Summit Saugatuck, LLC v. Water Pollution Control Auth. of the Town of Westport

Decision Date29 October 2019
Docket NumberAC 41949
Citation220 A.3d 183,193 Conn.App. 823
CourtConnecticut Court of Appeals
Parties SUMMIT SAUGATUCK, LLC v. WATER POLLUTION CONTROL AUTHORITY OF the TOWN OF WESTPORT

Peter V. Gelderman, Westport, for the appellant (defendant).

Timothy S. Hollister, Hartford, for the appellee (plaintiff).

Prescott, Bright and Bear, Js.

PRESCOTT, J.

The defendant, the Water Pollution Control Authority for the Town of Westport, appeals from the judgment of the trial court sustaining the appeal of the plaintiff, Summit Saugatuck, LLC, from the defendant's decision to deny the plaintiff's application for a sewer extension to service a proposed affordable housing development. The court remanded the matter back to the defendant with direction to approve conditionally the sewer extension application subject to the completion of ongoing improvements and upgrades of capacity to the sanitary sewer system in the town of Westport (town). On appeal, the defendant claims that the trial court, by sustaining the appeal and ordering a conditional approval of the application, improperly substituted its own judgment for the reasoned and lawful discretion exercised by the defendant. We agree and, accordingly, reverse the judgment of the trial court.1

The record reveals the following facts and procedural history. The plaintiff owns property or options to purchase property in an area of town that is zoned for high density development to be served by the town's sewer system. The plaintiff seeks to develop its property for multifamily residential use. A sewer extension from the town's system is needed to service the planned development.

In October, 2014, the plaintiff, pursuant to General Statutes § 7-246a,2 applied to the defendant for approval of a private sewer extension for a proposed 186 unit affordable housing development.3 Because a proposed sewer extension is deemed a municipal improvement, the defendant referred the application to the town's planning and zoning commission (zoning commission) for a report pursuant to General Statutes § 8-24. See footnote 1 of this opinion.

On January 8, 2015, the zoning commission held a hearing on the plaintiff's application. Steven Edwards, the town's public works director at the time, testified at the hearing that the town's existing sewer system required repairs and upgrades before it could handle the additional sewage from the proposed development. Specifically, Edwards explained that replacement of a force main running under the Saugatuck River and one of the pump stations could take up to five years.

Edwards thought a reasonable goal for the completion of the upgrade/repairs would be the summer of 2017.

The zoning commission issued a negative report on January 26, 2015. The plaintiff elected to withdraw its application with the defendant at that time.

The plaintiff subsequently entered into an agreement with an affiliate of the Westport Housing Authority (affiliate) pursuant to which the plaintiff would develop eighty-five market rate units and the affiliate would develop seventy adjacent affordable housing units. On April 11, 2016, the plaintiff reapplied to the defendant to construct a private sewer extension to service this new planned development.

In June, 2016, the defendant referred the plaintiff's latest application to the zoning commission for a § 8-24 report. Following a hearing on July 7, 2016, the zoning commission again issued a negative report due to the as yet incomplete upgrades to the sewer system, which it concluded were not likely to be accomplished for another two to four years.4 Despite the negative report, the plaintiff chose not to withdraw its application from consideration by the defendant. The defendant then held a public hearing on the plaintiff's sewer extension application on July 21, 2016. At that hearing, the plaintiff offered evidence about the projected timeline for the completion of the sewer upgrades and proposed that the defendant approve its application conditioned upon the final completion of all necessary upgrades to the sewer as well as the receipt of necessary wetlands and site plan approvals.

The defendant denied the plaintiff's application on July 27, 2016. The defendant concluded, in relevant part, that (1) the application violated a town policy that purportedly required a positive § 8-24 report from the zoning commission as a prerequisite to proceeding with a sewer extension application; (2) regardless of that policy, § 8-24 itself required a positive report from the zoning commission before the defendant could approve an application unless approval was obtained from the representative town meeting,5 which had not occurred here; and (3) given remaining uncertainties and risks associated with the planned force main replacement and pump station upgrade, it would be unwise for the defendant to issue an approval conditioned upon the plaintiff's agreement to defer construction of the sewer extension until repairs were completed rather than simply requiring the plaintiff to wait and reapply after all necessary repairs and improvements were finished and sufficient capacity existed.

The plaintiff filed an appeal from that ruling with the Superior Court on August 31, 2016. In addition to its supporting brief, the plaintiff filed a motion for permission to supplement the record. The defendant objected to the motion to supplement and later filed its brief opposing the plaintiff's appeal. The plaintiff filed a reply brief and a second motion for permission to supplement the record. The matter was heard on April 26, 2017.

In a decision filed on August 1, 2017, the trial court sustained the plaintiff's appeal. The court determined that the negative report issued by the zoning commission pursuant to § 8-24 was only advisory in nature and in no way was binding on the defendant, and, thus, it had been improper for the defendant to rely primarily on the negative report of the zoning commission as the basis for denying the plaintiff's sewer application, rather than considering the merits of the application.6 Accordingly, the court remanded the application to the defendant "for a new hearing on the matter, at which [the plaintiff] may produce new evidence germane to the equitable disposition of its application."7

On September 27, 2017, the defendant held a hearing in accordance with the court's remand order, which was continued to October 25, 2017. Because the plaintiff's joint venture agreement with the affiliate had terminated, the plaintiff informed the defendant on remand that it was pursuing the application with respect to a new affordable housing plan that consisted of 187 units for which the plaintiff would be the sole developer.8 The plaintiff presented evidence that the construction of the force main replacement and the upgrade to the pump station were scheduled to begin in December, 2017, and were to be completed in March, 2018. The plaintiff also submitted evidence demonstrating that all municipal, state, and federal permits for the sewer construction had issued and that the project was funded fully.

On October 25, 2017, the defendant nevertheless again denied the plaintiff's supplemented sewer extension application. It provided the following reasons for its decision: (1) "[T]he estimated date of completion of the replacement of the force main under the Saugatuck River and the upgrades to Pump Station # 2 is likely to be summer of 2018"; (2) "currently there is not sufficient capacity in the system to accommodate the proposed sewer line extension"; (3) the defendant agreed with Edwards' recommendation "against approving any project, whether conditional or not, that required more capacity than is available"; (4) the defendant, as a matter of policy, had never granted a conditional approval because "[e]vents could occur after a conditional approval that, if known at the time of approval, would have caused an application to be denied or modified," and "[t]here is no reason to grant approvals to extend a sewer prior to the time when the extension can physically be implemented"; (5) "[a]llocation of capacity prior to the completion of necessary work by the town is unfair to other developers and potential users who have been advised to wait until the work is complete to file applications"; (6) "although it is not the function of the [defendant] to consider land use issues in making its decisions (other than to the extent capacity may be affected), the application submitted by the [plaintiff] pursuant to the remand order was substantially different from the application that is the subject of the appeal"; and (7) "[the plaintiff] failed to provide a compelling reason to grant a conditional approval. The [plaintiff's] only stated reason was that it would benefit its ability to plan its project. That reason does not outweigh the public policy reasons for not granting conditional approvals (as set forth in item #4 ...)."

The plaintiff again appealed the denial of its application to the Superior Court, arguing that its property was located in the town's sewer district and, thus, could not be developed without sewer access. The plaintiff further claimed that the record was clear that ample sewer capacity exists or soon would exist for the proposed use, there had been no showing of any engineering impediments to tying into the sewer system, and the sewer extension would be privately funded. According to the plaintiff, on those facts, the defendant had a nondiscretionary duty to grant the sewer extension application or, in the alternative, abused its discretion by failing to do so.

Following briefing, the appeal was heard on April 3, 2018.9 The court again sustained the plaintiff's appeal and reversed the decision of the defendant. In a memorandum of decision filed on May 7, 2018, the court rejected the plaintiff's argument that the defendant had a ministerial duty to grant its extension because the plaintiff did not seek merely to...

To continue reading

Request your trial
3 cases
  • State v. Ward, AC 40534
    • United States
    • Connecticut Court of Appeals
    • 29 Octubre 2019
  • Summit Saugatuck, LLC v. Water Pollution Control Auth. of the Town of Westport
    • United States
    • Connecticut Supreme Court
    • 15 Septiembre 2020
    ...V. Gelderman, Westport, in opposition.The plaintiff's petition for certification to appeal from the Appellate Court, 193 Conn. App. 823, 220 A.3d 183 (2020), is granted, limited to the following issues:"1. Did the Appellate Court correctly determine that the trial court had improperly subst......
  • Summit Saugatuck, LLC v. Water Pollution Control Auth. of the Town of Westport
    • United States
    • Connecticut Supreme Court
    • 14 Enero 2020
    ...of the petition.Peter V. Gelderman, in opposition.The plaintiff's petition for certification to appeal from the Appellate Court, 193 Conn. App. 823, 220 A.3d 183 (2019), is granted, limited to the following issue:"Did the Appellate Court correctly determine that the trial court had improper......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT