingly was entered upon the first cause of action in the sum of $2,818.24 and judgment for $15,241.48 on the second cause of action. The court disallowed any damages by reason of the delay claimed by the plaintiffs due to cold weather conditions.
From this judgment the defendants have appealed to this court.
The letter mentioned by the court written by R. J. Studer to the Rasmussens is as follows:
'Rasmussen Brothers:
'Hope that you can make plans to move up by the end of this week, or by the 11th of July at the latest.
'Studer Construction Co.
'by /s/ R. J. Studer
'R. J. Studer'
The writing of this letter and the receipt thereof by the Rasmussens is not disputed herein.
The work to be done by the plaintiffs and appellees, as explained by the evidence herein, was to do some stripping of the top soil, brush and timber of the gravel strata in preparation for removal of gravel for processing, to produce gravel and place it on the roads and streets in accordance with the contract requirements and also to level the streets. In order for the plaintiffs to do this, it was necessary for the defendants to complete the utility work under the contract with the Government of the United States consisting of sewer lines and water lines. The Glasgow Air Force Base was laid out in blocks, with streets laid out at the sides. The water and sewer lines were not to be placed under but along the sides of the streets. But these lines crossed the streets at various places, and until the lines were so laid across, there were only short segments between the crossings which were too short for the operation of the machinery used by plaintiffs in placing the gravel on the streets and leveling them. In accordance with the letter above set out, plaintiffs, appellees, arrived at the Air Force base on July 13, 1955, but found that the water and sewer lines had not been laid by the defendants as required so as to enable them to place any gravel on the lines laid out for roads and streets. They did some stripping commencing about July 21 and July 28, 1955, but according to the testimony of Willard N. Rasmussen, this work was of no benefit in connection with the performance of the contract in that stripping should be done at the same time when the gravel is produced, but he employed some of his laborers in stripping so as to keep them away from the saloons.
There is some testimony in the case with reference to some gravel production being done in the...
To continue reading
Request your trial-
A. A. Baxter Corp. v. Colt Industries, Inc.
...Distributors' 'Compilation of Rental Rates,' where the loss of full rental value was the proper measure of damages. (Studer v. Rasmussen, 80 Wyo. 465, 344 P.2d 990.) When the leasing of the scale was under discussion no mention was made of standby rates that State might by contract be oblig......
-
Albrecht v. Zwaanshoek Holding En Financiering, B.V.
...And: "If there is an express contract in connection with the damages, that contract, of course, must govern." Studer v. Rasmussen, 80 Wyo. 465, 344 P.2d 990, 998 (1959). We have also recognized [T]he supreme court will not rewrite clear contracts. Nor will this court rewrite contracts under......
-
Zanetti Bus Lines, Inc. v. Hurd, 7151
...the issue of liability only. Satter v. Turner, 251 Minn. 1, 86 N.W.2d 85, 66 A.L.R.2d 1178; Anno. 34 A.L.R. 2d 988. Cf. Studer v. Rasmussen, 80 Wyo. 465, 344 P.2d 990. 28 U.S.C. § 2106 gives broad powers to Federal courts of appellate jurisdiction to affirm, modify, vacate, set aside, or re......
-
Lichter v. Mellon-Stuart Company
...sue for damages, but he may proceed to complete the work and then claim damages. Sheehan v. City of Pittsburg, supra; Studer v. Rasmussen, 80 Wyo. 465, 344 P.2d 990, 998; Williston on Contracts, vol. 3, rev. ed., § 704, at page 2027; Corbin on Contracts, vol. 3A, 1960 ed., § 755, at page 50......